Pan African Resources PLC                           

                (Incorporated and registered in England and Wales under            

        Companies Act 1985 with registered number 3937466 on 25 February 2000)     

                                     AIM Code: PAF                                 

                                     JSE Code: PAN                                 

                                  ISIN: GB0004300496                               

                              ("Pan African" or "Group")                           

     RESULTS OF DEFINITIVE FEASIBILITY STUDY FOR THE ELIKHULU TAILINGS PROJECT AND 
                                GROUP PRODUCTION UPDATE                            

    Pan African is pleased to announce positive results for the independent
    Definitive Feasibility Study ("DFS") for its Elikhulu Tailings Project
    ("Elikhulu" or "the Project").  The Pan African board of directors ("Board")
    has approved the construction of the Project, subject to finalisation of the
    Project financing package.

    The Project DFS results indicate excellent recovered grades and gold
    production, attractive financial returns and a low execution risk, with the DFS
    results surpassing expectations of previous technical and financial assessments
    of the Project.  The DFS was undertaken by DRA Projects SA Proprietary Limited
    who has reviewed and approved the information contained in this announcement in
    writing.

    DFS highlights and key assumptions

      * The planned commencement date of the Project is January 2017, with first
        gold forecast for the final quarter of the 2018 calendar year and full
        commissioning in December 2018.  
       
      * Annual recoverable gold production of approximately 56,000 ounces for its
        initial eight years of operations and 45,000 ounces of gold for the
        remaining five years thereafter.
       
      * Current arisings and inferred gold resource could extend Project life
        beyond the DFS estimated life of 13 years.
       
      * Optimal plant capacity for the Project allows 12-million tonnes per annum
        throughput.
       
      * The Project is expected to add approximately 25% to the Group's current
        production profile and reduce the Group's all-in sustaining cost ("AISC")
        profile.
       
      * Initial capital cost is forecast at approximately R1.74 billion (US$119.9
        million).
       
      * The Project internal rate of return ("IRR") (real, post-tax) of 23.1%
        (30.6% nominal) with a payback period of less than four years, based on
        assumed gold price of US$1180/oz (R17,110/oz).
       
      * Return on equity (real, post-tax) of 34.3% (42.5% nominal)  
       
      * Project net present value ("NPV") of R1.1bn (US$75.9 million).
       
      * AISC of US$523/oz over the life of the Project.
       
      * Cash outflow per ounce over the life of the operation is sub $650/oz,
        inclusive of debt servicing, and amounts to approximately $805/oz,
        inclusive of debt servicing, over the five year debt redemption term.
       
      * Average gold recovery rate over the life of the Project of 47.77%.
       
      * Environmental Impact Assessment ("EIA") and Water Usage Licence ("WULA")
        processes are underway, with both approvals expected by late 2017.
       
        DFS economic assumptions:
       
      * Gold price assumption: US$1,180/oz.
      * Rand/US Dollar exchange rate:  ZAR/US$:14.50.
      * NPV discount rate: 9% real.
      * Debt to equity ratio: 115%, debt to total capital ratio of 53%.
      * Long term South African inflation rate of 6.1%.

    Return on investment

    Pan African endeavours to invest only in projects positioned in the lower half
    of the cost curve, and only when the project execution and construction risk is
    within Pan African's capability.  The experience gained in the construction and
    operation of the Barberton Tailings Retreatment Plant ("BTRP") and the Evander
    Tailings Retreatment Plant ("ETRP") positions Pan African to successfully
    execute the construction and operation of the Elikhulu project. The Board is
    satisfied that the Project meets the Group's investment criteria and that the
    Group's track record of successfully operating three tailings plants, all of
    which were constructed on time and on budget, will be invaluable in the
    construction and operation of the Elikhulu Project. 

    Project funding

    Pan African funds its capital programmes and acquisitions with conservative
    debt levels that are appropriate for the specific project, and the Group's
    overall level indebtedness. The Project's execution and operational risk is
    deemed to be low, and the robust nature of the Project's cash flow generation
    allows for a relatively high level of debt funding.

