Tlou Energy Limited announced that it is currently drilling the Lesedi 6 gas production pod. The pod will comprise one vertical production well (Lesedi 6P) intersected by two lateral wells (Lesedi 6A and Lesedi 6B) drilled horizontally through the target reservoir section for several hundred metres. Lesedi 6P - Vertical Production Well; This well has been drilled to a depth of 589m and intersected 6m of the target lower Morupule coal.

Well casing was cemented in place, with fiberglass casing at the target coal seam underreamed to expose the coal to the well bore to facilitate dewatering and gas flow. Core-hole drilling; The objective of the core-hole is to provide additional geological control in the vicinity of the Lesedi 6 gas production pod. In addition to providing coal and gas content data, the core-hole accurately determined the top and bottom of the target coal seam close to where the lateral section of Lesedi 6A and Lesedi 6B will enter the coal.

This is important data for drilling of the lateral section of each well. The core-hole was completed and logged after reaching a total depth of 535m and intersecting 6m of coal. 18 coal samples were taken and placed in desorption canisters for further analysis.

Transmission Lines; Work on the transmission lines to connect Tlou's Lesedi power project to the existing power grid is progressing. Overall progress to date is 73%. This work is expected to be completed in 3Q23.

The 100 Km line includes planting wooden and steel pole structures. Most of the wooden poles have been erected and work has begun on the steel structures. Line stringing is also underway with 30km of the phase conductor and 67km of the GSW earth wire complete.

Substations; Substations are required at either end of the transmission line, one to tie Tlou's generators to the transmission line at Lesedi and another to integrate the line with the existing Botswana Power Corporation (BPC) substation at Serowe. OptiPower, a division of Murray & Roberts Ltd. has been contracted to complete this work. OptiPower has established a site in Serowe and appointed subcontractors for detailed engineering design and civils works with geotechnical assessments, soil resistivity and topographical surveys now complete.

The substations are expected to be commissioned in 2Q24. Operations and generation facility; Work is continuing on a purpose-built operations facility for the initial 10MW development and to allow for project expansion thereafter. This project is being managed by African Gas Services on behalf of Tlou and it is expected to be completed later this year.

This facility will also include the power generation site and the Company has engaged external advisors to provide technical and commercial advice relating to site based power generation design, procurement, construction and operation.