on Feb. 9.
Tesoro Mandan, ND 58.0 Total crude-oil processing capa- 2nd Q
city to increase by 17% to 68,000 2012
b/d by 2nd quarter 2012.
ROCKIES
WEST COAST
Exxon Torrance 155.0 Several units will be shut for
Mobil CA planned maintenance, including
hydrogen, coker and pretreater
starting June 4. Work will take
several weeks to complete, the
co. said on June 4.
Shell Martinez 156.4 Scheduled work (unspecified)
CA is underway, the co. said on
Apr 27. Traders said crude and
coker unit involved; end date
not provided.
Tesoro Wilmington 97.0 Planned maintenance underway at
CA unspecified units, the co. said
on June 6. No restart estimate.