Damang Reinvestment Plan

Monday, 24 October 2016

Johannesburg, 24 October 2016: Gold Fields Limited (Gold Fields) (JSE, NYSE: GFI) is pleased to announce the Reinvestment Plan for the Damang Gold mine in Ghana which will extend the life of mine (LOM) by eight years from 2017 to 2024. The Reinvestment Plan, entails Gold Fields investing US$1.4bn (operating and capital expenditure) over the LOM. It will enhance the Group's presence in one of its key operating regions and will result in significant social benefits for Ghana, including the creation and preservation of 1,850 direct jobs.

Over the LOM, a total of 165Mt will be mined, with 32Mt processed at a grade of 1.65g/t, resulting in total gold production of 1.56Moz. Mining and processing costs are estimated to average US$3.60/t and US$16.25/t, respectively while all-in costs (AIC) are forecast to average US$950/oz. The benefits of the Development Agreement (signed between Gold Fields and the Government of Ghana in March 2016), have been key inputs into the Plan and enhances the economics of the project.

The Reinvestment Plan is based on mineral resource models that have been updated in 2016 and extensively reviewed both internally and by external consultants, namely SRK, Optiro and Rowley Geological Services (RGS).

Since operations at Damang commenced in 1997, the mine has produced in excess of 4.0Moz, sourced from multiple open pits. Production from the Damang Pit Cutback (DPCB) came to an end in 2013, and since then mining has focused on the margins of the Damang pit (the Huni, Juno and Saddle areas) as well as lower grade satellite deposits. The decline in production since 2013 has been exacerbated by variations in grade in the northern and southern extremities of the DPCB and the satellite pits where grades have been lower than expected.

Consequently, a strategic review of Damang commenced in 2015 which identified that Gold Fields should return to mining the higher grade core of the main Damang orebody. Evaluation work in 2015 and 2016 considered a number of options, including:

Care and maintenance (C&M)
Closure
Continuing operations
Expanding operations

Given the importance of the region to the Group and taking into account the benefits of the Development Agreement, Gold Fields has taken the decision to continue operations at Damang through the Reinvestment Plan. The Group will also retain the optionality to expand the operation should the gold price strengthen sustainably to above US$1,400/oz.

The Reinvestment Plan entails a major cut back to both the eastern and western walls of the DPCB. The cut back will have a total depth of 341m, comprising of a 265m pre-strip to access the base of the existing pit. This will be followed by a deepening of the pit by a further 76m which will ultimately provide access to the full Damang orebody including the high grade Tarkwa Phyllite lithology. To provide short term ore supply, while the Damang pre-strip is in progress, mining will continue at the Amoanda, and paleaoplacer satellite pits (Lima South, Kwesi Gap and Tomento East). In addition, the plant feed will be supplemented by low grade surface stockpiles.

Inclusion of the Damang cutback will result in a 72% increase in Proven and Probable Reserves to 1.68Moz (31.5Mt @1.65g/t) compared with the December 2015 figure.

Mining will be undertaken by two mining contractors, with negotiations currently at an advanced stage. At this stage, the contractors are expected to be mobilised early in 2017. A total of 165Mt will be mined over a 7-year period, with the majority of material coming from the Damang Complex (DCPB/Saddle). Of this 32Mt will be processed at a grade of 1.65g/t, resulting in 1.56Moz of gold production. Operational metrics for the project are summarised in the table below:

2017 2018 2019 2020 2021 2022 2023 2024 LOM
Tonnes mined Kt 32 500 36 900 33 200 24 500 15 200 13 300 9 300 0 165 000
Tonnes milled Kt 4 200 3 450 4 200 4 200 4 200 4 200 4 250 3 600 32 300
Head grade g/t 0.90 1.25 1.75 1.80 2.10 2.05 2.05 1.10 1.65
Gold production Koz 110 125 220 225 265 250 260 115 1 565
Mining cost US$/t 3.30 3.10 3.35 3.70 4.25 4.50 5.20 0.00 3.60
Processing cost US$/t 15.95 17.75 15.95 15.95 15.95 15.90 15.65 17.40 16.25
AIC US$/oz 2 265 1 730 1 025 930 660 675 605 800 950

Apart from the waste strip, the only other significant capital required is for the construction of the Far East Tailings Storage Facility (FETSF) as the existing tailings storage facility (TSF) is approaching full capacity. An interim 2.5m raise has commenced on the TSF, which will provide for an additional 3.6Mt tailings capacity and is due for completion by the end of November 2016. Stage 1 of the new FETSF is planned for completion by end-2017 and will provide 20Mt capacity. Further lifts of the FETSF will cater for all tailings for the new LOM. Only minor capital work will be required on the Damang Processing Plant, mostly due to replacement of the SAG Mill shell in 2018.

Figure 1 below illustrates the capex profile for the Damang Reinvestment Plan:

In addition to the attractive returns associated with the project, the Reinvestment Plan will result in significant social and fiscal benefits flowing into Ghana and, more importantly, the communities surrounding Damang.

Gold Fields estimates direct employment associated with the Reinvestment Plan of 1,850 people. Of this:

368 will be Gold Fields employees, 55% of whom will come from the adjacent communities;
90 will be on fixed term contracts, all from the catchment community; and
Approximately 1,400 will be contractor employees, 60% of whom will come from local communities.

Assuming a dependency ratio in Ghana around eight dependents per direct mining job, the spin-off benefits of the new and retained jobs will be significant.

Investment in sustainable development projects is estimated to be US$5.0m over the eight-year period. This will be split between education (US$1.5m), health (US$0.2m), water and sanitation (US$0.7m), agriculture (US$1.6m) and infrastructure (US$1.0m).

Gold Fields has also commenced the tarring of the road between Damang and Tarkwa, estimated to cost US$17m, which is expected to have benefits for the mines as well as local stakeholders.

Previous page

Gold Fields Ltd. published this content on 24 October 2016 and is solely responsible for the information contained herein.
Distributed by Public, unedited and unaltered, on 24 October 2016 06:37:01 UTC.