f5128fec-dd63-4d93-be2e-e352a03b372d.pdf



Quarterly Report

For the quarter ending 30 September 2015


HIGHLIGHTS

  • PIOP Option and Sale Agreement with Todd Corporation rejected by shareholders at general meeting on 24 September 2015


  • Ongoing discussions with Todd Corporation prior to the expiry of the Alliance Agreement on 31 December 2015


  • Follow-up exploration completed at the Canegrass Project in WA


WA

Pilbara Iron Ore Project

Tom Price

CORPORATE

Magnet

Canegrass Gold Project

Todd Transaction

On 11 May 2015, Flinders Mines announced it had signed an Option and Sale Agreement with a

subsidiary of New Zealand's Todd Corporation for the 100% sale of Flinders' Pilbara Iron Ore Project (PIOP) (refer to ASX announcement dated 11/05/2015). This proposed transaction was rejected by shareholders at a general meeting held in Adelaide on 24 September 2015.


Future Outlook

The Company continues to hold meetings with Todd Corporation to discuss adding further value to the project within the framework of the existing Alliance Agreement. If no beneficial outcome is agreed by

31 December 2015, then Flinders will commence discussions with other parties in respect to developing the project.

Flinders also plans to reinvigorate its discussions with Chinese steel mills in respect to finalising offtake agreements and potential project investment.



Corporate Costs

The Company has completed a number of cost reduction measures during the quarter including a significant reduction in staff numbers and other corporate costs. The Directors, including the

Managing Director, have agreed to reduce their fees and salary by 20% from 1 November 2015.


PROJECTS

Pilbara Iron Ore Project (PIOP) - WA

During the quarter, the Company received approval from the Environment Minister in Western Australia for the expanded project. Further assessments and approvals are progressing with the State Minister for Aboriginal Affairs and the Federal Government.



EXPLORATION AND EVALUATION ACTIVITIES

WESTERN AUSTRALIA

Pilbara Iron Ore Project

There were no exploration and evaluation activities carried out on the Company's Pilbara Iron Ore Project tenements during the September 2015 quarter.


Canegrass Gold Project

During the quarter a small follow up air-core (AC)


118°

-28°

Mt Magnet


Project Area Prospect Homestead

0 10 km


Challa HS


Mt Magnet -

118°30'

Sandstone Rd

Honeypot

E58/236


E58/282 E58/232

drilling program was undertaken at the Honeypot gold prospect (Figure 1). A total of 31 holes for 428m were drilled (Figure 2 and Table 1).

The drilling was designed to cover the intersection of a major shear zone and a secondary fault to the

north of a significant intersection of 8m @ 2.03 g/t Au from 12m in hole HAC022 drilled earlier this year. Hole HAC022 is located at the northern end of a trend of

Figure 1 : Canegrass Gold Project is located approximately 60km SE from Mt Magnet, Western Australia.


Target

Zone

Felsic

anomalous holes that intersected a deformed and foliated mafic schist as well as late stage undeformed granitic dykes and quartz veining.

Dyke

All assays from the current round of drilling have


Zone

HAC022

6,868,000 mN

now been received and there were no significant intersections.


SOUTH AUSTRALIA

There were no exploration and evaluation activities carried out on the Company's South Australian tenements during the September 2015 quarter.


Ian Gordon Managing Director 30 October 2015


Fault

E58/236 E58/282


0 200 m

8m @ 2.01 g/t Au


Anomalous Zones


6,867,000 mN


AC drillhole - Aug 2015 AC drillhole - Mar 2015

639,000 mE

640,000 mE

Shear

Figure 2 : Honeypot prospect AC drillholes over ground TMI (magnetic) image.

