Log in
E-mail
Password
Remember
Forgot password ?
Become a member for free
Sign up
Sign up
Settings
Settings
Dynamic quotes 

4-Traders Homepage  >  Equities  >  Tokyo  >  Tokyo Electric Power Company Holding Inc    9501   JP3585800000

SummaryChartsNewsAnalysisCalendarCompanyFinancialsConsensusRevisions 
News SummaryMost relevantAll newsSector news 

Tokyo Elec. Power : (Oct 26,2011)Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, Oct. 26)

share with twitter share with LinkedIn share with facebook
share via e-mail
0
10/26/2011 | 10:10pm CEST
*Updates are underlined

All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down.

Unit 1 (Shut down)
- Explosive sound and white smoke were confirmed after the big quake 
  occurred at 3:36 pm on March 12. It was assumed to be hydrogen explosion.
- At 3:37 pm on March 25, we started injecting freshwater to the reactor 
  and are now injecting fresh water by a motor driven pump powered by the 
  off-site transmission line.
  Water is currently injected at approx. 3.8 m3/h through reactor feed 
  water system piping arrangement. 
- We commenced injection of nitrogen gas into Primary Containment Vessel at 
  1:31 am on April 7.
- At 11:22 am on August 10, we started cyclic cooling for the water in the 
  spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System. 
- At 1:17 pm on October 26, we started cutting off the designated piping 
  after confirming that the hydrogen density inside the piping for cooling 
  in case of reactor shutdown was less than 0.1 %, as one of the 
  construction work to install gas monitoring system inside the Primary 
  Containment Vessel.

Unit 2 (Shut down)
- At approximately 6:00 am on March 15, an abnormal noise began emanating 
  from nearby Pressure Suppression Chamber and the pressure within the 
  chamber decreased. 
- At 10:10 am on March 26, we started injecting freshwater to the reactor 
  and are now injecting fresh water by a motor driven pump powered by the 
  off-site transmission line. 
- At 2:59 pm on September 14, we started injecting water to the reactor 
  through core spray system water injection piping arrangement in addition 
  to the water injection through reactor feed water system piping 
  arrangement.
- Water is currently injected at approx. 3.0m3/h through reactor feed water 
  system piping arrangement, and at approx. 7.0 m3/h through core spray 
  system water injection piping arrangement.
- At 5:21 pm on May 31, we started cyclic cooling for the water in the 
  spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System.
- At 8:06 pm on June 28, we started injecting nitrogen gas into the Primary 
  Containment Vessel.
- At 1:05 pm on October 26, we started nitrogen purge of the designate 
  system after confirming that hydrogen is stored with the density of 6.5 % 
  when connecting piping arrangements on October 20, 2011, as one of the 
  construction work to install gas monitoring system inside the Primary 
  Containment Vessel. We finished the nitrogen purge at 1:42 pm because we 
  confirmed that the hydrogen density was 0%.

Unit 3 (Shut down)
- Explosive sound and white smoke were confirmed at approximately 11:01 am 
  on March 14. It was assumed to be hydrogen explosion.
- At 6:02 pm on March 25, we started injecting fresh water to the reactor 
  and are now injecting fresh water by a motor driven pump powered by the 
  off-site transmission line.
- At 2:58 pm on September 1, we started water injection by core spray 
  system in addition to water injection by the reactor feed water system 
  piping arrangement. 
  Water is currently injected at approx. 2.0 m3/h through reactor feed 
  water system piping arrangement, and at approx. 8.1 m3/h through core 
  spray system water injection piping arrangement.
- At 7:47 pm on June 30, we started cyclic cooling for the water in the 
  spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System.
- At 8:01 pm on July 14, injection of nitrogen gas into the Primary 
  Containment Vessel started.

Unit 4 (Outage due to regular inspection)
- At around 6 am on March 15, we confirmed the explosive sound and the 
  sustained damage around the 5th floor rooftop area of Reactor Building.
- At 12:44 pm on July 31, we started cyclic cooling for the water in the 
  spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System. 
- At 11:34 am on August 20, we started an operation of desalination 
  equipment in the spent fuel pool.
- At this moment, we don't think there is any reactor coolant leakage 
  inside the primary containment vessel.

Unit 5 (Outage due to regular inspection)
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 5:00 am on March 19, we started the Residual Heat Removal System Pump 
  in order to cool the spent fuel pool.
- At 2:30 pm on March 20, the reactor achieved cold shutdown.
- At 2:45 pm on July 15, we started the operation of the original Residual 
  Heat Removal System (System B) by its original seawater pump.
- At this time, we don't think there is any reactor coolant leakage inside 
  the primary containment vessel.

Unit 6 (Outage due to regular inspection)
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 10:14 pm on March 19, we started the Residual Heat Removal System Pump 
  of Unit 6 to cool down Spent Fuel Pool.
- At 7:27 pm on March 20, the reactor achieved cold shutdown. 
- At 2:33 pm on September 15, we started separately cooling the reactor 
  through the Residual Heat Removal System and the spent fuel pool through 
  Equipment Cooling Water System and Fuel Pool Cooling System.
- At this time, we don't think there is any reactor coolant leakage inside 
  the primary containment vessel. 

