INSTALLATION LICENSE GRANTED FOR EDP TRANSMISSÃO S.A. TRANSMISSION LINE

São Paulo, February 19th, 2018 - EDP - Energias do Brasil S.A. ("EDP" or "Company") (B3: ENBR3) informs its

shareholders and the market in general that the Instituto Estadual de Meio Ambiente e Recursos Hídricos (IEMA)1 has granted, on February 09th, 2018, the Installation License ("IL") for the Company EDP Transmissão S.A. referring to the 230 KV Transmission Line SE Linhares II - SE São Mateus II and São Mateus II Substation, lot 24 of the 2nd Stage of Auction 013/2015 of Public Power Transmission Lines.

The acquisition of the IL was expected for October, 2018, as per the schedule considered for the auction, being anticipated against the previous schedule. The construction work will take place immediately.

RAP2*

R$ 20.7 Million

Early Completion considered in Auction

10 months

ANEEL Operation Start

Aug/2020

Estimated Capex*

R$ 116 million

Transmission Line Supplier

Engelmig

Substation Supplier

GE

*As of Nov/2016

Miguel Nuno Simões Nunes Ferreira Setas

CEO and IR Director

1 State Institute of Environment and Water Resources ² Annual Permitted Revenue