Contact us Ian Gordon

Managing Director

Ph: (08) 8132 7950

Email: info@flindersmines.com


Investor Relations Duncan Gordon

Executive Director - Adelaide Equity Partners

Ph: (08) 8232 8800 or 0404 006 444

Email: dgordon@adelaideequity.com.au


Head Office

Level 1, 135 Fullarton Road Rose Park

South Australia 5067


PO Box 4031

Norwood South South Australia 5067


Ph: (08) 8132 7950

Fax: (08) 8132 7999

Email: info@flindersmines.com

www.flindersmines.com



Qualifying Statements


Forward-looking statements

This release may include forward-looking statements. These forward- looking statements are based on management's expectations and beliefs concerning future events as of the time of the release of this document. Forward-looking statements are necessarily subject to risks, uncertainties and other factors, some of which are outside the control of Flinders Mines Limited, that could cause actual results to differ materially from such statements. Flinders Mines Limited makes no undertaking to subsequently update or revise the forward-looking statements made in this release to reflect events or circumstances after the date of this release.

Competent Persons

The information in this report that relates to Exploration Targets, Exploration Results, or Mineral Resources is based on information compiled by Dr Graeme McDonald who is a member of the Australian Institute of Mining and Metallurgy and a full-time employee of Flinders Mines Limited. Graeme McDonald has sufficient experience that is relevant to the styles of mineralisation and types of deposits under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Graeme McDonald consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

Table 1 : Summary of Honeypot Prospect aircore holes drilled in August 2015.


Hole ID

Prospect

Tenement

Easting (MGA z50)

Northing (MGA z50)

RL

(m)

Dip

Azimuth

Total Depth (m)

HAC108

Honeypot

E58/282

6867843

639464

460

-90

0

13

HAC109

Honeypot

E58/282

6867846

639365

460

-90

0

21

HAC110

Honeypot

E58/282

6867832

639263

460

-90

0

26

HAC111

Honeypot

E58/282

6867942

639567

460

-90

0

9

HAC112

Honeypot

E58/282

6867953

639518

460

-90

0

5

HAC113

Honeypot

E58/282

6867951

639465

460

-90

0

10

HAC114

Honeypot

E58/282

6867952

639415

460

-90

0

56

HAC115

Honeypot

E58/282

6867955

639364

460

-90

0

15

HAC116

Honeypot

E58/282

6867949

639319

460

-90

0

10

HAC117

Honeypot

E58/282

6867951

639267

460

-90

0

10

HAC118

Honeypot

E58/282

6868042

639564

460

-90

0

4

HAC119

Honeypot

E58/282

6868044

639515

460

-90

0

18

HAC120

Honeypot

E58/282

6868051

639463

460

-90

0

14

HAC121

Honeypot

E58/282

6868056

639413

460

-90

0

16

HAC122

Honeypot

E58/282

6868059

639362

460

-90

0

4

HAC123

Honeypot

E58/282

6868053

639317

460

-90

0

18

HAC124

Honeypot

E58/282

6868054

639264

460

-90

0

2

HAC125

Honeypot

E58/282

6868149

639564

460

-90

0

3

HAC126

Honeypot

E58/282

6868148

639517

460

-90

0

2

HAC127

Honeypot

E58/282

6868152

639466

460

-90

0

4

HAC128

Honeypot

E58/282

6868152

639417

460

-90

0

14

HAC129

Honeypot

E58/282

6868148

639365

460

-90

0

10

HAC130

Honeypot

E58/282

6868143

639318

460

-90

0

4

HAC131

Honeypot

E58/282

6868252

639559

460

-90

0

10

HAC132

Honeypot

E58/282

6868244

639516

460

-90

0

22

HAC133

Honeypot

E58/282

6868249

639465

460

-90

0

30

HAC134

Honeypot

E58/282

6868247

639415

460

-90

0

12

HAC135

Honeypot

E58/282

6868242

639364

460

-90

0

13

HAC136

Honeypot

E58/282

6868243

639346

460

-90

0

11

HAC137

Honeypot

E58/282

6868258

639316

460

-90

0

16

HAC138

Honeypot

E58/282

6868257

639342

460

-90

0

26

distributed by