On 26 March, the Solitaire pipe-laying vessel started on the first stage of the Polarled installation project. The 482-kilometre long pipeline will transport gas from the Aasta Hansteen field in the Norwegian Sea to Nyhamna in western Norway.

One of the world's largest pipe-laying vessels, Solitaire, has started laying the Polarled gas pipeline. (Photo: Shell)

Statoil is operator during the development of the Polarled project and therefore responsible for laying the pipeline between Aasta Hansteen and Nyhamna. As operator for the gas plant, Shell is responsible for preparing the Nyhamna processing plant for gas reception.

Håkon Ivarjord, MPR's project venture manager. (Photo: Ivar Langvik)

"I am pleased to note that the pipeline is now connected to the Nyhamna processing plant. The pipeline pull-in to Nyhamna is an important milestone to the project and the Polarled licensees," says Håkon Ivarjord, MPR's project venture manager.

World record

The gas pipeline will be laid in water depths of up to 1265 metres. Even though smaller pipelines have been laid in waters exceeding this depth, this is the first time a gas pipeline measuring 36 inches in diameter is being installed at such water depth.

"When the pipeline is laid, we will install an end manifold with connection points for Aasta Hansteen and any future fields. Six T-joints on the pipeline for any further connections are also a unique feature of Polarled," says Alfred Øijord, PRO's project manager for Polarled.

Considerable cost reductions have so far been made by the Polarled Pipeline Project compared to the initial PAD estimate, as the company has obtained lower prices from the suppliers than originally calculated due to synergy effects with other pipeline projects and strict change and cost control.

Strategic

The Norwegian Sea has no infrastructure for gas, and efforts have been made over several years to develop various alternative gas transport solutions. The Polarled pipeline is the first pipeline to take the Norwegian gas infrastructure across the Arctic Circle.

The Polarled pipe-laying operation is scheduled to be completed by the end of August. (Photo: Shell)

"Polarled will have great and strategic impact on the future development of the region. The new pipeline will open a new gas province and stimulate exploration and resource development, which will fortify Statoil's position as an exporter of gas to Europe," says Jan Heiberg, acting head of the pipelines and processing unit of MPR asset management.

A pioneer

Aasta Hansteen is one of the largest and most complex industrial projects in Europe, and the first deepwater project in the Norwegian Sea.

The field development will include a so-called Spar platform. It will be the world's biggest of its kind and also the first platform of this type on the Norwegian continental shelf.

The Polarled pipe-laying operation is scheduled to be completed by the end of August. Nyhamna will be ready to receive Aasta Hansteen gas in 2017. When the pipeline comes on stream, Gassco will be operator for the pipeline and for the Nyhamna gas processing plant.

Published 2015-03-27, 09:23 CET. Updated 2015-03-27, 09:30 CET.

Facts about Aasta Hansteen

Location: Nearly 1300 metres below the sea surface, 300 kilometres west of Bodø

Operations organisation: Harstad

Port of departure: Brønnøysund

Recoverable reserves: 47 billion standard cubic metres of gas and some condensateFacts about Snorre 2040

Facts about Polarled

Capacity: Up to 70 million standard cubic metres of gas per day (MSm3/d)

Production: Pipeline: Japan; corrosion coating: Malaysia; concrete coating and shipping: Mo i Rana

Licensees: Statoil, Petoro, OMV, Shell, TOTAL, DEA Norge, ConocoPhillips, Edison, Maersk Oil, GDF SUEZ, Wintershall

distributed by