Resource Generation Ltd : Transcript from BRR media webcast
05/09/2012| 02:19am US/Eastern
Recommend:
0
BRR MEDIA
TRANSCRIPT OF WEBCAST BY PAUL JURY
MANAGING DIRECTOR RESOURCE GENERATION
WEDNESDAY, 9 MAY 2012
Q1 Today on BRR I'm joined by Mr Paul Jury, the Managing
Director of Resource Generation. The Company has released
some significant updates for its Boikarabelo Project and Paul
is going to talk me through a few points now. Paul, a couple
of questions. Can I get you to start by talking through the
significance of the water licence approval and the dismissal
of the mining right appeal for the Project? With these
milestones now completed, does this open the development path
for the Project? Could I ask you to provide an update on the
Transnet contract discussions and, finally, what activities
are you now focused on to progress the Project?
A1 Thanks very much. We've just released to the market
a presentation update on the Boikarabelo Project and where we
stand with its development path and, I guess, to deal with
the questions and probably to cover, the first part of that
presentation would hopefully answer most of those questions
as well. So in terms of the presentation itself, I'll talk to
slides 3 to 7 of the presentation, just to give a better feel
for where we're at.
The significance of receiving the water use licence and the
dismissal of the appeal against the mining right was that it
effectively cleared the path for all our regulatory approvals
for the Project to proceed. And that's a very pleasing step,
and it's certainly a significant step, especially given the
size and the nature of the quality of this Project and its
development for both the Limpopo Region and for South Africa
itself.
However, dealing with slide number 3 of our presentation -
the major bridge that we always had to cross was securing a
contract with Transnet. That's certainly a significant bridge
that we're still walking across, but we are at a very mature
stage in that process after some two years of negotiations,
and we hope that that can come to a successful conclusion
very soon.
On that basis, I guess, the mine construction timeline would
follow a path of us having first to go to our project finance
banks, get them to complete a detailed due diligence and,
having secured the project funding, to cap up our
requirements with equity, then get into the mine construction
phase. So that funding stage we would see as a four to five
month process, and then the mine construction phase would be
another 24 months. So the timeline to the first production
from the mine would probably follow that path. So, really,
the starting gun for that is to complete the contract with
Transnet.
On that basis I'll move to slide number 4. In relation to our
negotiations with Transnet, one of the major obstacles we've
had in our discussions with them has been their insistence
that they first complete feasibility studies associated with
allocations from the Waterberg. They would not make a firm
commitment until those studies were completed. For some time,
I guess, we have been bashing our heads up against each other
in respect to a firm allocation. What we have done is reached
a compromise with them. We, ourselves, do not have a concern
with the capacity available in the system, particularly in
respect to our 6 million tonnes. I should add that we are
very firm, we are very committed to signing a take or pay
contract for that. In doing so, I guess, we have asked
Transnet to put a deadline with respect to
their own feasibilities or their own studies, and we've
agreed that, in the case that they haven't completed their
studies by the end of December this year, that our commitment
would become firm.
On that basis we believe that we'd be able to take the
contract to our banks. Firstly, however, we have to complete
tariff negotiations and we just expect that that tariff
should be fair and equitable, basically associated with
charges that they made to other Waterberg operators.
Hopefully in the very near future we should see some
conclusions to these negotiations, in which case we could
then move on.
That being the case we could move to slide number 5 where we
would be talking basically to our banks straight away after
signing the contract, getting them into detailed due
diligence. Total project capex is still about $US750 million
and our plan there is to first secure our project financing,
which would probably cover around about 50 per cent of that
capital requirement based on the indicative offers that we
have received from the project banks. Once we've got that
project financing agreement at least in some form of secure
form, then we'd be able to move to the equity markets to top
up our capital expenditure requirement through an equity
raising. That's the process that would probably take four to
five months after we've signed the Transnet contract.
Just to move on about what we believe is the strengths of the
Project, On to slide 6 - what are the attributes that would
support a successful fundraising, particularly from debt and
equity? Clearly, we have a very large coal deposit, very
shallow overburden. It's a very low-cost mining operation.
Already there's a 745 million tonne bankable reserve defined
within that. It only represents 35 per cent of the total
resource, so it's a significant deposit and, with a long-life
mine, a very low-cost operation.
In conjunction with that, we've secured some long-term export
thermal coal contracts. There is still strong long-term
export thermal coal demand, particularly out of India, and we
have two long-term contracts with Indian companies there, one
for 38 years and another one for 20 years. If we were to
proceed with project funding we would be able to secure
further contracts, but we don't want to over-commit ourselves
at this early stage of the Project.
Now, they're really the two strong attributes that are
supporting, the financiers' interest in the Project. To some
extent there is also a middlings production stream. There is
solid domestic demand from Eskom particularly, and that would
also provide upside to our cash flows. But the critical
elements are the strong export thermal coal demand and,
obviously, the low- cost mining opportunity that presents
itself with our deposit.
I'd like to add, by moving to slide 7, that one of the major
issues associated with our company and our Project has been
this perception of sovereign risk, investing in South Africa.
I'd have to say that I don't particularly see that myself.
Our experience over the last few years has been driven by the
fact that we focused on becoming a very effective BEE in
ourselves, within the Company, and our BEE partners are very
much a singular part of our whole
management structure. So we operate as one and, I guess, the
effectiveness of that has been that we've been able to move
through and facilitate all the necessary approvals through
the various departments and bureaucracies that are required,
obviously, the three big ticket items being the mining right,
receiving our development consent, which is a life of mine
development consent which enables not only the construction
of the mine but also the rail link, and, most recently, the
issuing of the water use licence. There will be other
processes that we have to go through, but I have to say it
certainly signifies an effective BEE when the formula is
approached in the right sort of form.
So that wraps up the part of the presentation I'd like to
talk about. In closing though, in terms of confidence,
Transnet have expressed a strong desire to open up the
Waterberg. It is definitely one of the future areas for
development within South Africa, and there's been a big
commitment by them as well as the government. Signing a take
or pay contract with us is clearly low-hanging fruit for them
and it should be something that they ought to grasp because
it would not only underwrite our Project but also underwrite
one of the first developments of this major area for the
country.
I would encourage people to walk through the remainder of the
presentation off our website. We do provide in there some
updated material on the status of the mine and a lot of the
detail that we've been going through in order to make sure
that it is truly a deliverable Project. Thank you very much.