Strandline Resources Limited (ASX: STA) is pleased to advise the initial stages of commissioning of the Wet Concentration Plant (WCP) at its Coburn mineral sands project in WA is almost complete, paving the way for first production.

Final construction verification, water commissioning and sequence testing is now underway. Successful completion of this phase of commissioning will be followed by the introduction of the first ore and ramp up.

Pre-production mining of the open pits (pre-stripping) is also finished, and all dozer mining units and key equipment fleet are ready for ore mining.

While commissioning of the WCP continues, construction teams have transitioned to finalise the downstream

Mineral Separation Plant (MSP) and remaining support infrastructure, with overall project construction now ~95% complete.

Final drawdown of Coburn's senior finance facilities has also been successfully completed in accordance with the development plan.

Strandline expects to sell several shipments of Heavy Mineral Concentrate produced from the WCP while construction of the MSP is being completed.

Once the MSP is ready, HMC will then be transported to the MSP for further processing to produce Coburn's premium-quality final products, including chloride ilmenite, rutile, premium zircon and zircon concentrate.

Strandline Managing Director Luke Graham said: 'Strandline is on the cusp of production and cashflow. 'With pre-ore commissioning of the WCP almost finished, we are now preparing to deliver first ore to the plant and commence the production ramp-up and tuning process.

'This will be followed by our first shipment of HMC, which is expected to be worth ~A$10m at current spot prices, for a ~10,000t FOB shipment size (subject to market movements).

'At the same time, the construction emphasis is on completion of the MSP, which will add further significant value to our production'.

ABOUT COBURN MINERAL SANDS PROJECT

In May 2021 Strandline made a Final Investment Decision (FID) to proceed with the full development of its world-scale Coburn mineral sands project, located in the Gascoyne region of Western Australia. The construction schedule has first production of HMC planned for the December quarter of 2022.

The Coburn project is set to capitalise on its robust margins, the buoyant minerals sands commodity pricing outlook, its tier-1 location, and the growing demand for critical minerals.

The Coburn mine life currently sees mining continue until 2045 (based on mining the initial 22.5-year JORC 2012 compliant Ore Reserves), with the potential to extend to 2060 (total 37.5 years mine life) by converting Mineral Resources which exist immediately north and along strike of existing Ore Reserves.

The FID was supported by the updated Definitive Feasibility Study (DFS), released in mid-2020, which confirmed robust economics for the project over an initial 22.5-year life, including:

Pre-tax NPV of A$705m (AUD: USD 0.70, 8% DCF discount rate)

High margin revenue-to-operating cost (C1) ratio of 2.4

Projected revenue for the initial 22.5 years of Ore Reserves of A$4.4b

Average annual EBITDA of A$104m and +50% EBITDA margin (excluding ramp-up phase)

Fully funded to production and cash flow by a combination of 15-year A$150m NAIF1 loan alongside a 5- year US$60m Bond Issue, and cash reserves

Binding offtakes secured for 100% of Coburn's initial production with a diverse group of top-tier customers

ABOUT COBURN MINERAL SANDS PROJECT

In May 2021 Strandline made a Final Investment Decision (FID) to proceed with the full development of its world-scale Coburn mineral sands project, located in the Gascoyne region of Western Australia. The construction schedule has first production of HMC planned for the December quarter of 2022.

The Coburn project is set to capitalise on its robust margins, the buoyant minerals sands commodity pricing outlook, its tier-1 location, and the growing demand for critical minerals.

The Coburn mine life currently sees mining continue until 2045 (based on mining the initial 22.5-year JORC 2012 compliant Ore Reserves), with the potential to extend to 2060 (total 37.5 years mine life) by converting Mineral Resources which exist immediately north and along strike of existing Ore Reserves.

The FID was supported by the updated Definitive Feasibility Study (DFS), released in mid-2020, which confirmed robust economics for the project over an initial 22.5-year life, including:

Pre-tax NPV of A$705m (AUD: USD 0.70, 8% DCF discount rate)

High margin revenue-to-operating cost (C1) ratio of 2.4

Projected revenue for the initial 22.5 years of Ore Reserves of A$4.4b

Average annual EBITDA of A$104m and +50% EBITDA margin (excluding ramp-up phase)

Fully funded to production and cash flow by a combination of 15-year A$150m NAIF1 loan alongside a 5- year US$60m Bond Issue, and cash reserves

Binding offtakes secured for 100% of Coburn's initial production with a diverse group of top-tier customers

Strandline is committed to building a highly efficient and sustainable mining operation. The project provides significant public benefit including job creation, high Australian industry participation in the supply chain, new local business and indigenous engagement opportunities, as well as capital inflows for Australia.

Refer to the ASX Announcement dated 10 June 2020 for more information on the Coburn mineral sands project and details of the material assumptions underpinning the production target and financial results for the Coburn Project DFS, Ore Reserve and Mine Life Extension Case Scoping Study. The Company confirms that all material assumptions and technical parameters underpinning Resource Estimates, Production Targets and Project Feasibility Studies, continue to apply and have not materially changed.

Contact:

Luke Graham

CEO and Managing Director

Strandline Resources Limited

T: +61 8 9226 3130

E: enquiries@strandline.com.au

FORWARD LOOKING STATEMENTS

This report contains certain forward looking statements. Forward looking statements are only predictions and are subject to risks, uncertainties and assumptions which are outside of the control of Strandline. These risks, uncertainties and assumptions include commodity prices, currency fluctuations, economic and financial market conditions, environmental risks and legislative, fiscal or regulatory developments, political risks, project delay, approvals and cost estimates. Actual values, results or events may be materially different to those contained in this announcement. Given these uncertainties, readers are cautioned not to place reliance on forward looking statements. Any forward looking statements in this announcement reflect the views of Strandline only at the date of this announcement. Subject to any continuing obligations under applicable laws and ASX Listing Rules, Strandline does not undertake any obligation to update or revise any information or any of the forward-looking statements in this announcement to reflect changes in events, conditions or circumstances on which any forward looking statements is based.

(C) 2022 Electronic News Publishing, source ENP Newswire