News date: December 18, 2014

The value of the contract amounts to around PLN 27 million net.
The subject matter of the contract includes design, deliveries, assembly and launch of the new peak load boiler in the scope of Balance of Plant (without the delivery of boilers, flue gas ducts and chimney).

The scope of works shall include:

  • light fuel oil inflow installation along with adaptation of the existing tank,
  • system of thermal power output from the new boilers along with the delivery of equipment,
  • electrical installation,
  • the Control and Measurement Instruments and Automation installation, including CEMS (continuous emissions monitoring system),
  • construction works,
  • fire protection system,

as well as the start-up of equipment and staff training.
It is yet another energy contract of Budimex this year. In July, the company concluded a contract for the construction of a new power generating unit of net electrical capacity of 450 MWe (megawatts of electric power) at the Power plant in Turów. The project worth PLN 3,250 million net is carried out by Budimex in a consortium with Mitsubishi Hitachi Power Systems Europe GmbH (consortium leader, with 55.38% of shares) and Tecnicas Reunidas SA (consortium partner, with 22.31% of shares).
On 8 December 2014 PGNiG Termika SA settled the tender for the delivery and assembly of the flue denitriding plant and the modernisation of the desulphurisation plant for the K2 boiler at the Electrical Power and Heating Plant in Siekierki. The lowest bid (PLN 62.9 million net) was made by the consortium of Andritz Energy & Environment GmbH (leader, 49 per cent) and Budimex SA (partner, 51 per cent).
Meanwhile, the company is also searching for other power supply-related contracts. It has been analysing planned projects thoroughly and has made a bid in various tender procedures in the energy industry. As a consequence, Budimex plans to increase its headcount of power supply sector specialists.