STOCK EXCHANGE RELEASE
Talvivaara Mining Company Plc
11 June 2010
Second production line at metals recovery plant successfully commissioned
Talvivaara Mining Company Plc is pleased to announce that the second production
line at its metals recovery plant was successfully commissioned on 9 June with
zinc sulphide precipitation, followed by nickel sulphide precipitation on 10
June. The production line is currently operating well and will be ramping up
towards its full capacity during the upcoming months.
CEO Pekka Perä commented: "We are delighted that the second production line has
been brought on stream as planned, after a smooth and successful commissioning
process. This is a crucial milestone in our ramp up and gives us the much needed
capacity to take our production volumes to their planned levels."
ENQUIRIES
Talvivaara Mining Company Plc Tel: +358 20 7129 800
Pekka Perä, CEO
Saila Miettinen-Lähde, CFO
Timo Laatio, Investor Relations
Merlin PR Tel: +44 207 653 6620
David Simonson
Anca Spiridon
[HUG#1423247]