Terna communicates that at 15:22 today, power was restored to the primary station in the Teramo industrial area. The high-voltage infrastructures throughout the provinces of Abruzzo have been returned to normal operating conditions.

There is a single problem outstanding on a high-voltage line in the area north of Teramo which Terna technicians are currently working to resolve.

As critical weather conditions persist, over 150 Terna technicians continue to monitor the infrastructures despite the problematic conditions on the ground, coordinating with electricity distribution companies, national and local institutions, the Civil Protection Authority and the police.

Terna Rete Elettrica Nazionale S.p.A. published this content on 19 January 2017 and is solely responsible for the information contained herein.
Distributed by Public, unedited and unaltered, on 20 January 2017 09:13:08 UTC.

Original documenthttp://www.terna.it/Document-Details/Terna_High_Voltage_power_restored_to_the_Teramo_industrial_area.aspx

Public permalinkhttp://www.publicnow.com/view/FB6B5A51DA7CC621B59B7A72EA0210995333EDB0