02.09.14

Sonyachna Brama residential complex construction status update

During the period of 1-31 August 2014 construction works at the third and fourth phases of Sonyachna Brama residential complex (73-79 Lomonosova str., Kyiv) were carried out according to the schedule.

At the third phase of construction, landscaping of the area as well as asphalt and paving slabs laying works have been completed. Finishing works in the common areas of building B-13 are 95% complete.

At the fourth phase of construction, construction works were being carried out in two residential buildings. In building B-6, the following works took place:

-                  bricklaying of external walls - 100% complete;
-                  roofing  - 60% complete;
-                  windows installation - 50% complete.

In building B-7, the following works took place:

-                 construction of the monolith frame of technical premises;
-                brick laying works at the level of the 11th-12th floors.