Vancouver, British Columbia - CaNickel Mining Ltd. (TSXV: CML) ('CaNickel' or the 'Company') is pleased to release a summary of the results of a current independent Preliminary Economic Assessment ('PEA') and Mineral Resource Estimate ('MRE') on the Company's Bucko Lake Mine ('the Project') located 110 km southwest of Thompson, Manitoba near the Town of Wabowden. The PEA outlines a mine life of 13 years with average annual production of 7.8 million pounds of nickel at average cash costs and all-in sustaining costs ('AISC') per pound of nickel of US$4.91 and US$6.48, respectively. All dollar figures in this news release are Canadian unless otherwise stated.

Highlights of PEA

Current Bucko Lake MRE:

Measured and Indicated Mineral Resources of 5.7 million tonnes grading 1.24% nickel ('Ni') (using a 0.7% Ni cut-off grade) and 0.11% copper ('Cu') for contained metal content of 156.3 million pounds of nickel and 13.4 million pounds of copper.

Additional Inferred Mineral Resources of 10.6 million tonnes grading 1.18% Ni (using a 0.7% Ni cut-off grade) and 0.13% Cu for contained metal content of 275.6 million pounds of nickel and 31.2 million pounds of copper.

The PEA indicates that the Project would be rehabilitated from its current 'care and maintenance' status and placed into operation to produce 101 million pounds of payable nickel over a 13-year mine life.

Using a base case future life-of-mine (LOM) nickel price assumption of US$9.84/lb, the Project generates:

Pre-tax net present value using a discount rate of 6% (NPV6%) of $205 million and Internal Rate of Return (IRR) of 32%; and

After-tax NPV% of $169 million and IRR of 30%

Sensitivity analysis using a recent spot nickel price of US$13/lb for LOM, the Project generates:

Pre-tax NPV6% of $531 million and IRR of 65%; and

After-tax NPV6% of $389 million and IRR of 59%

Initial capital costs of $87 million (including $11 million contingency) with payback in 3.3 years.

The existing 1,000 tonne-per-day ('tpd') processing plant would be upgraded to 1,500 tpd.

Average cash costs of US$4.91/lb Ni and AISC of US$6.48/lb Ni.

Opportunities exist for operations to continue beyond the current LOM plan using resources from multiple known satellite deposits on active company claims: three contiguous deposits are located within 4 km from the Bucko Lake Mine, and a fourth deposit is located approximately 30 km away.

The PEA supersedes the March 31, 2009, Technical Report for the Project and Mineral Reserves are no longer declared for the Project.

'We are encouraged by the positive economics demonstrated by this PEA for the Bucko Lake Mine,' stated Kevin Zhu, CEO of CaNickel Mining Limited. 'The Project represents one of the more advanced, higher grade nickel sulphide projects in North America and benefits from existing infrastructure, including a previously operated 1,000 tpd process plant which we placed on care and maintenance due to low nickel prices in 2012. With demand and prices now surging for Class 1 nickel sulphide on the back of increased demand in electric vehicle batteries, production at the Bucko Lake Mine appears to be economically feasible once again.'

Mr. Zhu added: 'CaNickel now intends to advance on two fronts in the coming months: (1) review options for restructuring the Company's $90+ million in corporate debt; and (2) seek to advance the Project by completing a mine restart and closure plan along with pursuing growth opportunities by updating Mineral Resource Estimates for its four satellite deposits.'

*Cautionary Statement: The Bucko Lake PEA was prepared in accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects. Readers are cautioned that the PEA is preliminary in nature. It includes Inferred Mineral Resources that are considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as Mineral Reserves, and there is no certainty that the PEA outcome will be realized. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

Preparation of PEA

The PEA was prepared by independent firm P&E Mining Consultants Inc. of Brampton, Ontario, with geotechnical assistance from Knight Piesold Ltd. and backfill assistance by Paterson & Cooke Canada Inc. The PEA was prepared in accordance with the requirements of National Instrument 43-101 - Standards of Disclosure for Mineral Projects, and has an effective date of January 13, 2023. A Technical Report relating to the PEA, prepared in accordance with NI 43-101, will be filed on www.SEDAR.com and posted on the Company's website within 45 days of this news release.

For the PEA base case, a nickel price of US$9.84/lb was used. The Company recognizes that nickel prices have been especially volatile recently and readers therefore should review the Project Economics Summary and Sensitivity to Nickel Price chart in Table 6.

Updated Mineral Resource Estimate

The updated MRE incorporates results from a total of 428 drill holes drilled from 1962 to 2013, of which 360 drill holes intersected the mineralization wireframes used for the MRE. Additionally, recent metal prices were incorporated into the estimate for the PEA. The MRE, with an effective date of January 13, 2023, is summarized in Table 1 below.

