FAIRMONT, W.Va., Aug. 22, 2016 -- To help enhance service reliability for customers, FirstEnergy Corp. (NYSE: FE) is continuing construction work this summer and throughout the remainder of 2016 on distribution and transmission infrastructure projects totaling approximately $238 million in Mon Power's 34-county West Virginia service area.

To date, more than $150 million of the total has been spent on transmission enhancements to reinforce the system and support economic growth, along with constructing new distribution lines and inspecting and replacing utility poles and other equipment.

'Each year we carefully review and plan transmission and distribution projects that will enhance service to our customers while also preparing our system for future load growth,' said Holly Kauffman, president of FirstEnergy's West Virginia operations. 'By doing proactive upgrades, we focus on the reliability and resiliency of our system with the goal of reducing the duration and frequency of service interruptions.'

FirstEnergy projects completed, underway or planned in the Mon Power footprint in 2016 include:

  • Completing construction on a new 138-kilovolt (kV) transmission line that will support the natural gas industry and enhance electric service reliability for nearly 13,000 Mon Power customers in the Clarksburg and Salem areas. The 18-mile transmission line will be energized later this year and connects substations in Clarksburg and Waldo Run. About $46 million of the $83 million project will be spent in 2016.
  • Constructing a new transmission substation near Smithfield, W.Va., to meet the electrical needs of a nearby gas processing facility expanding its operations. The $76 million project includes building a two-mile transmission line to connect the new substation with the plant. The project is scheduled to be operational by year's end, with about $44 million spent on the project in 2016. Additionally, the project should enhance service reliability for more than 6,000 Mon Power customers in Wetzel, Marion and Tyler counties.
  • Building a new substation and two new, three-mile power lines near Greenwood, W. Va., at a cost of about $5 million to provide electrical service to a fracking water treatment plant to be constructed in Doddridge County. The project should be complete and in-service by mid-2016.
  • Adding a second transformer at a cost of $700,000 to a substation near Cassville, W. Va., to enhance service reliability for nearly 2,000 customers in western Monongalia County.
  • Providing electrical service to new residential and commercial customers in north-central West Virginia, specifically the Interstate-79 corridor and Parkersburg region, at a cost of more than $23 million.
  • Upgrading and replacing equipment on distribution circuits throughout the service territory at an expected cost of more than $6 million. The updates - including installing new wire, cable and fuses - are expected to enhance reliability for Mon Power customers.
  • Inspecting about 22,000 distribution poles and replacing about 260 poles at an expected cost of more than $1.6 million.

About $88 million of the budgeted total will be for transmission-related projects owned by the Trans-Allegheny Interstate Line Company (TrAILCo), a FirstEnergy transmission affiliate.

Mon Power, a FirstEnergy electric distribution company, serves about 385,000 customers in 34 West Virginia counties. Follow Mon Power on Twitter @MonPowerWV.

FirstEnergy is dedicated to safety, reliability and operational excellence. Its 10 electric distribution companies form one of the nation's largest investor-owned electric systems, serving customers in Ohio, Pennsylvania, New Jersey, West Virginia, Maryland and New York. The company's transmission subsidiaries operate more than 24,000 miles of transmission lines that connect the Midwest and Mid-Atlantic regions. Visit FirstEnergy online at www.firstenergycorp.com and follow on Twitter at @FirstEnergyCorp.

Editor's Note: Photos of service reliability work being done in the Mon Power area are available for download on Flickr.

