25.05.2017

IDGC of Centre - Belgorodenergo division provided the grid connection of the 'Paris' residential complex, built on the embankment of the Vezelka River in Belgorod.

To connect the multi-apartment complex, the branch laid 3.2 km of 10 kV cable lines and installed two package transformer substations with a total capacity of 3,260 kVA. When installing the power supply circuit the power engineers used modern Russian equipment and materials. The metering system is designed with the possibility of daily transmission of data on hourly electricity consumption to the AMR system of the Belgorodenergo branch.

The maximum capacity of the housing complex will be 1265.6 kW. In four stages, the branch will connect 16 electrical distribution panels. The project is planned to be completed in 2018.

Two houses of varying storeys of the 'Paris' micro-district are being built by the company 'TransYuzhStroy-PGS' on a plot of 4 hectares along Kharkovskaya Street in Belgorod. The first stage provides for the construction of a 7-13-storey building and an underground parking, while the first two floors will be given to non-residential premises - cafes and shops. The second stage involves the construction of another house and a parking lot.

As it became known, the name of the new micro-district - 'Paris' - was chosen because of the similarity of the architectural solution with the attic floors of the Parisian quarters of Montmartre. The complex is located in three minutes' walk from the main square of the city of Belgorod.

IDGC of Centre JSC published this content on 25 May 2017 and is solely responsible for the information contained herein.
Distributed by Public, unedited and unaltered, on 26 May 2017 07:10:30 UTC.

Original documenthttps://www.mrsk-1.ru/en/press-center/news/branches/60188/