ASX:GCY

Dalgaranga A Near Term +100,000 ozpa Low Cost and High Margin Gold Project in Western Australia

Moving to Development Investor Presentation March 2017

Disclaimer & Competent Persons Statement

This presentation contains forward looking statements. Forward looking statements are often, but not always, identified by the use of words such as "seek", "target", "anticipate", "forecast", "believe", "plan", "estimate", "expect" and "intend" and statements that an event or result "may", "will", "should", "could" or "might" occur or be achieved and other similar expressions. Indications of, and guidance on, future expected production or earnings and financial position and performance are also forward looking statements. The forward looking statements in this presentation are based on current expectations, estimates, assumptions, forecasts and projections about Gascoyne and the industry in which it operates as well as other factors that management believes to be relevant and reasonable in the circumstances at the date such statements are made, but which may prove to be incorrect. The forward looking statements relate to future matters and are subject to various inherent risks and uncertainties. Many known and unknown factors could cause actual events or results to differ materially from the estimated or anticipated events or results expressed or implied by any forward looking statements. Such factors include, among others, changes in market conditions, future prices of gold and exchange rate movements, the actual results of production, development and/or exploration activities, variations in grade or recovery rates, plant and/or equipment failure and the possibility of cost overruns. Neither Gascoyne, its related bodies corporate nor any of their directors, officers, employees, agents or contractors makes any representation or warranty (either express or implied) as to the accuracy, correctness, completeness, adequacy, reliability or likelihood of fulfilment of any forward looking statement, or any events or results expressed or implied in any forward looking statement, except to the extent required by law.

You are cautioned not to place undue reliance on any forward looking statement. The forward looking statements in this presentation reflect views held only as at the date of this presentation. Other than as required by law and the ASX Listing Rules, Gascoyne disclaims any duty to update forward looking statements to reflect new developments.

Information in this presentation is based on data compiled by Gascoyne's Managing Director Mr Michael Dunbar who is a member of The Australasian Institute of Mining and Metallurgy. Mr Dunbar has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which they are undertaking to qualify as Competent Persons under the 2012 & 2004 Edition of the Australasian Code for reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr Dunbar consents to the inclusion of the data in the form and context in which it appears.

2

Competent Persons Statement

The Glenburgh, Golden Wings and Gilbeys Mineral Resources have been estimated by RungePincockMinarco Limited, an external consultancy, and are reported under the 2012 Edition of the Australasian Code for reporting of Exploration Results, Mineral Resources and Ore Reserves (see GCY -ASX announcement 24th July 2014 titled: High Grade Domains Identified Within Updated Glenburgh Gold Mineral Resource and ASX announcement 15th March 2017 titled Dalgaranga Gold Resource Increased to over 1.2Moz). The company confirms that it is not aware of any new information or data that materially affects the information included in the original market announcements and, in the case of estimates of Mineral Resources that all material assumptions and technical parameters underpinning the estimate in the relevant market announcement continue to apply and have not materially changed. The Company confirms that the form and context in which the Competent Person's findings are presented have not materially modified from the original market announcements.

The Dalgaranga Ore Reserve has been estimated by CSA Global Pty Ltd, an external consultancy, and is reported under the 2012 Edition of the Australasian Code for reporting of Exploration Results, Mineral Resources and Ore Reserves (see GCY -ASX announcement 25th November 2016 titled: Feasibility Confirms Dalgaranga as a Low Cost / High Margin Project. The Company confirms that it is not aware of any new information or data that materially affects the information included in the original market announcements and, in the case of estimates of Ore Reserves all material assumptions and technical parameters underpinning the estimate in the relevant market announcement continue to apply and have not materially changed. The Company confirms that the form and context in which the Competent Person's findings are presented have not materially modified from the original market announcements.

The Egerton Mineral Resource estimate and Gaffney's Find prospect historical exploration results have been sourced from Exterra Resources annual reports and other publicly available reports which have undergone a number of peer reviews by qualified consultants, who conclude that the resources comply with the JORC code and are suitable for public reporting. This information was prepared and first disclosed under the JORC Code 2004. It has not been updated since to comply with the JORC Code 2012 on the basis that the information has not materially changed since it was last reported.

All references to dollars, cents or $ in this presentation are to AUS$ currency, Where US$ are stated FX exchange rate of A$/US$ rate of 75c is used.

Production Targets:

Production Targets outlined in this presentation are based 100% on Measured, Indicated and Inferred Mineral Resources and Proved and Probable Ore Reserves, No Exploration target or exploration upside has been incorporated.

