Quarterly Update on Operations
Released 07:01 25-Feb-2020



RNS Number : 9535D
Firestone Diamonds PLC
25 February 2020

25 February 2020

FIRESTONE DIAMONDS Plc

('Firestone', the 'Group' or the 'Company')

Quarterly Update on Operations

Firestone Diamonds plc (AIM: FDI), provides its quarterly update on operations at its Liqhobong Diamond Mine ('Liqhobong') for the quarter ended 31 December 2019 (Q2 of the Company's 2020 financial year).

Second quarter ended 31 December 2019

Summary:

· Lost time injury free quarter (Q1: lost time injury free);

· Diamond recoveries of 138 000 carats (Q1: 201 091 carats);

· Grade of 21 carats per hundred tonnes ('cpht') (Q1: 21 cpht);

· Waste tonnes moved for the quarter of 1 070 854 tonnes (Q1: 1 379 758 tonnes);

· The following results were impacted by the power disruption:

o Fewer ore tonnes treated of 668 120 tonnes (Q1: 963 986 tonnes);

o Higher operating cost of US$14.90 per tonne treated (Q1: US$10.32 per tonne treated);

o Two sales took place during the quarter at which 132 885 carats were sold (Q1: 168 612 carats), realising revenue of US$9.7 million (Q1: US$10.6 million) at an average value of US$73 per carat (Q1: US$63 per carat); and

o Lower cash balance at 31 December 2019 of US$17.0 million (Q1: US$21.8 million).

Power disruption

As announced previously, power supply to the mine was disrupted on 1 October causing the processing plant to be shut down until 26 October when alternative electricity supply was provided by diesel generators which were sourced from South Africa. During this time, no ore could be treated. From 27 October, the mine ran on generator power, albeit at a marginally lower capacity of approximately 90% until 1 December when the grid power was restored and operations returned to normal. The power disruption impacted operations, resulting in approximately 230 000 fewer ore tonnes being treated for the quarter and therefore fewer carat recoveries which translated into lower revenue. Operating costs for the quarter were US$1.1 million higher as they included the additional costs associated with renting and operating the diesel generators. The total impact of the power disruption to the business is estimated to be US$4.6 million.

Revised guidance for FY2020

Due to the power disruption and a subsequent review of the mine plan, the production guidance for FY2020 has been revised as follows:

· Diamond recoveries of between 720 000 and 750 000 carats (previously between 820 000 and 870 000 carats);

· Ore tonnes treated of between 3.3 and 3.6 million tonnes ('mt') (previously between 3.6 and 3.8 mt);

· Waste tonnes moved of between 4.9 and 5.2 mt (previously between 6.0 and 6.5 mt); and

· Operating cost remain at between US$13.501and US$14.501per tonne treated.

1 - Based on an average Rand:USDollar exchange rate of R14.50

Paul Bosma, Chief Executive Officer, commented:

'The unexpected power disruption had a devastating impact on production and revenue generation. The team however, did well to salvage the situation by procuring and installing generators from South Africa in record time to allow for operations to recommence.

As a result of the power disruption, we have reduced our guidance for the year in respect of diamond recoveries and ore tonnes treated.

During the quarter, good progress was made with our Lenders and non-binding term sheets were signed before year end with ABSA bank for a debt repayment standstill until 31 March 2021 and with our bondholders for a working capital facility of US$6 million for the same period. We expect both of these agreements to be formally documented before our financial year-end.

Due to the production setback and continued lacklustre market conditions, the Board has decided that it is imperative that it does all it can to reduce costs in order to survive the prolonged downturn. As announced earlier today, this includes delisting from AIM and reducing the size of the Board.'

Operations

During the quarter ended 31 December 2019, Liqhobong treated only 668 120 tonnes of ore compared to its plan of approximately 900 000 tonnes due to an unexpected power disruption. The power disruption prevented any ore from being treated from 1 October until 27 October, when alternative power provided by rented diesel generators made it possible to recommence treating ore at a marginally lower throughput rate of approximately 90%. From 1 December, operations returned to normal and capacity returned to 100% as grid power was restored. The lower tonnage treated resulted in fewer carats recovered for the quarter of 138 000 carats (Q1: 201 091 carats).

