• It will install a second transformer in the Copey substation 
  • New work will generate annual revenues in the sum of US$ 1.8 MM

ISA won the open public bid from the Mining-Energy Planning Unit (Unidad de Planeación Minero Energética -UPME) to install, operate and maintain a high-voltage transformer for the Copey substation, located in the department of Cesar. The award made on December 11th, 2013 was made final after the opinion of the Energy and Gas Regulatory Commission (CREG), pursuant to that which was established in the regulation.

With this new work, to be commissioned by November 30th, 2015, ISA will obtain annual revenues in the amount of US$ 1.8 MM (dollars as of December 31st, 2012).