Exxon Torrance 155.0 Several units will be shut for
Mobil CA planned maintenance, including
hydrogen, coker and pretreater
starting June 4. Work will take
several weeks to complete, the
co. said on June 4.
Shell Martinez 156.4 Scheduled work (unspecified)
CA is underway, the co. said on
Apr 27. Traders said crude and
coker unit involved; end date
not provided.
Tesoro Martinez 166.0 Hydrocracker has been shut for May 11-
CA two weeks of maintenance, traders 13
said on May 2.
Tesoro Wilmington 97.0 Planned maintenance underway at
CA unspecified units, the co. said
on June 6. No restart estimate.