Mining continued in predominantly the higher-grade southern part of the pit during the quarter in order to further excavate the sump that is planned to be used to store water during 2020. The recovered grade of 21 cpht was unchanged from the previous quarter and continued to be lower than the expected reserve grade. Work to improve the situation is continuing.

A total of 1 070 854 waste tonnes was moved during the quarter which was less than the 1 379 758 tonnes that was moved in the previous quarter. The waste mining plan was reduced due to a steepening of the cut 2 south design and the guidance has been updated accordingly.

Safety, Health & Environment

The first quarter was worked safely with no Lost Time Injury's recorded.

Financial

The combination of fewer ore tonnes treated and the increased cost of using generator power resulted in higher operating costs for the quarter of US$14.90 per tonne treated (Q1: US$10.32 per tonne treated) including waste stripping. However, operating costs on a year to date basis of US$12.19 per tonne treated including waste stripping remain well below guidance of between US$13.50 and US$14.50 per tonne treated due to fewer waste tonnes mined and cost savings across the operation as a result of stringent cost management. The total additional cost associated with renting and operating the diesel generators during the quarter was US$1.1 million with the total cash impact due to the power disruption estimated at US$4.6 million. However, Liqhobong's insurer has surprisingly repudiated the claim relating to the power disruption and Management is now considering its options in this regard. The cash balance at the end of the quarter was US$17.0 million (Q1: US$21.8 million).

Diamond Sales and Market Outlook

During the quarter, sales volumes decreased by 21% due to the power disruption to 132 885 carats compared to 168 612 carats sold in the previous quarter. However, average diamond values of US$73 per carat were higher than US$63 per carat in the previous quarter due to a number of larger and better-quality diamonds that were recovered and sold including one plus 100 carat diamond and two plus 90 carat diamonds. As a result, the sales value for the quarter of US$9.7 million was only 8% lower than US$10.6 million in the previous quarter.

The prices realised for the smaller goods that make up the bulk of our production by volume, remain subdued, impacted by a build-up of rough and polished inventory in the midstream. Initial indications are that the peak retail season at the end of the 2019 was satisfactory and therefore, it is anticipated that some restocking should take place during early 2020. However, due to the excess inventory held in the midstream and by the two largest producers, we expect that it will take some time for the value chain to rebalance and for there to be a sustained increase in prices. Other downside risks include ongoing US-China trade tensions and more recently the uncertain impact of the coronavirus on demand.

Debt restructuring

The electricity supply disruption has exacerbated an already challenging outlook for the Company, resulting in an inability to meet its scheduled debt repayments in the near term and as a result, agreement was reached with ABSA Bank to defer the December capital repayment of US$2.5 million. In addition, non-binding term sheets were signed with ABSA for the deferral of capital repayments for a 15-month period to 31 March 2021; and with our bondholders to provide a US$6.0 million working capital facility until 31 March 2021. We expect to have definitive agreements in place by year-end.

For more information please visitwww.firestonediamonds.comor contact:

Firestone Diamonds plc

+ 44 (0)20 3319 1690

Paul Bosma

Grant Ferriman

Macquarie Capital (Europe) Limited (Nomad and Broker)

+44 (0)20 3037 2000

Alex Reynolds

Tavistock (Public and Investor Relations)

+44 (0)20 7920 3150

Jos Simson

Gareth Tredway

Annabel de Morgan

Background information on Firestone

Firestone is an international diamond mining company with operations in Lesotho. Firestone commenced commercial production in July 2017 at the Liqhobong Diamond Mine. Liqhobong is owned 75% by Firestone and 25% by the Government of Lesotho. Lesotho is one of Africa's significant new diamond producers, hosting Gem Diamonds' Letšeng Mine, Firestone's Liqhobong Mine, Namakwa Diamonds' Kao Mine and Lucapa's Mothae Mine.


This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
END
UPDPPUGUPUPUGQC
London Stock Exchange plc is not responsible for and does not check content on this Website. Website users are responsible for checking content. Any news item (including any prospectus) which is addressed solely to the persons and countries specified therein should not be relied upon other than by such persons and/or outside the specified countries. Terms and conditions, including restrictions on use and distribution apply.
©2014London Stock Exchange plc. All rights reserved



Quarterly Update on Operations - RNS

Attachments

  • Original document
  • Permalink

Disclaimer

Firestone Diamonds plc published this content on 25 February 2020 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 25 February 2020 07:08:13 UTC