For personal use only

QUARTERLY ACTIVITIES REPORT

June 2022

26 July 2022

GME Resources Limited ("GME" or "the Company") provides an update on its activities completed during the June 2022 quarter.

Highlights

  • Updated PFS Outcomes delivers substantial increases to projected economic returns from development of NiWest Nickel Cobalt Project ("NiWest" or "the Project").
  • GME Board seeking to proceed to Definitive Feasibility Study (DFS) on NiWest, Scope of work and costing for study currently being developed.
  • Subsequent to the end of the Quarter, Paul Kopejtka appointed as Managing Director effective from September 2022

NiWest PFS Updated Economics

During the quarter GME Resources Limited ("GME" or "the Company") (ASX: GME) completed an update to the cost estimates and price A$/US$ inputs into the Pre-Feasibility Study ("PFS") for the 100%-owned NiWest Nickel-Cobalt Project in Western Australia. This update, which was finalised and announced on 21 July 2022, has confirmed the robustness of a long-life operation directly producing high-purity nickel and cobalt sulphate products to be delivered into lithium-ion battery raw material markets.

Table 1: Key updated PFS outcomes

Financial metric

PFS

Price Case 1

Price Case 2

Price Case 3

(Aug 2018)

(Jul 2022)

(Jul 2022)

(Jul 2022)

LME nickel price (US$/lb)

7.25

9.00

10.00

11.00

Nickel sulphate premium (%)

10%

10%

10%

10%

LME cobalt price (US$/lb)

25.00

28.50

32.00

35.00

Cobalt sulphate premium (%)

-

-

-

-

A$/US$

0.75

0.70

0.70

0.70

Avg cash opex (post Co credits) (US$/lb Ni)

3.24

3.99

3.79

3.63

Pre-production capex (A$M)

966

1,261

1,261

1,261

Life-of-mine sustaining capex (A$M)

582

742

742

742

Total free cashflow (post-tax) (A$M)

3,342

4,494

5,797

7,067

NPV (ungeared, post-tax, 8% real) (A$M)

791

1,082

1,587

2,079

IRR (ungeared, post-tax)

16.2%

16.5%

19.9%

23.0%

GME Resources Limited | Quarterly Activities Report - June 2022

Page 1 of 13

For personal use only

  1. Incorporates higher nickel and cobalt prices and cost escalation impacts since original PFS completed in mid-2018; current LME spot prices of approx. US$9.80/lb nickel and US$27/lb cobalt.
  1. Mine and process schedule, along with all PFS physical parameters (incl. Ore Reserve), unchanged:
  1. Low-stripopen pit mining and heap leaching followed by highly efficient Direct Solvent Extraction (DSX) to produce low-cost nickel and cobalt sulphate products. Initial 27-year operating life at a nameplate processing capacity of 2.4Mtpa.
  1. Total production of 456kt nickel (in nickel sulphate) and 31.4kt cobalt (in cobalt sulphate). Average annual production of 19.2kt nickel and 1.4kt cobalt over the first 15 years.
  1. Substantial further upside potential from inclusion of Wanbanna, Murrin North, Waite Kauri and Mertondale deposits into NiWest mine schedule to optimise grade profile, increase operating life and/or expand throughput.

(For full details on the NiWest Updated PFS Outcomes refer to ASX announcement 21 July 2022).

Updated PFS outcomes have resulted in GME Board seeking to proceed to Definitive Feasibility Study (DFS) on NiWest; scope and cost of works currently under development. Discussions are on going with a number of interested OEM 's who can access detailed information on the NiWest project via the company's data room.

PFS Update

NiWest hosts one of the highest-grade undeveloped nickel laterite Mineral Resources in Australia estimated to contain 85.2 million tonnes averaging 1.03% nickel and 0.06% cobalt (see Table 2). Over 75% of the resource is contained within the Measured and Indicated JORC categories with potential to expand the currently delineated mineralisation with further drilling. (Refer APPENDIX 1 NiWest Resources and Reserves)

Table 2: NiWest Mineral Resource estimate

Classification

Tonnes

Ni Grade

Co Grade

Ni Metal

Co Metal

(Mt)

(%)

(%)

(kt)

(kt)

Measured

15.2

1.08

0.064

165

9.8

Indicated

50.4

1.04

0.068

527

34.5

Inferred

19.5

0.95

0.057

186

11.0

Total

85.2

1.03

0.065

878

55.4

Columns may not total exactly due to rounding errors; tonnages are reported as dry tonnage. For full details refer to GME ASX release dated 8 August 2018, NiWest Nickel-Cobalt Project Pre-Feasibility Study. GME confirms that it is not aware of any new information or data that materially affects the Mineral Resource estimate information included in that release. All material assumptions and technical parameters underpinning the Mineral Resource estimate in that release continue to apply and have not materially changed.