Mineralization domain boundaries were determined from grade boundary interpretation constrained by lithological and structural controls determined from visual inspection of drill hole cross-sections and level plans. The domain outlines were influenced by the selection of mineralized material above 0.70% Ni that demonstrated a lithological and structural zonal continuity along strike and down dip and that had a reasonable prospect of economic extraction. The minimum constrained down-hole sample length for the wireframes was 2.0 m. In some cases, mineralization below 0.70% Ni was included for the purpose of maintaining zonal continuity and minimum mining width. On each cross-section, polyline interpretations were digitized from drill hole to drill hole, however, were not extended more than 25 m into untested territory. The interpreted polylines from each cross-section were wireframed into 3-Dimensional solids. The resulting solids (domains) were used for statistical analysis, grade interpolation, rock coding and Mineral Resource reporting purposes. Four mineralization domains were constructed for consideration for potential economic underground mining of the Mineral Resource Estimate.

In order to regularize the assay sampling intervals for grade interpolation, a 1.5 m compositing length was selected for the drill hole intervals that fell within the constraints of the above-mentioned Mineral Resource wireframe domains. Grade capping was investigated and applied to the 1.5 m composite values in the database within the constraining domain to ensure that the possible influence of erratic high-grade values did not bias the database. A variography analysis was undertaken as a guide to determining a grade interpolation search strategy. The Ni and Cu grade blocks in the model were interpolated with the Inverse Distance Squared method. The model block size was 2.5 m x 2.5 m x 2.5 m. The Nearest Neighbour interpolation method was utilized for validation.

Additional mineralization at the Bucko Lake property not captured in the PEA include four known satellite deposits located 4 to 30 km distance from the main deposit. These include the Bowden Lake, M11A, Halfway Lake and Apex prospects. All four deposits have historical mineral resources which the Company will update into compliant NI 43-101 Mineral Resource Estimates in the coming months. These satellite deposits represent an opportunity for extending the operational life of the Project, which will be evaluated in future studies.

Underground Mine Development

Despite underground development challenges associated with geotechnical stability experienced during previous operations at the Bucko Lake Mine from 2009 to 2012, there are no significant technical issues to preclude successful mining and processing of the nickel-copper mineralization. Optimization of mining methods and Life of Mine planning with cemented paste backfill hold the key to a successful mine restart and the PEA has adopted the following mine development strategy to overcome previously known issues:

Rehabilitate and re-use existing development where possible while avoiding stopes in historical production areas:

Refit and re-use the existing shaft for broken rock conveyance

Rehabilitate and re-use the existing ramp for trackless equipment access

Convert the existing 1,000 ft (305 m) Level exploration drift into new primary access on hanging wall ('HW') side of the deposit

Change access orientation to the HW from the footwall (FW) to improve geotechnical stability of the parallel wireframed domains.

Improve the ventilation system by relocating ventilation raises to the HW side of the deposit using raise-bores from the 1,000 ft Level to surface.

Postpone capital development while mining previously accessed areas.

FW drifts will allow improved grade selection, bypassing low-grade areas and allowing improvement of the grade profile by targeting more high-grade areas earlier.

Alimak ventilation raises will be attached to FW drifts to facilitate bypassing of levels in a mining block versus using drop raises, allowing further postponement of lateral development.

Areas of development to be situated away from weaker ultramafic contact areas. Development will be done either outside the ultramafic unit or fully inside the unit with improved ground support versus previous efforts at the mine. Intersections with the ultramafic unit, while unavoidable, will be minimized.

Mine design and planning were accomplished with the assistance of geomechanical input from Knight Piesold Ltd. based on the review of the historical mine performance, experience at similar operating mines, and empirical methods. Knight Piesold provided numerous recommendations on the PEA underground mine plan.

Paterson & Cooke Canada Inc. reviewed the paste backfill system that was previously installed at the Bucko Lake Mine. The system was installed just prior to mine suspension in 2012 and therefore never commissioned. Recommendations were provided on rehabilitating equipment, completing the paste plant installation and future test work.

Mining Method

The PEA is based on an underground mine operating at a mining rate of 1,500 tpd for a mine life of 13 years. The mining method was selected to ensure maximum geotechnical stability and grade control flexibility while minimizing initial capital expenditure requirements. It is estimated to take one year of pre-production and two years of production to reach the steady-state rate of 1,500 tpd. The underground mine production schedule is summarized in Table 2.

Long-hole mining, on both transverse and longitudinal orientations, has been chosen as the main mining method with a small subset (~2% of tonnes) of cut-and-fill mining above existing workings.

