Great Lakes Graphite Inc. provided update on 2014 Lochaber Winter Drill Program. Mr. Kyle Loney, President of Wolf Mountain Drilling, the contractor conducting the Lochaber drill program, reports that three of the six 100 m holes have now been completed. Further, Mr. Loney indicates that the program continues to progress on schedule.

Mr. Sbastien Bernier, P.Geo., a representative of SRK Consulting, who have been engaged to complete a NI-43-101-compliant resource estimate on the Lochaber property will be on site commencing this weekend. As each drill hole is completed, the drill core is being transported to Sudbury core shack. Once there, the core is logged, split and prepared for assay.

Core samples will then be shipped to AGAT Laboratories Inc. in Mississauga for analysis. The company anticipates that drilling will be completed before year end.