Dalgaranga Project:The Production Target is based on 93% Ore Reserves (Proved and Probable) and 7% Inferred Resources. There is a lower level of geological confidence associated with Inferred Mineral Resources and there is no certainty that further exploration work will result in the determination of Indicated Mineral Resources or that the Inferred Mineral Resources will add to the economics of the project. The first 6 years of the project's life is underpinned by this Ore Reserve, the last year of production is based on Inferred Resources, inclusion of these Inferred Mineral Resources does not substantially change the financial outcome or alter the viability of the project. There has historically been very good conversion of Inferred Resources into Indicated Resources as the structures and geological units that host the mineralisation at Dalgaranga can be traced along strike and at depth. Currently the drill density is too sparse to allow this material to be classified as Indicated Resources. As a result there is no assurance that the economic evaluation outlined in this presentation will be realised.

All of the JORC (2012) modifying factors have been adequately addressed and are sufficiently well understood (evidenced by estimation of a Proved and Probable Ore Reserve), including securing long term tenure with the grant of the Mining Lease, environmental baseline studies, mining studies, metallurgical studies, geochemical studies, tailings disposal studies, engineering studies including capital and operating cost estimates and hydrogeological studies all having been completed on the project.

The company confirms that the form and context in which the Competent Person's findings are presented have not materially modified from the original FS announcement.

Glenburgh Project: Glenburgh PFS was prepared and first disclosed under the JORC Code 2004 (the resource has now been updated to conform with the JORC 2012 guidelines). The Production Target is based on the JORC (2004) Resource (released to the ASX on April 29th 2013) which formed the basis for the preliminary Feasibility Study and was classified as Indicated and Inferred and as a result, was not sufficiently defined to allow conversion to an Ore Reserve; the financial analysis in the preliminary Feasibility Study is conceptual in nature and should not be used as a guide for investment. The Production Target is based on 70% Measured and Indicated Resources and 30% Inferred Resources. There is a lower level of geological confidence associated with Inferred Mineral Resources and there is no certainty that further exploration work will result in the determination of Indicated Mineral Resources or that the Inferred Mineral Resources will add to the economics of the project. However. there has historically been very good conversion of Inferred Resources into Measured and Indicated Resources as the structures and geological units that host the mineralisation at Glenburgh can be traced along strike and at depth. As a result there is no assurance that the economic evaluation outlined in this presentation will be realised. All of the JORC (2004) modifying factors have been adequately addressed and are sufficiently well understood to allow the completion of a PFS. An Ore Reserve has not been estimated for the Glenburgh Project. the JORC 2012 Glenburgh Mineral Resource estimate (outlined in this presentation), will form the basis for PFS update which is underway.

While the Company does not have all of the required funding in place for development of the projects, the Directors believe (given the Company's market capitalisation of circa $160M, which is almost double the expected capital cost for Dalgaranga the Company's history of raising capital, the current financial position of the Company, the Board's history of successful fundraisings and project development and the relatively modest pre-production capital requirements) it is reasonable to expect that funding (debt, equity, JV funding or funds from other sources or a combination of each) for the Dalgaranga Project will be available as and when it is required. It is also reasonable to assume that funding for the Glenburgh Project will also be available as and when required, particularly since

the staged approach to development of the two projects and the potential cashflow from Dalgaranga could see Glenburgh funded from internal (future) sources. 3

Near-Term High Margin Western Australian Gold Producer

2.3 Moz of Gold in Resource in Western Australia Dalgaranga - Western Australia's Next Gold Mine
  • Near-term High Margin production of +100,000ozpa

  • First gold planned for early CY18

    +1.23Moz Resource and Growing

  • Dalgaranga FS completed, confirms project as Low Cost / High Margin:

    • 105,000 ozpa in years 1 and 2, and LOM AISC $931/oz

    • Initial 6 year life of mine

      Glenburgh Gold Project

      (1.05 Moz)

      Glenburgh - Second Development Project Ready Exploration Drilling Identifying Significant Upside
    • NPV8 (pre tax) of A$177M, IRR 65%, Payback

  • Proved and Probable Ore Reserve of 552,000oz (Update is Underway)

  • Significant upside potential on a number of fronts

  • Pathway towards +200,000ozpa through organic growth from Glenburgh

  • 1.05Moz Resource

  • Development to be funded through cashflow from Dalgaranga

  • ONGOING EXPLORATION PROGRAM

  • Well funded to drive significant exploration drilling at both Dalgaranga and Glenburgh throughout 2017:

    • Dalgaranga: Focus on near-mine opportunities to add mine life

    • Glenburgh: 1Moz discovered already, only 30% of mineralised trends tested to date

Dalgaranga Gold Project

(1.23 Moz)

Perth

Western Australia

4

Gascoyne Resources Ltd. published this content on 21 March 2017 and is solely responsible for the information contained herein.
Distributed by Public, unedited and unaltered, on 21 March 2017 02:24:13 UTC.