For personal use only

ABN 62 009 260 315

Suite 8, Level 3

47 Havelock Street

West Perth WA 6005

PO Box 39

West Perth WA 6872

P: +61 8 9336 3388

www.gmeresources.com.au

ASX ANNOUNCEMENT/MEDIA RELEASE

21 July 2022

Updated PFS Outcomes for NiWest Nickel-Cobalt Project

GME Resources Limited ("GME" or "the Company") (ASX: GME) is pleased to advise of the completion of an update to the cost estimates and price/A$/US$ inputs into the Pre-Feasibility Study ("PFS") for the 100%-owned NiWest Nickel-Cobalt Project in Western Australia ("NiWest" or "the Project"). This update has confirmed the robustness of a long-life operation directly producing high-purity nickel and cobalt sulphate products to be delivered into lithium-ion battery raw material markets

  • Incorporates higher nickel and cobalt prices and cost escalation impacts since original PFS completed in mid-2018; current LME spot prices of approx. US$9.80/lb nickel and US$27/lb cobalt.
  • Mine and process schedule, along with all PFS physical parameters (incl. Ore Reserve), unchanged:
  1. Low-stripopen pit mining and heap leaching followed by highly efficient Direct Solvent Extraction (DSX) to produce low-cost nickel and cobalt sulphate products. Initial 27-year operating life at a nameplate processing capacity of 2.4Mtpa.
    1. Total production of 456kt nickel (in nickel sulphate) and 31.4kt cobalt (in cobalt sulphate). Average annual production of 19.2kt nickel and 1.4kt cobalt over the first 15 years.
  • Update delivers substantial increases to projected economic returns from development of NiWest.

Table 1: Key updated PFS outcomes

Financial metric

PFS

Price Case 1

Price Case 2

Price Case 3

(Aug 2018)

(Jul 2022)

(Jul 2022)

(Jul 2022)

LME nickel price (US$/lb)

7.25

9.00

10.00

11.00

Nickel sulphate premium (%)

10%

10%

10%

10%

LME cobalt price (US$/lb)

25.00

28.50

32.00

35.00

Cobalt sulphate premium (%)

-

-

-

-

A$/US$

0.75

0.70

0.70

0.70

Avg cash opex (post Co credits) (US$/lb Ni)

3.24

3.99

3.79

3.63

Pre-production capex (A$M)

966

1,261

1,261

1,261

Life-of-mine sustaining capex (A$M)

582

742

742

742

Total free cashflow (post-tax) (A$M)

3,342

4,494

5,797

7,067

NPV (ungeared, post-tax, 8% real) (A$M)

791

1,082

1,587

2,079

IRR (ungeared, post-tax)

16.2%

16.5%

19.9%

23.0%

  • Substantial further upside potential from inclusion of Wanbanna, Murrin North, Waite Kauri and Mertondale deposits into NiWest mine schedule to optimise grade profile, increase operating life and/or expand throughput.
  • Updated PFS outcomes have resulted in GME Board seeking to proceed to Definitive Feasibility Study (DFS) on NiWest; scope and cost of works currently under development.

Page 1 of 6

Updated NiWest PFS outcomes

For personal use only

NiWest hosts one of the highest-grade undeveloped nickel laterite Mineral Resources in Australia estimated to contain 85.2 million tonnes averaging 1.03% nickel and 0.06% cobalt (see Table 2). Over 75% of the resource is contained within the Measured and Indicated JORC categories with potential to expand the currently delineated mineralisation with further drilling.

Table 2: NiWest Mineral Resource estimate

Classification

Tonnes

Ni Grade

Co Grade

Ni Metal

Co Metal

(Mt)

(%)

(%)

(kt)

(kt)

Measured

15.2

1.08

0.064

165

9.8

Indicated

50.4

1.04

0.068

527

34.5

Inferred

19.5

0.95

0.057

186

11.0

Total

85.2

1.03

0.065

878

55.4

Columns may not total exactly due to rounding errors; tonnages are reported as dry tonnage. For full details refer to GME ASX release dated 8 August 2018, NiWest Nickel-Cobalt Project Pre-Feasibility Study. GME confirms that it is not aware of any new information or data that materially affects the Mineral Resource estimate information included in that release. All material assumptions and technical parameters underpinning the Mineral Resource estimate in that release continue to apply and have not materially changed.

An extensive PFS was completed on NiWest and released in mid-2018, including declaration of a maiden Ore Reserve ("PFS 2018"). This study demonstrated the technical and economic robustness of a long- life operation directly producing high-purity nickel and cobalt sulphate products to be delivered into high- growth lithium-ion battery raw material markets. For full details of the PFS 2018, refer to GME ASX release dated 2 August 2018, NiWest Nickel-CobaltProject Pre-FeasibilityStudy.

