SOMA Cimento demonstrated their confidence in KHD´s advanced technology, by placing an order for the engineering and equipment supply of its new 4,000 t/d clinker production line at SOMA cement plant, located near the town of Soma, Manisa in the Aegean region of Turkey.

The contract with SOMA Cimento, awards KHD the order for engineering, equipment supply, and supervision of erection and commissioning, including KHD's SIMULEX plant simulation system which will simulate the operation of the plant.

The core components of KHD's new line are:

  • 5-stage KHD Preheater with PYROCLON-RLowNOAF calciner, equipped with
    PYROTOP compact mixing chamber, tertiary air duct and PYROBOX calciner firing system.
  • PYRORAPID two-tire rotary kiln, with a diameter of 4.6 m.
  • PYRO-JETkiln burner
  • PYROFLOORclinker cooler equipped with a PYROCRUSHER System.

This project will mark the third commissioning of KHD's Low-NOx calciner with PYROLOOPTechnology in Turkey. Coupled with KHD's proven pyroprocessing technology, this project will combine cutting-edge thermal recuperation and low emissions technology.

This will be the KHD's 51 kiln line in Turkey. Traditionally, Turkey has the highest market share of KHD equipment, with almost 70% of Turkish production units designed and installed by KHD.

Commissioning of the plant is scheduled for the spring of 2018.

KHD Humboldt Wedag International AG published this content on 24 August 2017 and is solely responsible for the information contained herein.
Distributed by Public, unedited and unaltered, on 24 August 2017 12:42:05 UTC.

Original documenthttp://www.khd.com/newsdetails/items/Soma_Cimento.html

Public permalinkhttp://www.publicnow.com/view/7E5FDD75335EED5B57446DE8036B7F3EC045FC68