The sublevel spacing is set at 20 m (floor to floor) to allow use of top-hammer or in-the-hole drills. Mining will be carried out bottom-up in 'blocks' approximately 100 to 150 m in height.

A stope width of 12 m was selected to limit the hydraulic radius, enhance stability and reduce cable bolting requirements.

Cemented paste backfill will be utilized to provide improved stope and ground support, to improve stope cycling compared to previous operational backfill practices, and to reduce the amount of tailings stored on surface.

A modular approach to mining will be used:

Stopes will be segregated into high-grade (average 1.31% Ni mined grade) and low-grade (average 0.88% Ni mined grade) areas using a 1.0% Ni mined grade as the nominal split between high and low grades.

Low-grade mining areas are deferred where possible to postpone development costs and improve the production grade profile (segregation and selection done both vertically and laterally).

A combination of cemented paste backfill, transverse cross-cuts, and top-hammer drills will allow for the extraction of low-grade stopes situated between mined-out high-grade stopes later in mine life using up-hole drilling.

Mining will be kept above the 1,000 ft Level until high-grade stopes in the area are depleted prior to developing a ramp to the next block to minimize CAPEX. This strategy will be repeated in consecutive blocks until the maximum mine depth of approximately 900 m below surface is reached.

Initial production will use diesel trucks to haul material to the shaft with later production to use battery-powered electric trucks to limit ventilation requirements as the mine progresses deeper.

Trucks will not enter FW drifts and load-haul-dump equipment will haul all material to level access re-muck bays where the trucks will be loaded. This allows smaller FW drift profiles and reduces ventilation requirements on the levels.

Trucks will predominantly haul to the shaft and a portion of the tonnage from above the 1,000 ft Level will be trucked up the existing ramp directly to surface.

ABOUT CANICKEL

CaNickel Mining Limited is a Canadian junior mining company that owns the Bucko Lake Mine, currently on care and maintenance, near Wabowden, Manitoba. From 2009 to 2012, nearly 450,000 tonnes of mineralized material were mined to produce 6.9 million pounds of nickel before the mine was put on care and maintenance due to operational challenges and low nickel prices. Today, the Bucko Lake Mine and surrounding satellite deposits continue to host significant nickel sulphide resources grading over 1% Ni.

The mine and surrounding deposits benefit from excellent infrastructure including roads, rail, power, internet, personnel, and equipment. The mine can be accessed and operated all year, and existing mine infrastructure includes a 1,000-tpd processing plant, paste plant, on-site drill core shack, hoist and headframe, fine mineralized material bin, office, dry trailers, compressor room, tailings disposal management area and a 100-person camp.

Contact:

Shirley Anthony

VP

Corporate Development

T: 778-999-2771

Email: shirley@canickel.com

Website: www.buckolakemine.com

CaNickel Mining Limited

P.O. Box 35 1655-999 West Hastings Street

Vancouver

British Columbia CanadaV6C 2W2

Tel: 778-372-1806

Fax: 604-254-8863

Forward-Looking Statements

This press release may contain forward-looking statements including those describing the Company's future plans and the expectations of management that a stated result or condition will occur. Any statement addressing future events or conditions necessarily involves inherent risk and uncertainty. Actual results can differ materially from those anticipated by management at the time of writing due to many factors, most of which are beyond the control of the Company. In particular, this news release contains forward-looking statements pertaining, directly or indirectly, to the Company's plans regarding bringing, the Bucko Lake Mine back into production, resolving the Company's indebtedness and the economic and operational potential of the Bucko Lake Mine and satellite deposits.

Although the Company believes that the expectations and assumptions on which the forward-looking statements are based are reasonable, undue reliance should not be placed on the forward-looking statements because the Company can give no assurance that they will prove to be correct. Since forward-looking statements address future events and conditions, by their very nature they involve inherent risks and uncertainties, actual results could differ materially from those currently anticipated due to a number of factors and risks. These include, but are not limited to, general economic, market or business conditions, risks associated with the exploration and development industry in general (e.g., the outlook for nickel and copper, interest and exchange rates, inflation and capital market conditions, operational risks in development, exploration and production; the uncertainty of Mineral Resource Estimates; the uncertainty of estimates and projections relating to production, costs and expenses, and health, safety and environmental risks).

Readers are cautioned that the foregoing list of risk factors should not be construed as exhaustive. These statements speak only as of the date of this release or as of the date specified in the documents accompanying this release, as the case may be. The Company undertakes no obligation to publicly update or revise any forward-looking statements except as expressly required by applicable securities laws.

(C) 2023 Electronic News Publishing, source ENP Newswire