Bechtel-ENKA's SCPX Project construction works is on-going at its full speed. CSG-1 Site Progress is reaching to 80% as being at the final return of construction works with the commencement of Mechanical Completion activities. CSG-2 Site is progressed by 40%. On the other hand, Area 81 Site, which is located right near to the existing Baku-Tiflis-Ceyhan Pipeline (BTC) at the Turkish Border, is completed by 70% including, Brownfield Works, being executed inside the existing BTC PRMS for the integration of SCPX. The project worked 945 days and spent 9 million man-hours.