High gold grades maintained, as Serabi produces almost 10,000 ounces for the first quarter of 2017

Serabi Gold plc (AIM:SRB, TSX:SBI), the Brazilian focused gold mining and development company, is pleased to report first quarter production of almost 10,000 ounces of gold, in line with production guidance and provides an accompanying operational update on its Palito and Sao Chico high grade gold operations in the Tapajos region of Para State, Northern Brazil. HIGHLIGHTS
  • Strong first quarter production of 9,861 ounces of gold, on budget and in line with guidance.

  • Mine production totalled 36,918 tonnes at 10.12 grammes per tonne ("g/t") of gold.

  • 46,663 tonnes of ore processed through the plant for the combined mining operations, at a combined grade of 7.09 g/t of gold.

  • 2,251 metres of horizontal mine development completed in the quarter.

  • At Palito, expansion of working areas continues, with development and production now coming from eight veins from the 25 included in the geological resource.

  • Test stopes using long-hole mining are underway in the Senna vein, with good success to date. The Senna vein is showing wider widths, potentially allowing for an increased level of mechanisation. Four sublevels are already in development with a new cross cut being established at the 180mRL.

  • At Palito Main Zone, the main ramp has now reached the -50mRL, where the G3 vein is now under development.

  • At Sao Chico the main ramp has now been deepened to the 56mRL, approximately 190 vertical metres below surface. Production is coming from the 140mRL, and with sublevels developed on levels 128mRL, 116mRL, 100mRL, 86mRL and 70mRL, development is well ahead of production.

  • By the end of the first quarter, surface ore stocks were approximately 13,000 tonnes (31 December 2016: 21,000 tonnes) with an average grade of 4.0 g/t of gold.

  • Ground induced polarisation ("IP") survey undertaken at Sao Chico has identified some excellent targets within 500 metres of the current operation.

Mike Hodgson, CEO, said:

"A successful 2016 has been followed by a strong first quarter to 2017, with almost 10,000 ounces of gold being produced for the quarter; on budget and in line with guidance.

"Mine production from both the Palito and Sao Chico orebodies showed steady progress. Eight veins are now being worked in the Palito orebody, with four new veins coming on stream this quarter, significantly improving optionality. The Pipocas, G3 and Senna veins continue to form the backbone of production, whilst development of the new Zonta vein to

the west of Senna, ongoing development of the G1 and G2 veins, and veins within the Chico da Santa zone demonstrate the abundance of opportunity that exists at Palito.

"Ore development and production from the Sao Chico orebody continued in line with schedule and with excellent mined grades, at an average grade of over 12 g/t, achieved for the quarter. The main ramp has now reached the 56mRL with the Main Vein being intersected early in April. Stope ore production is currently focused on the 140mRL whilst development is progressing on five levels below and is nicely ahead of stoping activity.

"In the plant, the quarterly performance was very satisfying and the milled throughput of 46,000 tonnes for the quarter represents a 10 per cent improvement over the previous highest quarterly production level. As has previously been reported, the introduction of the third mill last year was principally to establish much needed contingency, however, we are making inroads into the surface stockpiles, though we still remain largely limited by overall plant capacity.

"In the latter half of 2016 the Company reported that, following the extension of its exploration license holdings around the Sao Chico orebody, it had recommenced surface exploration, with an IP geophysical survey. The purpose of the survey was to trace the trend of the Main Vein, which has sufficient sulphides to provide a clear conductivity anomaly and which in turn, we hoped, would provide targets for a subsequent drill programme. Due to the wet season arriving early, the programme had to be suspended, but nevertheless we processed the data from those areas where work had been completed. The initial results that have become available during this first quarter of 2017 are extremely promising. The survey was designed to traverse the known orebody to provide orientation, and focus to the east and west of the current strike. The results to date show two excellent anomalies 600 metres to the north and 300 metres to the south of the current workings, which, from a geophysical perspective, look even stronger than the orebody being mined. These anomalies appear to suggest a geometry consistent with the known orebody and could suggest parallel mineralisation. We are set to recommence the programme this coming quarter, though clearly we have already generated some exciting drill targets.

