15e06d36-e2ae-4e15-9913-275a105ff85b.pdf 4 February 2016


January Drilling Report


  • Wet Gas Business
    • Middleton East-1 cased and suspended; new pay zone identified in the Basal Patchawarra and extension of the Middleton field indicated
    • Jute-1 exploration well spudded in Northern Cooper


Wet Gas Business

Western Wet Gas Fairway

The Western Wet Gas joint venture with Beach (Drillsearch 50%, Beach 50% and Operator) spudded the Middleton East-1 well in mid-January to appraise the Middleton field in PPL 239 (formerly PEL 106, see map).


The well was drilled 1,338 metres east of the producing Middleton-1 well and mapped using the Irus 3D seismic survey. Middleton East-1 reached a total depth of 2,876 meters on 27 January 2016.


Drillsearch's preliminary evaluation of well logs indicates a gross interval in the Patchawarra Formation between 2,656 metres and 2,798 metres, with net pay of 16 metres.


One of the pay zones encountered in the Patchawarra Formation correlates to the

Middleton-1 well which was discovered in 2006, indicating an eastward extension of the Middleton field. In addition a new pay zone was identified in the Basal Patchawarra Formation. As a result, Middleton East-1 has been cased and suspended and a cased-hole test will be undertaken at a later date.


The Ensign 930 Rig has been released and moved to the Depps-1 well which is being drilled to appraise the producing Brownlow field. The well is expected to spud in early February.


Northern Cooper Gas and Liquids

Following the success of Willow-1 in early January, the Ensign 932 Rig moved to the second and final well in the Northern Cooper campaign, Jute-1, in PRL 174, spudding on 24 January 2016. As of 2 February 2016, the well was at a depth of 1,316 metres. It is expected to reach total depth of 3,704 metres by mid-February.


The well's key objectives include evaluation of the gas potential of tight sandstones of the Toolachee, Epsilon, and Patchawarra Formations, and the appraisal of the permit's unconventional Basin Centred Gas prospectivity.


Level 18, 321 Kent Street Sydney, NSW 2000 Australia

T +61 2 9249 9600

F +61 2 9249 9630

ABN 73 006 474 844

www.drillsearch.com.au

Monthly Drilling Summary

As at 2 February 2016


Well

Participants

Progress & Summary

Primary Target

Secondary Targets

Oil Wells

Bauer - 25**

DLS BPT*

60%

40%

Spud Date: Rig Release: Depth: Operation:

Progress:

Monday, 28 December 2015

Wednesday, 13 January 2016

1,743 m (TD)

Cased and Suspended 1,743 m (TD)

McKinlay Member Namur Sandstone

Birkhead Formation

PPL 253

Oil Business

Western Flank Oil C/E Basin, SA

Wet Gas Wells

Willow - 1

DLS*

Midcontinent

80%

20%

Spud Date: Rig Release: Depth: Operation:

Progress:

Thursday, 17 December 2015

Wednesday, 13 January 2016

3,402 m (TD)

Cased and Suspended 3,402 m (TD)

Toolachee Formation Epsilon Formation

Patchawarra Sandstone

PRL 173

Wet Gas Business

Northern Gas & Liquids C/E Basin, SA

Middleton East - 1

DLS BPT*

50%

50%

Spud Date: Rig Release: Depth: Operation:

Progress:

Monday, 18 January 2016

Monday, 1 February 2016

2,876 m (TD)

Cased and Suspended 2,876 m (TD)

Patchawarra Sandstone

Tirrawarra Sandstone

PPL 239

Wet Gas Business

Western Cooper Wet Gas C/E Basin, SA

Jute - 1

DLS*

Midcontinent

80%

20%

Spud Date: Rig Release: Depth: Operation:

Progress:

Sunday, 24 January 2016

Friday, 19 Feburary 2016 (Projected) 3,704 m (Proposed)

Drilling ahead

1,316 m

Patchawarra Sandstone

Toolachee Formation Epsilon Formation

PRL 174

Wet Gas Business

Northern Gas & Liquids C/E Basin, SA

* Indicates operator.


** For further information on this w ell please refer to the December 2015 Drilling Report released on 13 January 2016 and the December 2015 Quarterly Report released on 28 January 2016.


For further information please contact:


Dudley White

General Manager - Corporate Communications Phone: +61 2 9249 9669

Email: ir@drillsearch.com.au