Chubu Electric Power's schedule for transport of new fuel, spent fuel and low-level radioactive waste at the Hamaoka Nuclear Power Station in FY2017 is as follows.
The Schedule of these shipments is subject to change in future.
1 New fuel
No current plans
2 Spent fuel
No current plans
3 Low-level radioactive waste
Power plant name | Quantity shipped | Period of shipment | Receiving facility |
---|---|---|---|
Hamaoka Nuclear Power Station | Transport containers:80 (640 drums) | May 2017 |
Japan Nuclear Fuel Limited |
Hamaoka Nuclear Power Station | Transport containers:156 (1,248 drums) | June 2017 |
Japan Nuclear Fuel Limited |
Transportation of low-level radioactive waste in May 2017 was scheduled for fiscal year 2016, but it's brought forward.
Chubu Electric Power Co. Inc. published this content on 31 March 2017 and is solely responsible for the information contained herein.
Distributed by Public, unedited and unaltered, on 25 April 2017 01:16:01 UTC.
Original documenthttp://www.chuden.co.jp/english/corporate/ecor_releases/erel_pressreleases/3264048_18939.html
Public permalinkhttp://www.publicnow.com/view/02CCA841A3F44E4BBD08A2C4C1D6A03E7DCACAB8