ACTIVITIES AND CASHFLOW REPORT

13 November 2017

ASX/MEDIA RELEASE

ASX: CSD Share Price: $0.025 (in trading halt) ABN: 57 126 634 606

TIN M IN ES LIM ITED

SEPTEMBER 2017 QUARTER ACTIVITIES REPORT

QUARTERLY ACTIVITIES OVERVIEW

  • Recommenced mining at the Mt Garnet underground mine on 5 July 2017 with first ore delivered to the ROM on 6 July.

  • Dewatering of the lower levels of Mt Garnet underground mine completed in July.

  • Completed the Mt Garnet Mill refurbishment and commissioning and commenced concentrate production on 24 July.

  • Development work continued at the Dry River South (DRS) project, located 180km south of Mt Garnet at the Surveyor Mine, including:

    • Commissioning of the cased dewatering bore, including a new poly pipeline from the bore to the Balcooma pit, providing the infrastructure necessary to dewater the DRS mine.

    • Establishment of access to the DRS Portal.

    • Commencement of refurbishment of the DRS decline. Once completed, the decline will provide access to the upper production zones of DRS with production from DRS scheduled to commence early next year.

  • Released an updated JORC Resource for Chloe and Jackson deposits at Einasleigh of 3Mt @ 5.3% Zn.

  • Dismissal of Baal Gammon Copper's ("BGC") legal claim against the Company with BGC required to pay costs.

  • $1.8m payable to BGC under the Baal Gammon settlement agreement paid in full.

    SUBSEQUENT TO QUARTER END

  • Commenced trucking of concentrate to Townsville port in October.

  • Released an updated JORC Resource for the Kaiser Bill deposit at Einasleigh of 15.5Mt @ 0.93% Cu.

  • Announced CSD's "Company Roadmap Towards 2021" setting out a 4 year plan to maximise the value of the Company's projects (refer announcement dated 1 November 2017).

CONSOLIDATED TIN MINES LIMITED Page 1 of 5

Cairns Corporate Headquarters: 395 Lake Street, Cairns Qld 4870 Phone: +61 (7) 4032 3319

Email: info@csdtin.com.au Web: www.csdtin.com.au

OPERATIONS

The Company completed dewatering the Mt Garnet underground mine in July 2017 and recommenced underground mining operations on 5 July 2017, with first ore delivered to the ROM on 6 July 2017.

The Mt Garnet processing plant refurbishment and commissioning has been completed with the first concentrate produced on 24 July 2017. Transporting of concentrate to Townsville Port and sale to an offtake partner began during October.

Base Metal Production for the September quarter

Ore processed

35,938

tonnes

Mill feed grade Zn

2.77

%

Mill feed grade Cu

0.38

%

Zn recovery

73.33

%

Cu recovery

67.73

%

Zn metal produced in concentrate

758

tonnes

Cu metal produced in concentrate

103

tonnes

Construction of a cased dewatering bore hole at the DRS project was completed in July 2017. A specialist submersible pump has been fitted at the bottom of the bore hole and is being used to transfer water from the DRS underground mine to the Balcooma pit, with progress on schedule. Dewatering of the upper levels of the DRS mine is complete.

The Surveyor in-pit dump has been reshaped to allow access to the historic DRS portal. Refurbishment of the DRS portal has been completed and refurbishment of the DRS decline is underway. Production from the upper levels of the DRS mine is scheduled to commence later this year.

EXPLORATION

Drilling at the Einasleigh Project is continuing with drilling programs underway at the Chloe, Jackson and Kaiser Bill Prospects (three separate drill rigs). These programs are part of the Company's focused exploration strategy to develop new base metal resources to underpin future production. Drill results from the Chloe drilling program were announced to the market 20 September and analysis of this data resulted in successful identification of extension potential of the known mineralisation footprint.

The following updated JORC Resource were recently announced to the ASX:

Chloe and Jackson

3Mt @ 5.3% Zn

announced 19 September

Kaiser Bill

15.5Mt @ 0.93% Cu

announced 17 October

The Company has also continued its exploration program targeting additional base metal resources that can be economically transported to the Mt Garnet processing plant, including:

  • Completion of the second stage of drilling at the Mt Garnet Deeps project, with a third stage of drilling to be completed during the December quarter. Results of the Stage 2 drilling program were reported in the ASX announcement dated 10 July 2017. The Mt Garnet Deeps Project is a conceptual target parallel to the Mt Garnet underground mine and is being assessed with primary focus on the

    economic viability of Area 1 (refer to the 10 July 2017 announcement for further details). A decision on developing this area will be made by the board during the December quarter.

  • RC drilling of the Kingston and Clinker projects and the Balcooma deposit, all located near the Surveyor Mine.

  • Drilling of the Gillian Zinc prospect, located 9 km south of Mt Garnet, which is targeting potential Zinc at depth beneath the Gillian tin project.

  • Drilling of a multi-element (Pb, Zn, As, Cu) soil anomaly at the Nanyetta prospect, located three kilometres along strike to the north of the Mt Garnet mine.

The Company completed due diligence on the Muldiva prospect (refer CSD's ASX announcements dated 19 July and 30 October 2017). The results of this work indicated a potential prospect though did not meet the Company's expectation to add the anticipated tonnes and grade of ore to the Mt Garnet mill in a short timeframe and consequently the Board decided not to proceed with this acquisition.