"Exploration and evaluation drilling underground continued with approximately 1,950 metres of diamond drilling completed. This drilling is focusing on deeper drilling into inferred resources in the Senna, Pipocas and G3 veins in the Palito orebody, and similarly the down dip extension of the Main Vein in the Sao Chico orebody, with a view to converting substantial inferred resource to indicated status.

"Following the excellent operational performance of 2016, it is very pleasing to see this being continued with a very good first quarter. Grades coming out of the Sao Chico orebody have been excellent, the plant has processed record tonnages and the operation remains mill constrained. The exploration results which indicate excellent anomalies adjacent to the Sao Chico orebody, are obviously very exciting for us, and we want to progress these as soon as is practical."

Results

Total production for the first quarter of 2017 was 9,861 ounces of gold, generated from the processing of the run of mine ("ROM") ore from the Palito and Sao Chico orebodies, combined with the Palito surface coarse ore and the stockpiled flotation tailings accumulated from Palito mine production in 2014.

Gold production for the first quarter came from the processing of 46,663 tonnes of ore at overall combined grades of 7.09 g/t gold, which was sourced from mined ore from the Palito and Sao Chico orebodies, supplemented with lower grade surface stockpiled ROM and flotation tailings. Mined tonnage for the quarter totalled 36,918 tonnes with a grade of 10.12 g/t of gold.

At 31 March 2017, there were coarse ore stocks of approximately 13,000 tonnes with an average grade of 4.0 g/t of gold, and approximately 17,000 tonnes of flotation tails with an average grade of 2.5 g/t of gold. This stock is being consumed, albeit not as quickly as forecast and for now the operation remains plant constrained.

A total of 2,251 metres of horizontal development has been completed during the quarter, of which 1,176 metres was ore development. The balance is the ramp, cross cuts and stope preparation development.

2017 Guidance

The Company forecast 40,000 ounces of gold production for the year, with an AISC of between $950 and $975 per ounce, broadly in line with the cost guidance of 2016. Gold production for the first quarter is in line with the Company's forecast.

The 2017 guidance of 40,000 ounces is an eight per cent improvement on Serabi's initial guidance for 2016 which was 37,000 ounces. Management hope that, with the production efficiencies and improvements that can be implemented in 2017, Serabi will again be able to improve on its production guidance, as it did in 2016, where the Company exceeded its initial guidance by 6.5 per cent to produce 39,390 ounces.

Quarter 1

2017

Quarter 1

2016

Quarter 2

2016

Quarter 3

2016

Quarter 4

2016

Total

2016

Total

2015

1,669

1,900

1,910

1,607

1,928

7,345

6,800

582

1,025

1,031

1,042

696

3,794

2,800

2,251

2,925

2,941

2,649

2,694

11,209

9,600

26,093

26,752

25,198

31,916

34,611

118,477

111,751

9.07

11.84

10.48

9.52

7.38

9.62

10.05

10,825

10,794

8,408

11,217

9,968

40,387

24,096

12.64

9.00

6.81

9.88

14.38

10.12

8.66

36,918

37,546

33,606

43,133

44,579

158,864

135,847

10.12

11.02

9.56

9.61

8.94

9.74

9.8

46,663

36,615

39,402

42,464

40,485

158,966

130,299

7.09

8.58

8.17

8.08

7.6

8.11

8.43

9,861

9,771

9,896

10,310

9,413

39,390

32,629

Horizontal development -

PalitoMetres

Horizontal development -

Sao Chico Metres

Horizontal development -

TotalMetres

Mined ore - Palito Tonnes

Gold grade (g/t)

Mined ore - Sao Chico Tonnes

Gold grade (g/t)

Mined ore - Total Tonnes

Gold grade (g/t)

Milled ore Tonnes

Gold grade (g/t)

Gold production Ounces

  1. Gold production figures are subject to amendment pending final agreed assays of the gold content of the copper/gold concentrate and the gold bullion when smelting and refining processes are completed.

  2. Gold production totals for 2017 include treatment of 4,941 tonnes of flotation tails (2016 full year: 16,716 tonnes)

This announcement is inside information for the purposes of Article 7 of Regulation 596/2014.

