Husky has achieved first oil at the Spruce Lake Central thermal project in Saskatchewan and is moving towards startup of the Liuhua 29-1 field at the Liwan Gas Project. Spruce Lake Central, Husky's sixth 10,000-barrel-per-day thermal bitumen project since 2015, has been completed safely, on schedule and on budget with enhanced COVID-19 health protocols in place. Spruce Lake Central began steaming in the second quarter of 2020, and will ramp up to full production over the next couple of months. Husky's Saskatchewan thermal projects are directly linked to its Lloydminster Upgrader, Asphalt Refinery and Midwest U.S. refineries, with access to secured pipeline capacity and ample storage to maximize available margins. They are also not subject to the government-mandated production quotas that remain in place in Alberta.