SCPX Project has successfully achieved major contract milestones with Mechanical Completion and Hand Over of the facilities to Client at Compressor Station Georgia #1 (CSG-1) and Metering Station (Area-81) worksites. Currently, final completion works are on-going in parallel to commissioning support activities for both worksites.

Meanwhile, Compressor Station Georgia #2 (CSG-2) is well on track with 77% progress and reaching its peak manpower of 1,800.

Overall, SCPx Project has reached 88% completion by the end of August-2017.