    Rand Merchant Bank, a division of First Rand Bank Limited, has provided Pan
    African with all necessary approvals for a R1bn underwritten five-year debt
    facility on competitive terms ("RMB Facility"). This facility will be dedicated
    to the funding of the Project's development and will be repaid from the
    Project's cash flows, generated during the initial five years of production.
    This facility is in addition to the Group's current Revolving Credit Facility
    ("RCF") of R800 million (US$55.2 million), which can be extended to R1.1
    billion (US$75.9 million), conditional on approval from the RCF lenders.

    The Group is evaluating a number of funding proposals to fund the balance of
    the initial Project capital and, given its strong financial position and access
    to debt facilities, does not foresee difficulty in securing the balance of the
    funding on competitive terms.

    The RMB Facility's repayment profile is matched to the Project's cash flow
    generation and is not expected to impact Pan African's existing dividend
    policy, which provides for a pay-out ratio of 40% of annual free cash flow. 

    Cobus Loots, Pan African's CEO, said:

    "We are pleased to announce the positive findings of the independent Definitive
    Feasibility Study.  Operating low cost tailings plants has become an important
    business for Pan African in recent years, and we now intend to proceed with
    construction of the Elikhulu tailings retreatment project. This project is
    expected to materially enhance our Group's production profile and support Pan
    African's continued focus on low-cost, high-margin gold ounces. The substantial
    capital investment required demonstrates our commitment to the South African
    mineral sector and our shared responsibility of creating employment and
    alleviating poverty in the Evander community.

    Our primary consideration in any capital allocation decision is our ability to
    successfully execute the designated project and to generate the required
    returns over the investment horizon. The attractive returns already being
    earned on the capital invested in the BTRP and ETRP bear testimony to our
    previous success and will serve as invaluable experience in completing the
    Project.

    Elikhulu is expected to firmly establish Pan African as a leader in long-life,
    low-cost tailings retreatment, and possibly unlock other opportunities in the
    sector.  We expect the Project to reduce the Group and Evander cost profiles
    and generate robust cash flows and attractive returns for our shareholders."

    Scope of the project

    The Project entails establishing facilities and infrastructure at Evander Gold
    Mining (Proprietary) Limited ("Evander"), owned and operated by Pan African, to
    retreat gold plant tailings at a rate of 1-million tonnes per month. This is in
    addition to the existing production from the ETRP which will continue to
    operate independently of the Project for the next 13 years. Three existing
    tailings storage facilities will be reclaimed, in the following order: Kinross,
    Leslie and Winkelhaak. Post processing, these will be consolidated into a
    single enlarged Kinross tailings facility, contributing to reducing Evander's
    environmental footprint and associated environmental impact.

    The Project is expected to yield approximately 56,000oz of gold per annum for
    the initial eight years of production (while treating the Kinross and Leslie
    tailings storage facilities), and then approximately 45,000oz a year for the
    Project's remaining five years from processing the Winkelhaak tailings storage
    facility. These production figures exclude an inferred resource of 244,398oz of
    gold delineated in the soil material beneath the existing tailing dumps. 

    The average gold recovery over the life of the project is forecast at 47.77%.
    Using modelled recoveries, the gold dissolution value estimated for Kinross is
    51.38%, Leslie 48.29% and Winkelhaak 53.77%.

    Project capital:

                          Construction capital            Construction capital           Life of    
                                                                                        operation   
                                                                                                    
                                 Phase 1                 Phase 2         Phase 3       All Phases   
                                                                                                    
                          2017            2018            2021            2026            Total     
                                                                                                    
                        R      US$      R      US$      R      US$      R      US$      R      US$  
                     million million million million million million Million million million million
                                                                                                    
    Pre-construction  24.5     1.7      -       -       -       -       -       -     24.5     1.7  
                                                                                                    
    Process plant     273.3   18.8    409.9   28.3      -       -       -       -     683.2   47.1  
                                                                                                    
    Tailings storage  283.1   19.5    424.7   29.3    138.4    9.5      -       -     846.2   58.3  
    facility                                                                                        
                                                                                                    
    Overland piping   30.3     2.1    45.5     3.1    29.8     2.1    48.0     3.3    153.6   10.6  
                                                                                                    
    Hydraulic mining  22.6     1.6    34.0     2.3    125.9    8.7    58.4     4.0    240.9   16.6  
                                                                                                    
    Contingency       94.7     6.5    96.5     6.7    19.0     1.3     6.6     0.5    216.8   15.0  
                                                                                                    
    Total             728.5   50.2   1,010.6  69.7    313.1   21.6    113.0    7.8   2,165.2  149.3 

    Phase 1 capital relates to the initial capital required to construct the plant
    and associated infrastructure. This capital of R1.74 billion (US$119.9 million)
    includes a contingency of R191.2 million (US$13.2 million) to account for
    potential cost overruns and additional plant design requirements.

