FGC UES (included in Rosset Group) completed the technological connection of the oil and gas facilities of Salym Petroleum Development N.V. to the Unified National Electricity Grid. The capacity that can be provided to the company increased from 36 to 96 MW.

Power engineers expanded the open switchgear of the 220 kV Snezhnaya substation into two 110 kV linear cells. This allows the consumer to receive additional 60 MW.

The 220 kV Snezhnaya substation with the installed transformer capacity of 370 MVA was built in 1973. The power facility also supplies electricity to the fuel and energy companies, residential and industrial areas of KhMAO-Yugra and south of the Tyumen Region.