Others
- At around 10 am on June 13, we started the operation of the circulating 
  seawater purification facility installed at the screen area of Unit 2 and 
  3.
- At 8 pm on June 17, we started operation of Water Treatment Facility 
  against the accumulated water. At 6:00 pm on July 2, we started the 
  circulating injection cooling to inject the water, which was treated by 
  the accumulated water treatment system, to the reactors through the 
  buffer tank.
- At 7:41 pm on August 19, we started treatment of accumulated water by 
  parallel operation of one line from the cesium adsorption instrument to 
  the decontamination instrument and the other treatment line of the cesium 
  adsorption instrument No.2. 
- At 2:06 pm on October 7, we started to spray purified accumulated water 
  brought from Unit 5 and 6 continually in order to prevent dust scattering 
  and potential fire outbreaks from the cut down trees.
- At 10:00 am on October 20, we started transferring the accumulated water 
  from the basement of turbine building of Unit 3 to the High Temperature 
  Incinerator Building of Central Radioactive Waste Treatment Facility.
- At 10:12 am on October 20, we started transferring the accumulated water 
  from the basement of turbine building of Unit 2 to the Process Main 
  Building of Central Radioactive Waste Treatment Facility.
- From 5:31 pm on October 25 to 2:01 pm on October 26, we transferred the 
  accumulated water brought from the basement of turbine building of Unit 1 
  to the basement of turbine building of Unit 2. 
- At 10:00 am on October 26, we started transferring the accumulated water 
  from the basement of turbine building of Unit 6 to the temporary tanks. 
- At 9:47 am on October 26, for the water injection to the reactors of 
  Units 1 to 3, we switched from normal water injection line to emergency 
  water injection line, due to the shutoff of facilities for power source 
  reinforcement work. Along with the switching work, we adjusted the amount 
  of water injection from water feeding system to approximately 3.8 m3/h 
  for Unit 1's reactor. Likewise, we adjusted the amount of water injection 
  to Unit 2's reactor to approximately 3 m3/h from water feeding system, 
  and to approximately 8m3/h from Core Spray System.
- On October 26, we replaced the vane to adjust flow amount of water 
  injection line to the Unit 3's reactor in order to improve the ability to 
  control the water injection amount. 

share with twitter share with LinkedIn share with facebook
share via e-mail
0
Latest news on TOKYO ELECTRIC POWER COMPA
09/22 TOKYO ELECTRIC POWER : Taipower to make final decision on gas generator rental p..
09/21 TOKYO ELECTRIC POWER : Radioactive contaminated water could leak after typhoon p..
09/20 TOKYO ELECTRIC POWER : Gov't to set up panel to discuss scrapping Fukushima plan..
09/07 TOKYO ELECTRIC POWER : Japan's ex-leader backs sick US sailors who blame radiati..
09/02 TOKYO ELECTRIC POWER : Expert plays down TEPCO ban of term "meltdown" in nuclear..
09/02 TOKYO ELECTRIC POWER : Plant operator detects increase in temperature in ice wal..
08/30DJTOKYO ELECTRIC POWER : Typhoon Lionrock Crosses Northern Japan
08/29 TOKYO ELECTRIC POWER : Fukushima Nuclear Plant Prepares for Typhoon
08/29DJTyphoon Lionrock Closes In on Japan
08/25 INVITING APPLICATIONS : Proposals on Expertise and Technology Applicable to Deco..
More news
Sector news : Electric Utilities - NEC
09/23DJFed Targets Big Bank Commodity Lines
09/22DJCharlotte Authorities Seek to Restore Order After Two Nights of Violence
09/22DJDUKE ENERGY : Charlotte Authorities Seek to Restore Order After Night of Protest..
09/22DJTotal Cuts Investments, Costs Further to Lift Profitability
09/19DJNEXTERA ENERGY : Sweetens Deal for Energy Future's Oncor
More sector news : Electric Utilities - NEC
News from SeekingAlpha
08/31 WALL STREET BREAKFAST : Eurozone Economic Figures Fail To Budge
08/31 Tepco soars after governor drops re-election bid
08/30 WALL STREET BREAKFAST : Apple Slammed In EU Tax Crackdown
08/30 Japan braces for arrival of Typhoon Lionrock
07/05 A YEAR OF SCANDAL : The Beginning Of The End Of Cronyism In Japan?
Advertisement
Financials ( JPY)
Sales 2017 5 550 417 M
EBIT 2017 -
Net income 2017 160 961 M
Debt 2017 4 993 619 M
Yield 2017 -
P/E ratio 2017 4,96
P/E ratio 2018 5,63
EV / Sales 2017 1,02x
EV / Sales 2018 0,98x
Capitalization 686 196 M
More Financials
Chart TOKYO ELECTRIC POWER COMPA
Duration : Period :
Tokyo Electric Power Compa Technical Analysis Chart | 9501 | JP3585800000 | 4-Traders
Full-screen chart
Technical analysis trends TOKYO ELECTRIC PO...
Short TermMid-TermLong Term
TrendsBullishBearishBearish
Technical analysis
Income Statement Evolution
More Financials
Consensus
Sell
Buy
Mean consensus OUTPERFORM
Number of Analysts 4
Average target price 620  JPY
Spread / Average Target 45%
Consensus details
EPS Revisions
More Estimates Revisions
Managers
NameTitle
Naomi Hirose Executive President & Representative Director
Fumio Sudo Chairman
Makoto Takahashi IR Contact, Manager-Accounting & Finance Group
Hiroshi Yamaguchi Executive Vice President, Head-Technology & Safety
Toshihiro Sano Representative Director & Executive Vice President
More about the company
Sector and Competitors
1st jan.Capitalization (M$)
TOKYO ELECTRIC POWER C..-38.03%6 788
DUKE ENERGY CORP15.59%56 851
SOUTHERN CO14.40%52 390
DOMINION RESOURCES, IN..13.85%48 190
IBERDROLA SA-8.55%42 781
KOREA ELECTRIC POWER C..--.--%34 936
More Results