At ENKA's Samawa CCPP, located in Iraq, mobilization activities started in August 2017 after the soil investigation works had finished. As the end of May 2018, all erection works were completed and the mobilization realization rate of %85 was achieved, only architectural and electrical works of some buildings are remaining.

The perimeter wall that was a very critical milestone for security and safe works of the site was finished on January 5th, 2018. By the end of May 2018, 13,997 meters bored piles were installed and reached %20 of total quantities.

Up to date 550,000 man-hours were worked without lost time incident (LTI).