Sep. 11, 2014

Nippon Steel & Sumitomo Metal Corporation

The current operational status of Nagoya Works' facilities, which suspended operation due to the accident of September 3rd, is as follows:

Facility
Time and date of
resumption of operation
No. 4 Coke Oven 21:26, September 5th
No. 3 Blast Furnace 7:25, September 6th
No. 5 Coke Oven 14:27, September 6th
No. 1 Blast Furnace 15:49, September 6th
Steelmaking Plant 15:51, September 6th
 No. 2 Coke Oven  17:18, September 6th
 Plate Mill 3:30, September 7th
 No. 5 Continuous hot-dip galvanizing
& galvannealing line(CGL)
17:05, September 7th
 No. 2 Continuous hot-dip galvanizing
& galvannealing line(CGL)
18:08, September 7th 
 Hot Rolling Mill 10:51, September 8th
No. 1 Continuous hot-dip galvanizing
& galvannealing line(CGL)
20:25, September 8th
 No. 2 Continuous annealing
and processing line(CAPL)
14:50, September 9th
No. 1 Continuous annealing
and processing line(CAPL)
14:00, September 11th