4 June 2013

Manager of Company Announcements

ASX Limited

Level 6, 20 Bridge Street

SYDNEY NSW 2000

By E-Lodgement GALOC-5H AND GALOC-6H DRILLING COMMENCES Highlights:

Commencement of drilling with the spud of the Galoc-

5H and 6H development wells

Otto Energy Limited ("Otto") (ASX:OEL), as operator of the producing Galoc oilfield joint venture offshore the Philippines, provides the following update on the Galoc-5H and Galoc-6H drilling campaign in SC14C, part of the Galoc Phase II development approved in 2012.

Progress

Otto is pleased to advise that at 1300 hours on 4 June 2013, the Ocean Patriot semi-submersible drilling rig commenced drilling the Galoc-5H and 6H development wells. Drilling is expected to take approximately 115 days including the flowing of the wells for clean-up.

Forward Plan

The forward plan is to drill the 36" (914 mm) hole to 392 metres and install the 30" conductor prior to drilling the 171/2"
(444 mm) hole to 950 metres.

OTTO AT A GLANCE

• ASX-listed oil and gas company with a strategy to grow its integrated oil and gas business across exploration, development and production

• Focused on South East Asia and East

Africa

• Operator of the producing Galoc oil field in the Philippines, which provides cashflow

• Opportunity rich with substantial exploration prospects and leads COMPANY OFFICERS

Rick Crabb Chairman

Ian Macliver Director Rufino Bomasang Director John Jetter Director Ian Boserio Director Gregor McNab CEO

Matthew Allen CFO/Coy Secretary

Otto will provide weekly updates on drilling progress commencing on Wednesday 12 June 2013.

Head Office 32 Delhi Street, West Perth WA 6005 Australia PO Box 1414, West Perth, WA 6872 Australia T: +61 8 6467 8800 F: +61 8 6467 8801

Manila Office 32nd Floor Philamlife Tower, 8767 Paseo de Roxas, Makati City 1226, Philippines T: +63 2 773 2700 F: +63 2 773 2801 info@ottoenergy.com ASX Code: OEL ABN: 56 107 555 046

Figure 1: MODU Ocean Patriot being moored on field, taken from FPSO Rubicon Intrepid

--Ends--

Contact: Matthew Allen

Chief Financial Officer

+61 8 6467 8800 info@ottoenergy.com

Media:

Dudley White

MAGNUS Investor Relations + Corporate Communication

+61 2 8999 1010 dwhite@magnus.net.au

Head Office 32 Delhi Street, West Perth WA 6005 Australia PO Box 1414, West Perth, WA 6872 Australia T: +61 8 6467 8800 F: +61 8 6467 8801

Manila Office 32nd Floor Philamlife Tower, 8767 Paseo de Roxas, Makati City 1226, Philippines T: +63 2 773 2700 F: +63 2 773 2801 info@ottoenergy.com ASX Code: OEL ABN: 56 107 555 046

Location and Proposed Depth

The Galoc field is located in Service Contract SC14C (Galoc Sub Block) in 290m of water approximately 65km North West of Palawan Island and 350km south of Manila in the Republic of the Philippines. The Galoc-5H and Galoc-6H development wells are being drilled within the existing producing field that has delivered over 10
MMbbls of production since the field was commissioned in 2008.
The wells are being batch drilled in 311 metres of water. It is planned that the Galoc-5H and Galoc-6H development wells will be drilled to a total vertical depth of 2,190 with approximately 2,000 of horizontal completion. Drilling is expected to take approximately 115 days including the flowing of the wells for clean-up.
After drilling of both Galoc-5H and Galoc-6H is completed, the DOF operated Skandia Hercules construction vessel will be used to install the subsea equipment and complete the hook-up of both wells to the FPSO Rubicon Intrepid.

First oil from the Phase II wells is expected during Q4 2013.

Head Office 32 Delhi Street, West Perth WA 6005 Australia PO Box 1414, West Perth, WA 6872 Australia T: +61 8 6467 8800 F: +61 8 6467 8801

Manila Office 32nd Floor Philamlife Tower, 8767 Paseo de Roxas, Makati City 1226, Philippines T: +63 2 773 2700 F: +63 2 773 2801 info@ottoenergy.com ASX Code: OEL ABN: 56 107 555 046


APPENDIX A: SUMMARY

SC14C Galoc-5H and Galoc-6H Development Wells

Location

Palawan Basin, Philippines

Permit

SC14C

Well Type

Horizontal development wells

Target

Turbiditic sandstone in Miocene Galoc Classic Unit

Water Depth

Approximately 311 metres

Planned total depth

Approximately 2,190 metres vertical

Total drilled length approximately 5,000 metres for each well

Duration

115 days (including well clean-up flow)

Note: Depth is measured in metres below the rig rotary table or drilling floor

Joint Venture Partners:

Participant

Participating Interest %

Galoc Production Company W.L.L. (Operator)

(Wholly owned subsidiary of Otto Energy Ltd (ASX: OEL))

33.00000

Galoc Production Company No. 2 Pte Ltd

(Wholly owned subsidiary of Kuwait Foreign Petroleum

Exploration Company)

26.84473

Nido Production (Galoc) Pty Ltd

(ASX: NDO)

22.87952

Oriental Petroleum & Minerals Corporation and Linapacan

Oil Gas & Power Corporation

7.78505

The Philodrill Corporation

7.21495

Forum Energy Philippines Corporation

2.27575

Head Office 32 Delhi Street, West Perth WA 6005 Australia PO Box 1414, West Perth, WA 6872 Australia T: +61 8 6467 8800 F: +61 8 6467 8801

Manila Office 32nd Floor Philamlife Tower, 8767 Paseo de Roxas, Makati City 1226, Philippines T: +63 2 773 2700 F: +63 2 773 2801 info@ottoenergy.com ASX Code: OEL ABN: 56 107 555 046

distributed by