GME Resources Limited | Quarterly Activities Report - June 2022

Page 2 of 13

For personal use only

An extensive PFS was completed on NiWest and released in mid-2018, including declaration of a maiden Ore Reserve ("PFS 2018"). This study demonstrated the technical and economic robustness of a long-life operation directly producing high-purity nickel and cobalt sulphate products to be delivered into high-growthlithium-ion battery raw material markets. For full details of the PFS 2018, refer to GME ASX release dated 2 August 2018, NiWest Nickel- Cobalt Project Pre-FeasibilityStudy.

Figure 1: NiWest Project location showing individual deposit areas and proximity to infrastructure

As previously announced (refer GME ASX release dated 8 April 2022, NiWest Nickel-CobaltProject - PFS Update Commenced), GME, in conjunction with its key consultants, has undertaken an update of the cost and metal/A$/US$ price assumptions utilised in the PFS 2018. All physical parameters from the PFS 2018 remain unchanged as part of this exercise, including the mine and process schedule and the Ore Reserve. For a summary of key modifying factors within the Updated PFS process, refer to Appendix A of the ASX release 21 July 2022 (Updated PFS Outcomes for NiWest Nickel/Cobalt Project).

The key physical parameters (remain unchanged) from the PFS 2018 are presented in Table 3 and Figure 2.

GME Resources Limited | Quarterly Activities Report - June 2022

Page 3 of 13

For personal use only

Table 3: Key PFS 2018 physical and operational outcomes

Physical Parameters

Unit

First 15 years

LOM total

Construction and Ramp-up

Construction period (incl. 6 months mining)

months

na

24

Heap pad and plant ramp-up phase

months

na

20

Mining

Mining activities

years

15

20

Ore mined

Mt

54.0

64.9

Waste mined

Mt

115.2

132.9

Strip ratio

waste:ore

2.1

2.0

Processing

Ore processed

Mt

36.0

64.9

Processing life

years

15.0

27.1

Nickel head grade

% Ni

1.05

0.91

Cobalt head grade

% Co

0.071

0.058

Steady-state nickel recovery

%

79

79

Steady-state cobalt recovery

%

85

85

Contained nickel produced

kt

288

456

Nickel sulphate produced (99.95% purity)

kt

1,290

2,044

Contained cobalt produced

kt

21.0

31.4

Cobalt sulphate produced (>99.9% purity)

kt

99.9

149.9

GME Resources Limited | Quarterly Activities Report - June 2022

Page 4 of 13

Figure 2: NiWest nickel and cobalt production (contained in sulphates)

only

25.0

Nickel (in nickel sulphate)

Cobalt (in cobalt sulphate)

outputcobaltand(kt)

20.0

High-grade extensional

upside potential

15.0

use

10.0

Nickel

5.0

1-Y Y0 Y1 Y2 Y3

Y4 Y5 Y6 Y7 Y8 Y9 Y10 Y11 Y12

Y13 Y14 Y15 Y16 Y17 Y18 Y19

Y20 Y21 Y22 Y23 Y24 Y35 Y26 Y27 Y28

0.0

personal

Capital and Operating Costs

Forecast operating and capital costs have been re-estimated through a process of further

prospective supplier interaction and general inflationary scaling. These revised cost estimates

are presented in Tables 4 and 5 and have an estimated band of certainty of +/-35%, with the

pre-production capital estimate also incorporating an increased contingency allowance of

approximately 25%.

Table 4: Operating cost estimates

Item

A$/t ore processed

A$/t Ni produced

A$/lb Ni produced

Updated PFS July 2022

Mining

27.4

3,902

1.77

Processing

81.5

11,623

5.27

For

General and admin

7.2

1,023

0.46

Product distribution

6.8

966

0.44

Total (ex royalties)

122.9

17,514

7.94

PFS 2018

Mining

21.2

3,026

1.37

Processing

63.1

9,000

4.08

General and admin

5.8

825

0.37

Product distribution

5.7

809

0.37

Total (ex royalties)

95.8

13,660

6.19

GME Resources Limited | Quarterly Activities Report - June 2022

Page 5 of 13

This is an excerpt of the original content. To continue reading it, access the original document here.

Attachments

  • Original Link
  • Original Document
  • Permalink

Disclaimer

GME Resources Limited published this content on 25 July 2022 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 25 July 2022 22:38:00 UTC.