Letter

to shareholders

January, 2014
Progress update of the CHO Morcenx power plant.
As indicated in our previous letter to Shareholders, the gasifier is erected on its structure since
21/11/2013 and the connections to the auxiliaries (Turboplasma, boiler…etc) are being finalized. Work is continuing on schedule and budget.

Achievements of December, 2013