30 May 2017

ASX Limited

Level 40, Central Park

152-158 St George's Terrace Perth WA 6000

I am pleased to attach the following items for immediate release to the market:

  1. DeGrussa Mine Plan, Ore Reserve and Mineral Resource Update; and

  2. Resources Rising Stars Presentation. Yours sincerely,

Matt Fitzgerald Chief Financial Officer and Company Secretary

Level 1, 31 Ventnor Avenue

PO BOX 1495

T

+61 8 6430 3800

WEST PERTH WA 6005 AUSTRALIA

WEST PERTH WA 6005

  • AUSTRALIA

F

+61 8 6430 3849

ABN 55 105 154 185

www.sandfire.com.au

E

admin@sandfire.com.au

DEGRUSSA MINE PLAN, ORE RESERVE AND MINERAL RESOURCE UPDATE Highlights
  • Updated Mine Plan, incorporating the Monty Mine and OSPA (100% basis):
    • Total 7.0Mt grading 5.1% Cu and 1.6g/t Au for 359,000t of contained copper and 368,000oz of contained gold;

    • DeGrussa's 1.6Mtpa concentrator to be fed from DeGrussa at 1.2-1.3Mtpa from mid-

      CY2019 to allow ore from Monty to be blended in at a rate of 0.3-0.4Mtpa; and

    • Sandfire will purchase Talisman Mining Limited's ("TLM") 30% share of the Monty JV ore under an Ore Sale and Purchase Agreement (OSPA).

  • Updated Underground Ore Reserve, incorporating the Monty Mine (70% basis):
    • 6.8Mt grading 5.0% Cu and 1.6g/t Au for 337,000t of contained copper and 355,000oz of contained gold (including UG ore on surface stockpiles); and

    • Updated DeGrussa Ore Reserve based on underground mining depletion and mining modifying factors.

  • Open Pit Ore Reserve:

o 2.8Mt grading 1.2% Cu and 1.0g/t Au for 35,000t of contained copper and 84,000oz of contained gold (copper oxide ore stockpiled at surface).

  • Updated Underground Mineral Resource, incorporating the Monty Mine (70% basis):
    • 7.2Mt grading 6.0% Cu and 1.9g/t Au for 434,000t of contained copper and 450,000oz of contained gold; and

    • Updated DeGrussa Mineral Resource based on mining depletion, sterilisation and resource definition drilling.

Note: DeGrussa stated as at 31 December 2016; Monty stated as at 31 March 2017

Sandfire Resources NL (ASX: SFR, "Sandfire") is pleased to announce an updated Mine Plan, Mineral Resource and Ore Reserve for the 1.6Mtpa DeGrussa Copper-Gold Mine.

The updated Mine Plan, Mineral Resource and Ore Reserve includes the DeGrussa, Conductor 1, Conductor 4 and Conductor 5 lenses at DeGrussa as well as the Monty deposit (70% SFR: 30% TLM under the Springfield JV). These deposits underpin the mine life of the DeGrussa operation through until CY2021.

Figure 1 - Monty Copper-Gold Project Location (WA)

Table 1 and Table 2 summarises a combined DeGrussa and Monty Mine Plan, Ore Reserve and Mineral Resource by mining tonnes, key output and orebody (refer Appendix 1 and 2 for full details of the Ore Reserve and Mineral Resource).

Table 1 - DeGrussa and Monty Mine Plan, Ore Reserve and Mineral Resource

DeGrussa and Monty

Tonnes

(Mt)

Copper

(%)

Gold (g/t)

Contained Copper (t)

Contained Gold (oz)

Monty basis

Mine Plan**

7.0

5.1

1.6

359,000

368,000

100%

Ore Reserve**

9.5

3.9

1.4

372,000

439,000

70%

Mineral Resource*

10.1

4.6

1.6

469,000

539,000

70%

Table 2 - DeGrussa and Monty Mine Plan, Ore Reserve and Mineral Resource by Orebody

DeGrussa and Monty

Tonnes

(Mt)

Stockpiles

(Mt)

DG (Mt)

C1 (Mt)

C4 (Mt)

C5 (Mt)

Monty (Mt)

Monty basis

Mine Plan**

7.0

0.1

0.6

2.2

1.8

1.6

0.8

100%

Ore Reserve**

9.5

2.9

0.6

2.1

1.7

1.6

0.6

70%

Mineral Resource*

10.1

3.0

0.5

2.5

1.8

1.6

0.7

70%

Notes:

Calculations have been rounded to the nearest: 1,000t; 0.1% Cu grade; and 1,000t Cu metal and 0.1g/t Au grade; and 1,000oz Au metal. Differences may occur due to rounding.