    Phase 2 and 3 capital of R313.1 million (US$21.6 million) and R113.0 million
    (US$7.8 million), respectively, which is required to re-establish the
    hydro-mining infrastructure to the Leslie and Winkelhaak tailing dumps, will be
    funded from Project-generated cash flows.

    Mineral reserve estimate

    Tailings         Probable reserve  Probable reserve  Probable Au      
    facility         tonnes (M)        grade (g/t)       content (Moz)    
                                                                          
    Kinross                47.0              0.31              0.47       
                                                                          
    Leslie                 70.1              0.32              0.71       
                                                                          
    Winkelhaak             70.0              0.24              0.55       
                                                                          
    Total                  187.1             0.29              1.73       

    The mineral reserve estimate is a probable 187.1Mt and comprises the Kinross
    (47.0Mt), Leslie (70.1Mt) and Winkelhaak (70Mt) tailings storage facilities at
    Evander. The combined 187.1Mt will provide feed material to the existing ETRP
    at 200,000 tonnes per month, and to the Project process plant at a rate of
    1-million tonnes per month (of which 40,000 tonnes per month will be from
    run-of-mine tailings).

    The combined mineral reserve contains an estimated 1.73Moz of gold of which an
    estimated 688,700oz of gold will be recovered over the life of the Project.
    This estimate excludes the inferred resource 244,398oz of gold leached into the
    soil beneath the existing tailing dumps, which could potentially increase the
    Project life. 

    The mineral reserve estimate assumes a non-selective mining method whereby the
    whole of mineral deposit is mined in a predetermined sequence. The mining
    method allows for a 100% extraction of the target mineral deposit. Hydraulic
    mining has been selected as the preferred mining method as it is proven
    technology, cost effective and operationally well understood.

    Competent person

    Mr Barry Naicker, the group mineral resource manager, has signed-off the
    mineral reserve information contained in this announcement, following his
    review and approval. He is a member of the South African Council for Scientific
    Professions (400234/10). Mr Naicker has 15 years of experience in economic
    geology and mineral resource management. He is based at 1st Floor, The Firs,
    corner Cradock and Biermann Avenues, Rosebank 2196, Gauteng.

    Timeline to production

    Phase 1 of the hydraulic mining at the Kinross tailings storage facility is
    scheduled to commence in the fourth calendar quarter of 2018 and for the
    Project to reach full commercial production December of that year. Phase 2 at
    the Leslie tailings storage facility is scheduled for the end of the third
    quarter of 2021 and Phase 3 at Winkelhaak in the third calendar quarter of
    2026.

    Cost profile

    The Project is expected to be a low cost producer with a cash cost of US$440/oz
    and an AISC of US$523/oz over the life of the Project. Cash costs for Phase 1
    are however lower at US$398/oz, due to the lower re-mining costs of the Kinross
    tailings dump. The Phase 2 and 3 cash costs are expected to be US$448/oz and
    US$504/oz, respectively.

    Environmental impact

    The EIA process for the Project is underway and Department of Mineral
    Resources' ("DMR") approval is expected to be granted by late 2017. The WULA
    process has also commenced with Department of Water Affairs' approval expected
    in late 2017. Water will be sourced from the existing Evander underground
    workings and the Leeuwpan evaporation dam, which is owned and operated by
    Evander. The Leeuwpan dam is situated approximately 10km south west of the
    Kinross tailings storage facility and, based on the Project's overall water
    balance, there is sufficient water to support the Project through its life.

    Financial evaluation

    The project benefits from a short commissioning period and is highly cash
    generative from inception, which enables the Project to be funded with a
    relatively high level of gearing.  The Project's all-in cash outflow per ounce,
    inclusive of debt instalments, is US$636 per ounce over the life of operation,
    and US$805 per ounce during the 5 year debt redemption period, which
    illustrates the economic robust nature of the Project. With a real IRR of 23.1%
    (nominal 30.6%), and a payback period of less than four years, the project
    generates distributable cash flow from inception and should enhance Pan
    African's ability to continue declaring sector leading dividends to
    shareholders.

