April 27, 2016 Electric Power Development Co., Ltd

Outline of Fiscal 2016 Electric Power Supply Plan (Power Generation)

J-POWER (Electric Power Development Co., Ltd.) has today submitted its Fiscal 2016 Electric Power Supply Plan (Power Generation) to the Organization for Cross-regional Coordination of Transmission Operators, Japan (OCCTO).*

For the outline of the Fiscal 2016 Electric Power Supply Plan, please refer to the attached table.

* In pursuance of the provisions of Article 29 of the Electricity Utilities Industry Law, J-POWER has submitted the plan to the Minister of Economy, Trade and Industry, through OCCTO.

Table: Fiscal 2016 Electric Power Supply Plan (Power Generation)

(Table)‌

Fiscal 2016 Electric Power Supply Plan (Power Generation)

Electric Power Development Plan

Item

Type of Power

Project

Prefecture

Maximum Output

Start of Construction

Start of Operation

Under Construction

Thermal Power

Takehara New Unit No.1

Hiroshima

600MW

Dec-2015

Jun-2020

Nuclear Power

Ohma Nuclear Power

Aomori

1,383MW

May-2008

To Be Determined

Under Preparation for Construction

Hydroelectric Power

Shinkatsurazawa

Hokkaido

16.8MW

Jul-2017

Jun-2020

Akiba No.1

Shizuoka

47.2MW

(Unit No.1) May-2018 (Unit No.2) May-2017

Akiba No.2

Shizuoka

35.3MW

May-2016

Thermal Power

Isogo New Unit No.2

Kanagawa

600MW

Apr-2017

Jun-2017

Other

Geothermal power

Onikobe

Miyagi

0MW

Apr-2017