Microsoft Word - 20151030 FND September 15 Quarterly Final


For ASX Market Release: 30 October 2015


Quarterly Activities Report - September 2015

HIGHLIGHTS

Wetar Copper Project


  • Copper cathode produced for the quarter was 425 tonnes. Sales were 406 tonnes at an average price of US$2.38/lb

  • Earthworks completed on a number of major structures

  • Coastal infrastructure construction progresses rapidly

  • 25,000 t.p.a. copper cathode SX-EW plant remains on track for commissioning in Q1 2016

  • The 12 month rolling LTIFR and Injury Severity rates remain at zero

    Corporate

  • A further US$35.0 million drawn under the Term Loan Facility and VAT Working Capital Facility

  • Hedge book (copper and diesel fuel) valued at US$30.6 million as at 30 September 2015

  • At 30 September cash on hand was AUD$38.9 million and unused project finance facilities were US$108.0 million


Managing Director Barry Cahill commented: 'It is pleasing to report the significant progress made on the expansion project during the quarter, which remains on budget and on track for production in Q1 2016. During the December quarter, the expansion project will really take shape as we advance into an intensive construction phase on the 25,000

t.p.a SX-EW plant.'


Contacts: Mr Gary Comb

Non-Executive Chairman

Mr Barry Cahill Managing Director Mr James Wentworth Chief Financial Officer


Phil Retter Investor Relations NWR Communications

phil@nwrcommunications.com.au

T: +61 407 440 882


Perth Office: Level 1, 5 Ord Street West Perth WA 6005 T: +61 8 6555 3996

F: +61 8 6555 3998

E: info@findersresources.com

ASX Code: FND

www.findersresources.com


WETAR COPPER PROJECT (FINDERS 72%)

3,000 t.p.a. SX-EW plant Production Report

The 3,000 t.p.a. plant operated as expected during the quarter as summarised in the following table.

Table 1: Wetar Quarterly Copper Production


Full Year 2014 Total

March 15 Quarter

June 15 Quarter

September 15 Quarter

YTD 2015

Total

Ore stacked

t

139,587

-

44,540

42,898

87,438

Grade

% Cu

2.42

-

1.72

1.59

1.65

Metal stacked

t Cu

3,385

-

764

682

1,446

Copper stripped

t Cu

1,416

104

203

425

732

Copper sold

t Cu

1,306

127

76

406

609

Copper sale price

US$/lb Cu

2.88

2.63

2.77

2.38

2.48



Good progress was made on the Gold Pit Leach Pad (GPLP) during the quarter with 42,898 tonnes ore stacked. Stacking on the GPLP will be suspended after commissioning of the new crusher in October as the focus switches to stacking the KKV Heap leach Pad in readiness for the commissioning of the 25,000 t.p.a. SX-EW plant.

Temperatures on the GPLP heaps are within the required range and work continues on neutralising the acid in solution. The success of these efforts is reflected in the improved production performance (copper stripped) in the Table 1.


Image 1 - Stacking on the GPLP heaps


The new crusher arrived on site at quarter's end and was in the process of being commissioned on the KKV Heap Leach Pad during October. Commissioning involved crushing the bedding layer prior to ore stacking.


Image 2 - New crusher being commissioned on KKV leach pad


Copper cathode produced has continued to be exported as LME Grade A copper cathode without any issues during the quarter.


25,000 t.p.a. SX-EW plant Construction Progress

Mine construction and related activities advanced in accordance with expectations during the September quarter.

Earthmoving activity increased following mobilisation of a second earthmoving fleet, with Stormwater Pond Three advancing to the floor of the underdrainage. Once the underdrainage is installed, the dam walls will be shaped and compacted to allow installation of the liner.

The first cell of the KKV Heap Leach Pad, which is the largest pad adjacent to the 25,000 t.p.a SX-EW plant site, is lined and the new crusher is currently crushing the initial bedding layer.

Earthworks at Stormwater Pond Two have been completed and the pond is currently being lined. Once completed the pumps and necessary pipework will be installed and the pond will be ready for use.

The 25,000 t.p.a. SX-EW plant raffinate pond located adjacent to the plant site is lined and ready for use.

The final cut on the neutralisation pad is currently being undertaken prior to handover for the commencement for concrete work. The cut required widening of the main haul road to allow the pad to be enlarged. During the excavation of the open pit haul ramp onto the main access ramp a small quantity of additional ore was excavated from outside the ore reserve.


Image 3 - Lining of Stormwater Pond 2 commences


Pouring of concrete to establish the foundations for the 25,000 t.p.a SX-EW plant continued. Tank refurbishment has been completed on a number of the major tanks. The fibreglass contractor's focus has now turned to the construction of the new settler and the electrolyte recirculation tank. Refurbishment of the EW cells continues.


Image 4 - Foundations for the EW electrolyte circulation tank


The fibreglass contractor completed the refurbishment of the SX settler tanks and the lifting of these tanks into position on the SX site commenced during the quarter.

distributed by