CCCC Guangzhou Dredging Co., Ltd. has recently won the bid for the Phase 2 extension works of the channel dredging project in Tieshan zone of Beihai Port in Guangxi, with a total dredging volume of 24 million cubic meters, a contract value of 730 million yuan and a construction period of 9 months.

With a full length of some 18.7 kilometers, a designed effective width of 190-330 meters and a designed bottom elevation of -14.0--14.7 meters, the project involves temporary cofferdam works in the reclamation zone, dredging and reclamation works in the temporary silt storage pit, channel dredging, navigation and navigation aid works, etc.

After its completion, the project will better meet the needs of the rapid growth of the cargo handling capacity of Beihai's coastal ports, ship upsizing and harbor industry development, and be conducive to further enhancing Beihai's competitiveness.