Member access

4-Traders Homepage  >  Shares  >  AUSTRALIAN SECURITIES EXCHANGE LIMITED  >  Atlas Iron Limited    AGO   AU000000AGO1

End-of-day quote. End-of-day quote AUSTRALIAN SECURITIES EXCHANGE LIMITED - 05/24
0.775 AUD   -3.73%
05/15DJBrockman Seeks Access to Fortescue's Pilbara Railway
05/06DJPort Hedland Iron-Ore Exports Rise on Demand from China, Taiwan
04/22 Commodities slump sends slow ripples through world economy
SummaryQuotesChart AnalysisNewsCalendarCompanyFinancialsConsensusRevisionsForum 

Atlas Iron Limited : Atlas to deliver next phase of growth

04/26/2012| 08:43pm US/Eastern
Recommend:
0
27th April 2012 PILBARA'S EMERGING POWERHOUSE TO DELIVER NEXT PHASE OF GROWTH

Atlas Iron Limited (ASX Code: AGO) is pleased to report on its Horizon 1 projects in the north Pilbara. Atlas' continued assessment and development of its DSO projects demonstrates they are amongst the world's most capital efficient iron ore expansion projects.

HIGHLIGHTS

• Mt Dove Mine development to commence June 2012, with production from Dec 2012
• Abydos Mine development to commence May 2012, with production from Apr 2013
• Export rate to grow from 6Mtpa to 10Mtpa from June 2013, increasing to 12Mtpa by Dec 2013
• Low capex cost, in the range of $60-$70 per annualised tonne of incremental installed mine/plant capacity
• Low cash operating cost at 12Mtpa, targeting $47 to $52 / tonne in FY 2014
• Atlas' strong cash position and strong operating cash flows provides ease of financing
• Atlas' Standard Mine Model at Mt Webber (Atlas owned infrastructure, contractor operated) is a precursor for future roll out at McPhee Creek and SE Pilbara DSO projects
Following feasibility work and project development to date, Atlas is pleased to provide an update of its Horizon 1 project objectives and production expansion plans, including:

Phase A - 10Mtpa Export Rate

Status

Total

Capex

Wodgina Mine and Infrastructure

Upgrade

Pit expansions underway and infrastructure construction

approximately 50% complete

$252M

Mt Dove Mine Development

Permitting advanced. Construction commencing from June

2012. Board approved

$252M

Abydos Mine Development

Permitting advanced. Construction commencing from May

2012. Board approved

$252M

Sub total - Phase A

Additional 6Mtpa installed plant capacity

$252M

Phase B - 12Mtpa Export Rate

Mt Webber Mine Development

Pending Board and environmental approvals. Construction to start in Jan 2013. Ramp up to 6Mtpa installed plant

capacity. Atlas owned infrastructure, contractor operated

*$250M

Off-Highway haul road

development - 100km and Utah Point port and Boodarie Link expansions

Grant of tenure for haul road is subject to a Warden's Court

process, the outcome of which may impact on the haul road's alignment and cost, and has delayed road construction. Port construction due to commence in May

2012. Port infrastructure capital funding and operations solutions via 3rd parties, with discussions well advanced

**$170M

Sub total - Phase B

Additional 6Mtpa installed plant capacity

$420M

Total Capex - 12Mtpa

$672M

LessCapex already spent on

Phase A

$42M

Remaining Capex spend

$630M

*- Atlas notional share. Altura Mining owns 30% of the Mt Webber joint venture (southern portion of the Mt Webber deposit) and

therefore notionally owns approx.16% of the combined Mt Webber reserve. An agreement on the joint funding of the Mt Webber DSO

project has yet to be finalised.

**- Provisional estimate, pending final road alignment, port access arrangements and approvals.

"Atlas will deliver massive growth in production and operating cash flows, with globally competitive capital and operating costs," Ken Brinsden, Atlas' Managing Director said. "Expanded mine production is just around the corner with the imminent development of the Mount Dove and Abydos mines".
Further details for the North Pilbara development and production expansions are provided below.

Mine Production Profile Atlas Pilbara Project Locations - Horizons 1 and 2

Atlas' production objectives over the periods comprising the 2013 and 2014 financial years, inclusive of the introduction of new mine production capacity from the Mt Dove, Abydos and Mt Webber mines are indicated below.

14

Mine Production Profile

12

10

Abydos

8

Mount Dove

6

4

Wodgina

2

0 Pardoo

Mount Webber

Jul-12 Jan-13 Jul-13 Jan-14

Cumulative Mine Production Rate

Discrete mine production contribution to total tonnes shipped will vary from quarter to quarter according to the requirements of the Company's mine schedules and operating strategy.
Atlas is targeting cash operating costs to be in the range of $47-$52/tonne at the 12Mtpa production rate in FY 2014.

NORTH PILBARA EXPANSION PROJECTS Wodgina Mine and Infrastructure Upgrade Project

Atlas is pleased to report that the additional pits proposed at the Wodgina Mine have obtained environmental approval and are now under development, including the Dragon and Constellation mining area.
Construction of the infrastructure upgrades at the Wodgina site is now approximately 50% complete.

Wodgina Mine Layout - Showing the Existing Anson Pit and New Mining Areas at Dragon, Constellation and Hercules Mt Dove Mine Development

The Mt Dove Mine delivers additional tonnes and higher grade ore to the Atlas blend. Mt Dove is proposed to be established as a wholly contracted operation, with a mine life of approximately 15 months at a nominal rate of 2Mtpa.
All tenure is established for the project and permitting is well advanced. Major contracts will be awarded within the next month with construction commencing during June 2012 and production from December 2012.

