April 27, 2016 Electric Power Development Co., Ltd
Outline of Fiscal 2016 Electric Power Supply Plan (Power Generation)
J-POWER (Electric Power Development Co., Ltd.) has today submitted its Fiscal 2016 Electric Power Supply Plan (Power Generation) to the Organization for Cross-regional Coordination of Transmission Operators, Japan (OCCTO).*
For the outline of the Fiscal 2016 Electric Power Supply Plan, please refer to the attached table.
* In pursuance of the provisions of Article 29 of the Electricity Utilities Industry Law, J-POWER has submitted the plan to the Minister of Economy, Trade and Industry, through OCCTO.
Table: Fiscal 2016 Electric Power Supply Plan (Power Generation)
(Table)
Fiscal 2016 Electric Power Supply Plan (Power Generation)
Electric Power Development Plan
Item | Type of Power | Project | Prefecture | Maximum Output | Start of Construction | Start of Operation |
Under Construction | Thermal Power | Takehara New Unit No.1 | Hiroshima | 600MW | Dec-2015 | Jun-2020 |
Nuclear Power | Ohma Nuclear Power | Aomori | 1,383MW | May-2008 | To Be Determined | |
Under Preparation for Construction | Hydroelectric Power | Shinkatsurazawa | Hokkaido | 16.8MW | Jul-2017 | Jun-2020 |
Akiba No.1 | Shizuoka | 47.2MW | (Unit No.1) May-2018 (Unit No.2) May-2017 | |||
Akiba No.2 | Shizuoka | 35.3MW | May-2016 | |||
Thermal Power | Isogo New Unit No.2 | Kanagawa | 600MW | Apr-2017 | Jun-2017 | |
Other | Geothermal power | Onikobe | Miyagi | 0MW | Apr-2017 |
EPDC - Electric Power Development Co. Ltd. issued this content on 27 April 2016 and is solely responsible for the information contained herein. Distributed by Public, unedited and unaltered, on 28 April 2016 08:17:53 UTC
Original Document: http://www.jpower.co.jp/english/news_release/pdf/news160427_2.pdf