25.08.2016

IDGC of Centre - Bryanskenergo division summed up the implementation of the repair program for the first half of 2016.

Implementation of measures of the document on a number of indicators is ahead of schedule. The power company repaired 137.5 km of 35-110 kV overhead lines and 805.4 km of 0.4-10 kV overhead lines (116% and 104% of the targets of the half-year), 269 transformer substations of 6-10/0.4 kV (112 % of the plan). 333.9 hectares (126% of the planned figure) of ROWs along overhead lines of 0.4 - 110 kV were cleared from tree and shrub undergrowth​​. The 110 kV Substations Lopandino, Energoremont and Polpinskaya were overhauled.


The implementation of the repair program is one of the key events of preparation of electric grid facilities of Bryanskenergo for the autumn-winter peak loads. Timely and full implementation of its activities allows to provide reliable power supply of consumers of the Bryansk region in the period of cold weather. of Centre - Orelenergo division Irina Savelieva.

IDGC of Centre JSC published this content on 25 August 2016 and is solely responsible for the information contained herein.
Distributed by Public, unedited and unaltered, on 25 August 2016 09:29:05 UTC.

Original documenthttps://www.mrsk-1.ru/en/press-center/news/branches/56824/

Public permalinkhttp://www.publicnow.com/view/FECCA9267FDDB96D3AE589F69CD0BC9314F38650