As part of their testing programmes at the European Marine Energy Centre (EMEC) in Orkney, Scotland, Alstom's tidal devices have now generated over 1GWh of electricity, in actual operating conditions, to the Scottish grid.

Alstom's 1MW tidal turbine, deployed in 2013 as part of the ReDAPT[1]  project, at EMEC's tidal test site, has demonstrated its endurance, autonomous running and performance, generating at its full nominal power since July 2013.  Previously, the 500 kW tidal stream turbine had already generated electricity into the national grid after its connection In September 2010at the Fall of Warness.

Together, both tidal turbines have therefore produced over 1GWh of power to feed the local grid.