* Mineral Resource for DeGrussa is based on a 1.0% Cu cut-off and allows for mining depletion and sterilisation as at 31 December 2016. Mineral Resource for Monty is based on a 1.0% Cu cut-off.

** Mine Plan and Ore Reserve include mining dilution and mining recovery

Mine Plan

The Mine Plan is Sandfire's internal plan which schedules forecasted production parameters, operating and capital works programs. It is developed with the assistance of both internal Sandfire employees and external consultants and includes both Mineral Resource and Ore Reserve. Table 3 summarises the underground mining and processing plans of the DeGrussa and Monty Mines.

Underground Mine

Tonnes

(Mt)

Copper

(%)

Gold (g/t)

Contained Copper (t)

Contained Gold (oz)

DeGrussa

6.2

4.6

1.6

286,000

330,000

Monty (100% basis)

0.8

9.4

1.5

74,000

38,000

Total

7.0

5.1

1.6

359,000

368,000

Monty is included in the Mine Plan on a 100% basis. Sandfire holds 70% of Monty under the unincorporated Springfield JV, and has entered into an Ore Sale and Purchase Agreement (OSPA) with Talisman Mining Limited to purchase its 30% of ore mined by the JV - refer Sandfire's ASX announcement "Positive Monty Feasibility Study Paves Way for Development of New High-Grade Copper Mine" released dated 6 April 2017.

The Company continues to incorporate Inferred Mineral Resources from portions of Conductor 1, Conductor 4 and Conductor 5 and Monty into its Mine Plan process due to the geological continuity and high copper grade tenor of these deposits.

A zone of mineralisation at DeGrussa associated with Conductor 5 adjacent to the Shiraz and Merlot Faults and the water-bearing dolomite unit has not been included in the Mineral Resource, Ore Reserve or Mine Plan. Further diamond drilling is required to assess the extent and nature of this mineralisation and the potential for mining. It is planned for this drilling to start in Q1 FY2018 following commissioning of a new underground pump system.

Production from the DeGrussa mine is currently sourced from Conductor 1, Conductor 4, Conductor 5 and DeGrussa. The Mine Plan confirms underground mine production continuing at the current rate of 1.6Mtpa until mid-CY2019, when it will progressively reduce to allow capacity for ore from Monty to be blended. This strategy will provide alignment of the production profiles of the two mines through to mid-2021.

Ore Reserve Update

The DeGrussa Ore Reserve has been updated based on the December 2016 Mineral Resource model, depletions and mining modifying factors as applicable up to 31 December 2016. Ore Reserves for Monty are as outlined in Sandfire's ASX announcement "Positive Monty Feasibility Study Paves Way for Development of New High-Grade Copper Mine" released dated 6 April 2017, with both summarised and combined in Table 4.

Table 4 - Ore Reserve

DeGrussa Mine Ore Reserve

Tonnes

(Mt)

Copper

(%)

Gold (g/t)

Contained Copper (t)

Contained Gold (oz)

Underground Mine (includes stockpiles)

6.1

4.6

1.7

281,000

326,000

Stockpiles (Open Cut)

2.8

1.2

1.0

35,000

84,000

December 2016 - Total

8.9

3.6

1.4

316,000

410,000

Monty Mine Ore Reserve (70% basis)

Tonnes

(Mt)

Copper

(%)

Gold (g/t)

Contained Copper (t)

Contained Gold (oz)

Underground Mine

0.6

8.7

1.4

56,000

29,000

March 2017 - Total

0.6

8.7

1.4

56,000

29,000

Total Ore Reserve

Tonnes

(Mt)

Copper

(%)

Gold (g/t)

Contained Copper (t)

Contained Gold (oz)

Underground Mine (includes stockpiles)

6.8

5.0

1.6

337,000

355,000

Stockpiles (Open Cut)

2.8

1.2

1.0

35,000

84,000

Total

9.5

3.9

1.4

372,000

439,000

Mineral Resource Update

The DeGrussa Mineral Resource has been updated as at 31 December 2016 based on mining depletions, sterilisation and resource definition drilling. Mineral Resources for Monty are as outlined in Sandfire's ASX announcement "Maiden High-Grade Mineral Resource for Monty VMS Deposit: 99,000t Copper and 55,000oz Gold" released dated 13 April 2016, with both summarised and combined in Table 5:

Sandfire Resources NL published this content on 30 May 2017 and is solely responsible for the information contained herein.
Distributed by Public, unedited and unaltered, on 29 May 2017 23:06:08 UTC.