Dynacor Gold Mines Inc. reported production results for the month and year to date ended May 2018. In May 2018, the Corporation produced 6,902 ounces of gold (6,205 ounces in May 2017) at its Veta Dorada plant which is similar to the production in the previous month. During the month of May 7,985 metric tonnes of mineralized material were processed (6.4 % above the forecast of 7,500 MT). Gold grades of the purchased and processed material were less than anticipated resulting in a lower gold production.

During the first five months of 2018 the Veta Dorada plant processed 36,298 metric tonnes (MT) of material compared to 27,095 MT in the same period last year. This represents an increase of 34% and confirms the efforts underway to increase the processing volume each month.

The Corporation is continuing to ramp up production on its way to its annual production guidance of 90-94,000 ounces.