    The Project's estimated real post tax cash flows and pre-debt instalments, over
    the initial four years of production are illustrated hereunder:

                  Dec-19          Dec-20          Dec-21          Dec-22     
                                                                             
                 R      US$      R      US$      R      US$      R      US$  
              million million million million million million million million
                                                                             
    Revenue   1,062.0    73.2 1,032.0    71.2   982.0    67.7   978.0    67.4
                                                                             
    Operating (333.0)  (23.0) (336.0)  (23.2) (339.0)  (23.4) (337.0)  (23.2)
    costs                                                                    
                                                                             
    Capital    (64.0)   (4.4) (169.0)  (11.7) (273.0)  (18.8)  (64.0)   (4.4)
    costs                                                                    
                                                                             
    Taxation    (1.0)   (0.1)   (1.0)   (0.1)  (47.0)   (3.2) (176.0)  (12.1)
    and                                                                      
    royalties                                                                
                                                                             
    Post tax    664.0    45.7   526.0    36.2   323.0    22.3   401.0    27.7
    cash                                                                     
    flows                                                                    

    Further information on the Project

    A presentation with further Project detail is available on the Pan African
    website (www.panafricanresources.com). The complete DFS is also available for
    review at Pan African's corporate office.

    PRODUCTION UPDATE

    Interim            Mining and tailings operations           
    Period                                                      
    ending       Barberton   Evander  Uitkomst     Phoenix      
    31 December  Mines and  Mines and Colliery  Platinum (PGE   
                   BTRP       ETRP      (Coal      ounces)      
                   (Gold      (Gold   tonnes)*                  
                  ounces)    ounces)                            
                                                                
    Actual 2015   56,447     45,350       -         4,493       
                                                                
    Forecast      49,000     42,000    330,000      4,900       
    2016                                                        
                                                                
    Percentage    (13.2%)    (7.4%)    100.0%       9.1%        

    *Uitkomst Colliery was acquired on 31 March 2016, and the coal tonnes forecast
    includes approximately 200,000 tonnes from the underground mining operation and
    130,000 acquired coal tonnes for processing and blending.

    Gold mining operations production update

    The Group previously guided gold production of approximately 200,000oz for the
    2017 financial year.  In light of challenges experienced with its operating
    environment and underground operations in recent months, the Group now
    considers it appropriate to revise this guidance down to approximately
    195,000oz of gold production for the 2017 financial year, with gold production
    in the 2nd half of the financial year exceeding 1st half performance.

    In addition to the operational challenges detailed below, community unrest in
    the Barberton area and DMR safety stoppages ("Section 54 regulatory notices")
    severely affected gold production in the current reporting period.  Pan African
    is actively engaging with all stakeholders in this regard, in order to ensure
    that operations are allowed to operate at steady-state and in a sustainable
    manner.

    Cobus Loots, Pan African's CEO, said:

    "Operational performance from our underground operations during the 1st half of
    the 2017 financial year has been disappointing. Pan African's mines are not
    exempt from the political and social unrest that is prevailing in South African
    society at present.  The current state of affairs is clearly unacceptable and
    our management team will not relent until the previous operational form has
    been restored.  All stakeholders have to work together in this regard, the
    Group will use all means at our disposal to ensure we protect and increase
    value for our stakeholders".

    The decreased production guidance is principally due to the following factors:

    Evander Mines

    Operational:

      * Evander Mines' 7 Shaft, which is used to hoist ore from underground mining
        operations to surface for processing, is undergoing critical maintenance
        following the dislodgement of a steel shaft guide which damaged the shaft
        infrastructure. Even though primary repairs have been completed, 7 Shaft's
        hoisting speed is curtailed until the full maintenance programme is
        completed. The shaft is expected to resume normal hoisting speed in early
        January 2017.
      * Evander Mines experienced a material increase in DMR initiated safety
        stoppages during the past five months. The operation was issued with four
        Section 54 regulatory notices, which resulted in 13 lost production days
        (Comparable period: three Section 54 regulatory notices resulting in 2 lost
        production days).  The majority of the lost production days related to the
        7 Shaft incident.