Mount Dove Mine Layout

Abydos Mine Development

The Abydos mine will commence construction from May 2012, with first production and associated haulage to port anticipated from April 2013 at a rate of 2-3 Mtpa.
As a result of ongoing difficulties in establishing tenure (and thereby land access) for the Abydos Mine's haul road access across an existing railway line, Atlas is taking advantage of an alternate haulage route that takes mine production to the North via the Marble Bar road, rather than the initially proposed haulage to the west. The Northern haul road option provides for a haulage distance largely the same as that originally proposed.
Atlas is progressing through a 'Warden's Court' process (the means by which land access disputes are resolved under the Western Australian Mining Act) in relation to an objection received to developing the originally proposed haul road. Atlas will continue to pursue the process of planning and permitting the original haul road to provide an option for future expansion of the Abydos Mine.

Atlas and Venturex agreement on Abydos DSO Project Haul Road

On 26 April 2012, Atlas entered into an agreement with Venturex Resources Limited (Venturex) to establish a Haul Road linking the new Abydos mining operation to the existing sealed Marble Bar Road via Venturex's access road route to the proposed Venturex Sulphur Springs Hub site. Under the agreement, Atlas and Venturex will have shared access and capacity rights to the Haul Road to service and support Atlas' Abydos DSO project and Venturex's proposed Sulphur Springs project. Venturex and Atlas have also agreed to cooperate with each other in relation to investigating the potential for shared development of other infrastructure capacity in the region. This is currently Atlas' preferred haulage route for the Abydos project.

Abydos Mine Layout Mount Webber Mine Development

The Mt Webber Mine will ramp up to 6Mtpa (subject to the completion of the Off-Highway haul road development - see Off-Highway Haul Road Development section below) utilising a fixed crushing and screening plant to be owned by Atlas and operated by contractors.
The final infrastructure to support up to 6Mtpa will be installed as per the Atlas' 'Standard Mine Model', within which infrastructure capacity is installed in 5-6Mtpa modules for the Mt Webber mine and subsequent mine developments at McPhee Creek and the South East Pilbara projects. Atlas intends to utilise the existing mining contractor model for mining operations.
The standard mine model will use the principle that the infrastructure is designed once and rolled out at each new mining location. Under this approach infrastructure design, construction and site delivery costs will be reduced, contributing to overall lower costs of development and faster mine site construction.

Mount Webber Mine Layout

Off Highway Haul Road Development

In light of the progress being made with respect to rail haulage solutions, the off-highway haul road will now be built from Wodgina to Port Hedland, a distance of approximately 100km. Initial estimates for the likely combined off-highway haul road capacity will be up to 15Mtpa pending the various combinations of individual production from the contributing mines.
Grant of tenure for the off-highway haul road is subject to a Warden's Court process. The outcome of this process may have an impact on the road's alignment and therefore cost. Furthermore the ramp up of mine production capacity at Mt Webber to achieve 12Mtpa from 10Mtpa has been delayed to December 2013 as a result of the abovementioned Warden's Court process.

Utah Point Port and Boodarie Link expansions

Since commissioning of the Utah Point Port in September 2010, Atlas' confidence in the ability of the port to deliver and sustain Atlas' expansion objectives has increased. As a result, Atlas will now look to further incrementally expand facilities at the Port to support expanded mine production. This will require further investment in Utah Point by Atlas and its contractors, in developing expanded landside facilities.
These facilities include upgrades within the Yard 2 land area, including; more sophisticated stacking and reclaiming infrastructure, and ultimately the interconnection of Yard 2 facilities to the terminal of the off-highway haul road solution in the Boodarie Industrial Estate.
Discussions on infrastructure capital funding and operations solutions with third parties are well advanced.

Further enquiries please contact

Ken Brinsden, Managing Director Tel: +618 9476 7900
Mark Hancock, Chief Commercial Officer

Production and Shipping Targets

The production and shipping targets for Atlas' DSO projects are subject to the completion of all necessary feasibility studies, environmental permitting, port access, financing arrangements, execution of infrastructure related agreements, necessary agreements with joint venture parties and timely project construction

distributed by
Recommend :
0
Partner Area
React to this article
 
Latest news on ATLAS IRON LIMITED
05/15DJBrockman Seeks Access to Fortescue's Pilbara Railway
05/06DJPort Hedland Iron-Ore Exports Rise on Demand from China, Taiwan
04/22 Commodities slump sends slow ripples through world economy
04/04DJAustralia Rail Study Shows Benefits of New Pilbara Network
04/02DJMARKET COMMENT: S&P/ASX 200 May Rise As Dividend Payments Flow
03/27DJBrockman, Partners See Pilbara Rail Project Plans Firming Up by June
03/07 ATLAS IRON LIMITED: Change of Share Registry
03/06DJAustralia Port Hedland Feb Iron Ore Exports Down 9.9% at 19.9 Million Tons
02/28DJAustralian Ports, Energy Facilities Reopen After Cyclone
02/27DJAustralian Ports, Energy Facilities Reopen After Cyclone Rusty
Advertisement
Chart
Duration : Period :
Atlas Iron Limited Technical Analysis Chart | AGO | AU000000AGO1 | 4-Traders
Income Statement Evolution
Atlas Iron Limited : Income Statement Evolution
More Financials
Dynamic quotes  
ON
| OFF
Copyright © 2013 Surperformance. All rights reserved.