Decmil Group Limited, working together with RJE Global, has been advised of conditional preferred status as Balance of Plant contractor for the construction of the 108 MW Waddi Wind Farm in Western Australia. The project is located approximately 15 km north-west of the township of Dandaragan and approximately 150 km north of Perth in the mid-west region of the wheatbelt, in close proximity to where Decmil successfully delivered the Yandin and Warradarge Wind Farms completed in 2020. An early works scope of works will be agreed to support the development phase of the project which is targeted to commence construction in late 2023.

Decmil was awarded the circa $79 million Yandin Balance of Plant contract for the 214 MW Yandin Wind Farm in April 2019 and the $72 million Warradarge Balance of Plant contract for the 180MW Warradarge Wind Farm in March 2019.