Figure 1: NiWest Project location showing individual deposit areas and proximity to infrastructure

Page 2 of 6

For personal use only

As previously announced (refer GME ASX release dated 8 April 2022, NiWest Nickel-CobaltProject - PFS Update Commenced), GME, in conjunction with its key consultants, has undertaken an update of the cost and metal/A$/US$ price assumptions utilised in the PFS 2018. All physical parameters from the PFS 2018 remain unchanged as part of this exercise, including the mine and process schedule and the Ore Reserve. For a summary of key modifying factors within the Updated PFS process, refer to Appendix A of this release (NiWest Nickel/Cobalt Project, Updated Pre-FeasibilityStudy Executive Summary: Capital and Operating Costs Review, July 2022).

The key physical parameters from the PFS 2018 are presented in Table 3 and Figure 2.

Table 3: Key PFS 2018 physical and operational outcomes

Physical Parameters

Unit

First 15 years

LOM total

Construction and Ramp-up

Construction period (incl. 6 months mining)

months

na

24

Heap pad and plant ramp-up phase

months

na

20

Mining

Mining activities

years

15

20

Ore mined

Mt

54.0

64.9

Waste mined

Mt

115.2

132.9

Strip ratio

waste:ore

2.1

2.0

Processing

Ore processed

Mt

36.0

64.9

Processing life

years

15.0

27.1

Nickel head grade

% Ni

1.05

0.91

Cobalt head grade

% Co

0.071

0.058

Steady-state nickel recovery

%

79

79

Steady-state cobalt recovery

%

85

85

Contained nickel produced

kt

288

456

Nickel sulphate produced (99.95% purity)

kt

1,290

2,044

Contained cobalt produced

kt

21.0

31.4

Cobalt sulphate produced (>99.9% purity)

kt

99.9

149.9

Figure 2: NiWest nickel and cobalt production (contained in sulphates)

25.0

Nickel (in nickel sulphate)

Cobalt (in cobalt sulphate)

(kt)

20.0

High-grade extensional

output

upside potential

15.0

cobalt

Nickel and

10.0

5.0

0.0

Y-1

Y0

Y1

Y2

Y3

Y4

Y5

Y6

Y7

Y8

Y9

Y10

Y11

Y12

Y13

Y14

Y15

Y16

Y17

Y18

Y19

Y20

Y21

Y22

Y23

Y24

Y35

Y26

Y27

Y28

Forecast operating and capital costs have been re-estimated through a process of further prospective supplier interaction and general inflationary scaling. These revised cost estimates are presented in Tables 4 and 5 and have an estimated band of certainty of +/-35%, with the pre-production capital estimate also incorporating an increased contingency allowance of approximately 25%.

Page 3 of 6

Table 4: Operating cost estimates

Item

A$/t ore processed

A$/t Ni produced

A$/lb Ni produced

personal use only

Updated PFS

Mining

27.4

3,902

1.77

Processing

81.5

11,623

5.27

General and admin

7.2

1,023

0.46

Product distribution

6.8

966

0.44

Total (ex royalties)

122.9

17,514

7.94

PFS 2018

Mining

21.2

3,026

1.37

Processing

63.1

9,000

4.08

General and admin

5.8

825

0.37

Product distribution

5.7

809

0.37

Total (ex royalties)

95.8

13,660

6.19

Table 5: Capital cost estimates

Category

Breakdown

Updated PFS

PFS 2018

(A$M)

(A$M)

Direct Costs

Crushing and Heap Leaching

138.0

Processing

193.7

Utilities and Reagents (including acid plant)

312.9

General Infrastructure

42.3

Total Direct Costs

852.6

686.8

Indirect Costs

EPCM

72.7

Owners

9.7

Other Indirects

76.8

Total Indirect Costs

185.3

159.3

Contingency

% of Total Directs (25% 2022, 17.5% 2018)

222.6

120.2

Total Pre-Production Capital

1,260.5

966.3

Life-of-Mine Sustaining Capital

742.0

582.0

Updated NiWest PFS financial projections incorporating these revised cost estimates under several nickel, cobalt and A$/US$ price scenarios are presented in Table 6. The basis for these revised price assumptions is outlined in Appendix A, as with the sensitivity of financial outcomes to key input estimates.