CORPORATE

BGC's legal claim against the Company has been dismissed and BGC have been ordered to pay costs. Prior to this verdict the Company completed its obligation to pay $1.8m to BGC under the Baal Gammon settlement agreement.

The Company's audited financial statements for the year ended 30 June 2016 were lodged with ASX on 18 July 2017 and the December 2016 half-year financial statements were lodged on 17 August 2017. Quarterly reports for June, September & December 2016 and March 2017 were lodged on 18 August 2017 and the June 2017 Quarterly report was lodged on 25 August. The audit of the Company's 30 June 2017 financial statements is expected to be completed during the December quarter. The Directors will keep shareholders informed of any developments relating to the reinstatement to trading on ASX through the issue of further Company announcements as soon as further information becomes available.

CASH RESERVES & LOAN FACILITIES

The Company had $651,185 in cash reserves at the end of the September 2017 quarter.

As reported in the March 2017 Quarterly Activities Report dated 18 August 2017, Cyan Stone Pty Ltd (Cyan) has agreed to provide the Company with pre-payments of the subscription funds to fund the Company's working capital requirements and exploration activities. Whilst this is not a loan facility, should shareholders not approve the issue of shares to Cyan, the amounts prepaid will be converted into an interest-bearing loan.

For further information, please contact:

Cairns Corporate Headquarters Phone: +61 (7) 4032 3319

Website: www.csdtin.com.au Email: admin@csdtin.com.au

The company confirms that it is not aware of any new information or data that materially affects the information included in the original market announcements and, in the case of estimates of Mineral Resources or Ore Reserves, that all material assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to apply and have not materially changed.

Table 1: Schedule of Tenements as at 30 September 2017

Registered Holder

Tenement No.

Tenement Name

Interest at start of quarter

Interest at end of quarter

Status

Consolidated Tin Mines

MDL 38

Gillian

100%

100%

Granted

MDL 381

Windermere

100%

100%

Granted

MDL 448

Herberton Deep Lead

100%

100%

Granted

MDL 482

Jeannie River

100%

100%

Granted

EPM 14185

Mt Garnet

100%

100%

Granted

EPM 15611

Lynd River

100%

100%

Granted

EPM 17073

Mt Garnet Extended

100%

100%

Granted

EPM 17547

Tate River Extended

100%

100%

Granted

EPM 17623

Mt Garnet West

100%

100%

Granted

EPM 17753

Mt Garnet Nth West

100%

100%

Granted

EPM 17875

Lynd River Extended

100%

100%

Granted

EPM 17917

Smith's Creek Extended

100%

100%

Granted

EPM 18000

Mt Garnet East

100%

100%

Granted

EPM 18118

Bolwarra

100%

100%

Granted

EPM 18321

Mt Garnet South

100%

100%

Granted

EPM 18795

Gillian

100%

100%

Granted

EPM 19105

Jimbilly North

100%

100%

Granted

EPM 19204

Nettle Creek South

100%

100%

Granted

EPM 19323

Kangaroo Creek

100%

100%

Granted

EPM 19468

Jeannie River Extended

100%

100%

Granted

EPM 19603

Dinner Creek

100%

100%

Granted

EPM 25386

Spring Creek

100%

100%

Granted

EPM 25427

Nettle Creek

100%

100%

Granted

EPM 25428

Reedy Creek

100%

100%

Granted

EPM 25689

Twelve Mile

100%

100%

Granted

EPM 25702

Soda

100%

100%

Granted

EPM 25711

Brownville

100%

100%

Granted

EPM 25939

Torwood

100%

100%

Granted

EPMA 26087

Einasleigh Extended

0%

0%

Application

EPMA 26540

Silver Valley

0%

0%

Application

EPMA 26635

Einasleigh Upper

0%

0%

Application

MLA 20583

Mid Battle Creek

0%

0%

Application

MLA 20584

Nettle Creek Extended

0%

0%

Application

MLA 20585

Upper Battle Creek

0%

0%

Application

MLA 20693

Pinnacles

0%

0%

Application

MLA 20694

Windermere

0%

0%

Application

ML 20743

Gillian

100%

100%

Granted

MLA 100022

Maitland

0%

0%

Application

Registered Holder

Tenement No.

Tenement Name

Interest at start

Interest at end

Status

CTM Alluvial Pty Ltd

EMPA 26453

Lynd Regional

0%

0%

Application

ML 4069

Nettle Creek

100%

100%

Granted

ML 4073

Nettle Creek

100%

100%

Granted

ML 4074

Nettle Creek

100%

100%

Granted

MLA 20721

Kangaroo Creek

0%

0%

Application

MLA 20722

Martins Terrace

0%

0%

Application

MLA 20723

Martins Hill

0%

0%

Application

MLA 100023

Boomerang

0%

0%

Application

Consolidated Tin Mines Limited published this content on 16 November 2017 and is solely responsible for the information contained herein.
Distributed by Public, unedited and unaltered, on 15 November 2017 21:29:08 UTC.

Original documenthttp://www.csdtin.com.au/wp-content/uploads/2017/11/September-2017-Quarterly-Actiities-and-Cashflow-Report.pdf

Public permalinkhttp://www.publicnow.com/view/FD82D26095A485C26918AB90BE811DB1002E8D17