16.04.14

IDGC of Centre - Tambovenergo division summed up the implementation of the 2013 investment program. The document is based on the activities aimed at ensuring the smooth operation of power equipment, improving the quality of power supply, creation of conditions for grid connection of new customers in the Tambov region.

In the reporting period, the branch spent 497.9 million on them, representing 100% of the annual plan. At the same time, the power engineers achieved over-fulfillment of key targets of the program. By the end of 2013 Tambovenergo commissioned 36.3 MVA of capacity and 133.1 km of power lines, representing 157% and 106% of the planned values , respectively. These results were achieved by increasing the number of grid connections, as well as the implementation of measures to improve the reliability of electricity supply to consumers.

Particular attention in the framework of the investment program implementation was paid to the construction of the grid infrastructure required to connect agricultural and social and community purpose facilities. Among the major projects implemented by the branch in these areas - the connection to the grid of apartment houses in the neighborhoods "Cozy" and "Sloboda" in Tambov, facilities of LLC "Tambov turkey", a livestock complex of LLC "Resource", and LLC "Tambov Bacon".

"The investment program implementation is one of the important activities of the branch. Reconstruction of power facilities, modernization of equipment, use of modern technology, commissioning of new production capacity, which increases the grid transmission capacity, ultimately, they make a significant contribution to ensuring safe and reliable operation of the electric grid complex of the Tambov region," stressed Deputy Director for Capital Construction of Tambovenergo Konstantin Svirin.

To news
distributed by