Forward-Looking Statements: This news release includes forward-looking statements based on information currently available to management. Such statements are subject to certain risks and uncertainties. These statements include declarations regarding management's intents, beliefs and current expectations. These statements typically contain, but are not limited to, the terms 'anticipate,' 'potential,' 'expect,' 'forecast,' 'target,' 'will,' 'intend,' 'believe,' 'project,' 'estimate,' 'plan' and similar words. Forward-looking statements involve estimates, assumptions, known and unknown risks, uncertainties and other factors that may cause actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements, which may include the following: the speed and nature of increased competition in the electric utility industry, in general, and the retail sales market in particular; the ability to experience growth in the Regulated Distribution and Regulated Transmission segments; the accomplishment of our regulatory and operational goals in connection with our transmission investment plan, including, but not limited to, the proposed transmission asset transfer to Mid-Atlantic Interstate Transmission, LLC, and the effectiveness of our strategy to reflect a more regulated business profile; changes in assumptions regarding economic conditions within our territories, assessment of the reliability of our transmission system, or the availability of capital or other resources supporting identified transmission investment opportunities; the impact of the regulatory process and resulting outcomes on the matters at the federal level and in the various states in which we do business including, but not limited to, matters related to rates and the Electric Security Plan IV; the impact of the federal regulatory process on Federal Energy Regulatory Commission (FERC)-regulated entities and transactions, in particular FERC regulation of wholesale energy and capacity markets, including PJM Interconnection, L.L.C. (PJM) markets and FERC-jurisdictional wholesale transactions; FERC regulation of cost-of-service rates, including FERC Opinion No. 531's revised Return on Equity methodology for FERC-jurisdictional wholesale generation and transmission utility service; and FERC's compliance and enforcement activity, including compliance and enforcement activity related to North American Electric Reliability Corporation's mandatory reliability standards; the uncertainties of various cost recovery and cost allocation issues resulting from American Transmission Systems, Incorporated's realignment into PJM; economic or weather conditions affecting future sales and margins such as a polar vortex or other significant weather events, and all associated regulatory events or actions; changing energy, capacity and commodity market prices including, but not limited to, coal, natural gas and oil prices, and their availability and impact on margins and asset valuations, including without limitation impairments thereon; the risks and uncertainties at the CES segment, including FES, related to continued depressed wholesale energy and capacity markets, including the potential need to deactivate or sell additional generating units; the continued ability of our regulated utilities to recover their costs; costs being higher than anticipated and the success of our policies to control costs and to mitigate low energy, capacity and market prices; other legislative and regulatory changes, and revised environmental requirements, including, but not limited to, the effects of the United States Environmental Protection Agency's Clean Power Plan, Coal Combustion Residuals regulations, Cross-State Air Pollution Rule and Mercury and Air Toxics Standards programs, including our estimated costs of compliance, Clean Water Act (CWA) waste water effluent limitations for power plants, and CWA 316(b) water intake regulation; the uncertainty of the timing and amounts of the capital expenditures that may arise in connection with any litigation, including New Source Review litigation, or potential regulatory initiatives or rulemakings (including that such initiatives or rulemakings could result in our decision to deactivate or idle certain generating units); the uncertainties associated with the deactivation of certain older regulated and competitive fossil units, including the impact on vendor commitments, such as long-term fuel and transportation agreements, and as it relates to the reliability of the transmission grid, the timing thereof; the impact of other future changes to the operational status or availability of our generating units and any capacity performance charges associated with unit unavailability; adverse regulatory or legal decisions and outcomes with respect to our nuclear operations (including, but not limited to, the revocation or non-renewal of necessary licenses, approvals or operating permits by the Nuclear Regulatory Commission or as a result of the incident at Japan's Fukushima Daiichi Nuclear Plant); issues arising from the indications of cracking in the shield building at Davis-Besse; the risks and uncertainties associated with litigation, arbitration, mediation and like proceedings, including, but not limited to, any such proceedings related to vendor commitments, such as long-term fuel and transportation agreements; the impact of labor disruptions by our unionized workforce; replacement power costs being higher than anticipated or not fully hedged; the ability to comply with applicable state and federal reliability standards and energy efficiency and peak demand reduction mandates; changes in customers' demand for power, including, but not limited to, changes resulting from the implementation of state and federal energy efficiency and peak demand reduction mandates; the ability to accomplish or realize anticipated benefits from strategic and financial goals, including, but not limited to, the ability to continue to reduce costs and to successfully execute our financial plans designed to improve our credit metrics and strengthen our balance sheet through, among other actions, our cash flow improvement plan and other proposed capital raising initiatives; our ability to improve electric commodity margins and the impact of, among other factors, the increased cost of fuel and fuel transportation on such margins; changing market conditions that could affect the measurement of certain liabilities and the value of assets held in our Nuclear Decommissioning Trusts, pension trusts and other trust funds, and cause us and/or our subsidiaries to make additional contributions sooner, or in amounts that are larger than currently anticipated; the impact of changes to material accounting policies; the ability to access the public securities and other capital and credit markets in accordance with our financial plans, the cost of such capital and overall condition of the capital and credit markets affecting us and our subsidiaries; actions that may be taken by credit rating agencies that could negatively affect us and/or our subsidiaries' access to financing, increase the costs thereof, and increase requirements to post additional collateral to support outstanding commodity positions, letters of credit and other financial guarantees; changes in national and regional economic conditions affecting us, our subsidiaries and/or our major industrial and commercial customers, and other counterparties with which we do business, including fuel suppliers; the impact of any changes in tax laws or regulations or adverse tax audit results or rulings; issues concerning the stability of domestic and foreign financial institutions and counterparties with which we do business; the risks associated with cyber-attacks and other disruptions to our information technology system that may compromise our generation, transmission and/or distribution services and data security breaches of sensitive data, intellectual property and proprietary or personally identifiable information regarding our business, employees, shareholders, customers, suppliers, business partners and other individuals in our data centers and on our networks; and the risks and other factors discussed from time to time in our United States Securities and Exchange Commission (SEC) filings, and other similar factors. The foregoing factors should not be construed as exhaustive and should be read in conjunction with the other cautionary statements and risks that are included in our filings with the SEC, including but not limited to the most recent Annual Report on Form 10-K and any subsequent Quarterly Reports on Form 10-Q. New factors emerge from time to time, and it is not possible for management to predict all such factors, nor assess the impact of any such factor on our business or the extent to which any factor, or combination of factors, may cause results to differ materially from those contained in any forward-looking statements. FirstEnergy expressly disclaims any current intention to update, except as required by law, any forward-looking statements contained herein as a result of new information, future events or otherwise.

FirstEnergy Corporation published this content on 22 August 2016 and is solely responsible for the information contained herein.
Distributed by Public, unedited and unaltered, on 22 August 2016 19:19:03 UTC.

Original documenthttps://www.firstenergycorp.com/newsroom/news_releases/-238-million-in-infrastructure-projects-planned-in-mon-power-are.html

Public permalinkhttp://www.publicnow.com/view/67A00657A5253D08651C9E5C3360B279004BD1DA