    Barberton Mines

    Industrial relations and community protests:

      * Three separate community protests relating to unrest as a result of poor
        government service delivery in the area and competing recruitment interests
        from lobby groups was experienced, which resulted in 6 days of lost
        production.
       
      * Union related demands resulted in workers embarking on a go slow which
        adversely affected productivity.
       
    Operational:

      * Fairview mine experienced flexibility issues, specifically at its very high
        grade 11-block.  Work is underway to develop a new production platform.
        Further flexibility improvements will be achieved via a new decline under
        development.  In addition, a new refrigeration plant will improve working
        conditions in this area.
      * Six Section 54 regulatory notices, which resulted in 8 lost production
        days. (Comparable period: one Section 54 regulatory notice resulting in 3
        lost production days). Barberton Mines and Pan African continue to engage
        with all stakeholders, including the DMR, in order to reduce the impacts of
        these notices in future.

    Uitkomst Colliery

    Production and performance for the period has remained in line with
    expectations. Uitkomst Colliery has also bought-in additional coal from
    neighbouring mining operations to optimise its washing plant's operations. If
    the current favourable coal price environment continues, the payback period for
    this acquisition is expected to be less than the four years previously
    forecast.

    Phoenix Platinum

    Phoenix Platinum processing capacity has increased from 25,000 tons per month
    to 30,000 tonnes per month, following the installation of a scrubber in July
    2016. The operation has experienced water constraints due the persistent
    drought conditions during October and November 2016. Despite these challenges,
    production is expected to increase by 9.1% to 4,900oz for the 31 December 2016
    reporting period.

    Forward looking statements

    Any forward looking statements made throughout this announcement regarding the
    future financial performance of the Group have not been reviewed or audited by
    the Group's external auditors. The Board accepts full responsibility for the
    accuracy of the information contained in this announcement.

    Pan African is not obliged to publicly update any forward-looking statements
    included in this announcement, or revise any changes in events, conditions or
    circumstances on which any such statements are based, occurring after the
    publication date of this announcement, other than as required by regulation.

    Johannesburg

    5 December 2016

    Contact information                                                    
                                                                           
    Corporate Office                              Registered Office        
    The Firs Office Building                      Suite 31                 
    1st Floor, Office 101                         Second Floor             
    Cnr. Cradock and Biermann Avenues             107 Cheapside            
    Rosebank, Johannesburg                        London                   
    South Africa                                  EC2V 6DN                 
    Office:   + 27 (0) 11 243 2900                United Kingdom           
    Facsimile: + 27 (0) 11 880 1240               Office:   + 44 (0) 207   
                                                  796 8644                 
                                                  Facsimile: + 44 (0) 207  
                                                  796 8645                 
                                                                           
    Cobus Loots                                   Deon Louw                
    Pan African Resources PLC                     Pan African Resources PLC
    Chief Executive Officer                       Financial Director       
    Office: + 27 (0) 11 243                       Office: + 27 (0) 11 243  
    2900                                          2900                     
                                                                           
    Phil Dexter                                   John Prior / Paul Gillam 
    St James's Corporate Services Limited         Numis Securities Limited 
    Company Secretary                             Nominated Adviser and    
    Office: + 44 (0) 207 796 8644                 Joint Broker             
                                                  Office: +44 (0) 20 7260  
                                                  1000                     
                                                                           
    Sholto Simpson                                Matthew Armitt / Ross    
    One Capital                                   Allister                 
    JSE Sponsor                                   Peel Hunt LLP            
    Office: + 27 (0) 11 550 5009                  Joint Broker             
                                                  Office: +44 (0) 207 418  
                                                  8900                     
                                                                           
    Julian Gwillim                                Lorna Cobbett            
    Aprio Strategic Communications                Bell Pottinger PR        
    Public & Investor Relations SA                Public & Investor        
    Office: +27 (0)11 880 0037                    Relations UK             
                                                  Office: + 44 (0) 203 772 
                                                  2564                     
                                                                           
    Jeffrey Couch/Neil Haycock/Thomas Rider                                
    BMO Capital Markets Limited                                            
    Joint Broker                                                           
    Office: +44 (0) 207 236 1010                                           

    www.panafricanresources.com