Press Release (Mar 10,2013)
Status of TEPCO's Nuclear Power Stations after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (Daily Report as of 3:00 PM, March 10)


Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March 11, 2011, TEPCO's facilities including our nuclear power stations have been severely damaged. We deeply apologize for the anxiety and inconvenience caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on April 17, 2011, we have compiled the roadmap towards restoration from the accident and on July 19 we accomplished the Step1 target "Radiation dose is in steady decline". Then on December 16 we confirmed the accomplishment of the Step 2 target "Release of radioactive materials is under control and radiation doses are being significantly held down".
In addition, on December 21, 2011, we have compiled the "Mid-to-long-Term Roadmap toward the Decommissioning of Fukushima Daiichi Nuclear Power Units 1-4, TEPCO".
In addition to the maintenance of the plant's stable condition, we will implement Mid-to-Long Term countermeasures towards the decommissioning of Fukushima Daiichi Nuclear Power Units 1-4 to enable evacuees to return to their homes as soon as possible and reduce the anxiety of the people in Fukushima and the whole nation as soon as possible.

Below is the status of TEPCO's nuclear power stations (Fukushima Daiichi and Fukushima Daini).

* The updates are underlined.

[Fukushima Daiichi Nuclear Power Station]
·Unit 1 to 4: Abolishment (April 19, 2012)
·Unit 5 to 6: Outage due to regular inspections before the earthquake

-During the reliability improvement work to be implemented on Unit 2 feed water system scheduled in March, the reactor water injection from the feed water system is planned to be suspended. In prior to the reliability improvement work implementation, water injection from the feed water system was suspended with all amount injected from the reactor core spray system for the purpose of confirming that there is no significant impact on reactor cooling. At 1:16 PM on February 20, the amount of water injection from the feed water system was decreased from approx. 1.9m3/h to 0m3/h and the amount of injection from the reactor core spray system was increased from approx. 3.4m3/h to approx. 5.5m3/h. As no significant fluctuation was found with reactor cooling due to this, the amount of water injection has been adjusted as follows at 7:30 PM on February 22. Feed water system: Increased from 0m3/h to approx. 2.0m3/h, reactor core spray system: Decreased from approx. 5.5m3/h to approx. 3.5m3/h. In order to perform the reliability improvement work at Unit 2, the reactor water injection amount was adjusted as follows at 2:21 PM on March 10. Feed water system: Decreased from approx. 1.9m3/h to 0m3/h, reactor core spray system: Increased from approx. 3.5m3/h to approx. 5.5m3/h.

[Fukushima Daini Nuclear Power Station]
·Unit 1 to 4: Shutdown due to the earthquake.

Appendix: Past Progress (As of 3:00 pm, on March 10, 2013) (PDF 690KB)
Appendix: Past Progress (From March 11, 2011 to December 31, 2011) (PDF 523KB)
* Revised past progress

The aforementioned attachments are only available in Japanese.
We apologize for any inconvenience this may cause.