Enquiries

SERABI GOLD plc

Michael Hodgson t +44 (0)20 7246 6830

Chief Executive m +44 (0)7799 473621

Clive Line t +44 (0)20 7246 6830

Finance Director m +44 (0)7710 151692

e contact@serabigold.com www.serabigold.com

BEAUMONT CORNISH Limited

Nominated Adviser & Financial Adviser

Roland Cornish t +44 (0)20 7628 3396

Michael Cornish t +44 (0)20 7628 3396

PEEL HUNT LLP

UK Broker

Matthew Armitt t +44 (0)20 7418 8900

Ross Allister t +44 (0)20 7418 8900

Blytheweigh

UK Financial PR

Tim Blythe t +44 (0)20 7138 3204

Camilla Horsfall t +44 (0)20 7138 3224

Copies of this release are available from the Company's website at www.serabigold.com

Forward-looking statements

Certain statements in this announcement are, or may be deemed to be, forward looking statements. Forward looking statements are identified by their use of terms and phrases such as ''believe'', ''could'', "should" ''envisage'', ''estimate'', ''intend'', ''may'', ''plan'', ''will'' or the negative of those, variations or comparable expressions, including references to assumptions. These forward looking statements are not based on historical facts but rather on the Directors' current expectations and assumptions regarding the Company's future growth, results of operations, performance, future capital and other expenditures (including the amount, nature and sources of funding thereof), competitive advantages, business prospects and opportunities. Such forward looking statements reflect the Directors' current beliefs and assumptions and are based on information currently available to the Directors. A number of factors could cause actual results to differ materially from the results discussed in the forward looking statements including risks associated with vulnerability to general economic and business conditions, competition, environmental and other regulatory changes, actions by governmental authorities, the availability of capital markets, reliance on key personnel, uninsured and underinsured losses and other factors, many of which are beyond the control of the Company. Although any forward looking statements

contained in this announcement are based upon what the Directors believe to be reasonable assumptions, the Company cannot assure investors that actual results will be consistent with such forward looking statements.

Qualified Persons Statement

The scientific and technical information contained within this announcement has been reviewed and approved by Michael Hodgson, a Director of the Company. Mr Hodgson is an Economic Geologist by training with over 25 years' experience in the mining industry. He holds a BSc (Hons) Geology, University of London, a MSc Mining Geology, University of Leicester and is a Fellow of the Institute of Materials, Minerals and Mining and a Chartered Engineer of the Engineering Council of UK, recognizing him as both a Qualified Person for the purposes of Canadian National Instrument 43-101 and by the AIM Guidance Note on Mining and Oil & Gas Companies dated June 2009.

Neither the Toronto Stock Exchange, nor any other securities regulatory authority, has approved or disapproved of the contents of this news release.

GLOSSARY OF TERMS

The following is a glossary of technical terms: "Au" means gold.

"assay" in economic geology, means to analyze the proportions of metal in a rock or overburden sample; to test an ore or mineral for composition, purity, weight or other properties of commercial interest.

"development" - excavations used to establish access to the mineralised rock and other workings "DNPM" is the Departamento Nacional de Produção Mineral.

"grade" is the concentration of mineral within the host rock typically quoted as grams per tonne (g/t), parts per million (ppm) or parts per billion (ppb).

"g/t" means grams per tonne.

"granodiorite" is an igneous intrusive rock similar to granite. "igneous" is a rock that has solidified from molten material or magma. "Intrusive" is a body of igneous rock that invades older rocks.

"on-lode development" - Development that is undertaken in and following the direction of the Vein

"mRL" - depth in metres measured relative to a fixed point - in the case of Palito and Sao Chico this is sea-level. The mine entrance at Palito is at 250mRL.

"saprolite" is a weathered or decomposed clayrich rock.

"stoping blocks" - a discrete area of mineralised rock established for planning and scheduling purposes that will be mined using one of the

various stoping methods.

"vein" is a generic term to describe an occurrence of mineralised rock within an area of non-mineralised rock.

Serabi Gold plc published this content on 12 April 2017 and is solely responsible for the information contained herein.
Distributed by Public, unedited and unaltered, on 12 April 2017 06:15:10 UTC.