Table 6: Key updated financial projections

For

Financial Outcomes

Unit

PFS

(Aug 2018)

Price Inputs

LME nickel price

US$/lb

7.25

Realised contained nickel price (in sulphate)

US$/lb

8.00

LME cobalt price

US$/lb

25.00

Realised contained cobalt price (in sulphate)

US$/lb

25.00

A$/US$ exchange rate

US$

0.75

Valuation, Returns and Key Ratios

NPV8% (pre-tax, ungeared)

A$M

1,390

NPV8% (post-tax, ungeared)

A$M

791

IRR (pre-tax, ungeared, real basis)

%

21.2

IRR (post-tax, ungeared, real basis)

%

16.2

Payback period (pre-tax)

Years

4.4

Pre-production capital intensity

US$/lb pa

19.5

NPV8% (pre-tax) /Pre-production capex

ratio

1.4

Project life / Payback (pre-tax)

ratio

6.1

Cashflow Summary

Nickel sulphate revenue

A$M

10,730

Cobalt sulphate revenue

A$M

2,309

Total revenue

A$M

13,039

Site operating costs

A$M

-5,859

Product distribution costs

A$M

-369

Royalties - State and private

A$M

-429

Project operating surplus

A$M

6,381

Pre-production capital expenditure

A$M

-966

LOM sustaining capital expenditure

A$M

-582

Case 1

Case 2

Case 3

(Jul 2022)

(Jul 2022)

(Jul 2022)

9.00

10.00

11.00

9.90

11.00

12.10

28.50

32.00

35.00

28.50

32.00

35.00

0.70

0.70

0.70

1,883

2,604

3,306

1,082

1,587

2,079

21.6%

25.9%

29.7%

16.5%

19.9%

23.0%

4.4

3.7

3.3

23.8

23.8

23.8

1.5

2.1

2.6

6.2

7.3

8.3

14,227

15,808

17,389

2,820

3,166

3,463

17,047

18,974

20,852

-7,550

-7,550

-7,550

-441

-441

-441

-559

-627

-693

8,497

10,356

12,168

-1,261

-1,261

-1,261

-742

-742

-742

Page 4 of 6

For personal use only

Project free cashflow (pre-tax)

A$M

4,833

6,494

8,353

10,165

Tax paid

A$M

-1,490

-2,000

-2,556

-3,099

Project net cashflow (post-tax)

A$M

3,342

4,494

5,797

7,067

Unit Cash Operating Costs

Net operating costs (post Co credits)

A$/lb Ni

4.32

5.70

5.42

5.19

Net operating costs (post Co credits)

US$/lb Ni

3.24

3.99

3.79

3.63

All-in-sustaining cost (AISC)

US$/lb Ni

3.68

4.50

4.31

4.15

Further upside opportunities

The PFS is based on mining and processing of solely the economic component of the Measured and Indicated Resources within the Eucalyptus, Hepi and Mt Kilkenny deposits. As such, the Inferred Resources within these three deposits, combined with the entire Wanbanna, Murrin North, Waite Kauri and Mertondale deposits, presents significant potential opportunity to deliver further grade profile optimisation and increase the operating life and/or the production rate of the NiWest Project. Further infill drilling is required to increase the resource classification at each of the respective deposits.

Next Steps

The Updated PFS outcomes have resulted in the GME Board seeking to proceed to a DFS on NiWest. The scope and cost of works for a DFS is currently under development.

GME is also engaged in discussions with potential strategic partner/offtake parties as part of assessing the range of potential ownership, development and funding structures available to the NiWest Project.

For further information please contact:

Jamie Sullivan

Michael Vaughan

Managing Director

Fivemark Partners

Perth, Western Australia

Perth, Western Australia

+61 8 9336 3388

+61 422 602 720

jamiesullivan@gmeresources.com.au

michael.vaughan@fivemark.com.au

About GME Resources Limited:

GME Resources Limited is an ASX-listed exploration and development company with nickel, cobalt and gold interests in Western Australia. GME's principal asset is its 100% owned NiWest Nickel Cobalt Project situated adjacent to Glencore's Murrin Murrin Operations. The Company has completed a Pre-Feasibility Study which has confirmed the technical and economic viability of a heap leach and direct solvent extraction operation at one of the largest undeveloped nickel/cobalt deposits in Australia. Further information is available on GME's website: www.gmeresources.com.au.

Page 5 of 6

This is an excerpt of the original content. To continue reading it, access the original document here.

Attachments

  • Original Link
  • Original Document
  • Permalink

Disclaimer

GME Resources Limited published this content on 20 July 2022 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 20 July 2022 23:03:05 UTC.