BluMetric Environmental Inc. announced that it has been retained by Linde Canada to complete an environmental remediation plan for an industrial property in Montreal East. This remediation plan has been approved by the Ministry of the Environment and the Fight against Climate Change . BluMetric will be overseeing the management and removal of contaminated soils, concrete, and water with work having to be completed over a very tight schedule through the month of September.

The Company will be responsible for removing an estimated 4,681m³ of contaminated soil from the site, in addition to replacing and relocating another 9,085m³ of clean soil. The total value of the contract is approximately $1.4 million with margins inline with similar, historical contracts.