Tungsten APT USD 19,500 / tonne (26

October 2016)

King Island Scheelite Limited (KIS)

through its 100% Dolphin Project on King Island, Tasmania is one of the world's richest tungsten deposits and could

meet a significant proportion of the world's tungsten requirements over a minimum 13 years.

King Island Scheelite Limited ABN 40 004 681 734

Level 26, 259 George Street Sydney NSW 2000

GPO Box 5154

Sydney NSW 2001 P. +61 2 8622 1400 F. +61 2 8622 1401

www.kingislandscheelite.com.au

Chairman

Director Director

Board of Directors

Johann Jacobs Allan Davies Chris Ellis

ASX: KIS

Market Capitalisation $8.1 million Shares on Issue 165.3 million

52 Week High 11.0 cents

52 Week Low 4.9 cents

Share Price 4.9 cents

Report for the Quarter Ended 30 September 2016

HIGHLIGHTS

  • Studies were completed during the Quarter to satisfy EPA requirements for the Revised Environmental Assessment Report

  • This final Environmental Assessment Report will be submitted to EPA in November 2016

  • Pumping of water out of the open cut void continues so as to maintain a consistent level in the sump

  • Tungsten markets remain depressed with limited potential for significant increase in prices

  • As a result of current tungsten market the Board is examining the potential of producing a lesser amount of concentrate at a lower grade - a "Start-up Option"

31 October 2016

King Island Scheelite (ASX: KIS)

Report for the Quarter Ended 30 September 2016

King Island Scheelite Limited (Company) is pleased to present its activity report for the quarter ended 30 September 2016.

Environmental Approvals

Additional studies, which include all up to date data, have now been completed and included within a Revised Environmental Assessment Report which will be submitted to the EPA for their review in November 2016. It is expected that amended EPA conditions, reflecting the revised mining operations will be issued early in 2017. These amended conditions will not impact upon the overall approval for the mine.

Definitive Feasibility Study ("DFS") and Start up Option

Work continued on the consolidation of recent studies into a Definitive Feasibility Study. This work can only be completed when the final environmental approvals have been obtained.

Following attendance at the annual International Tungsten Industry Association Annual General Meeting in Stockholm, in September, the Board has decided to examine the potential of staging the development of the Dolphin Mine commencing with a lower production profile producing a lower grade concentrate.

It is anticipated that the preliminary findings of this exercise will be completed within the current Quarter.

Pit Pumping

Consistent with our previous plans, the inflow of water from predominantly rain water runoff, is being managed with the installed smaller pump utilized on a regular basis to maintain a consistent water level in the sump. After a relatively dry second calendar quarter, heavy rains were experienced at Grassy from May through to September. Relatively continuous pumping was required to keep water levels in check.

APT Market

Ammonium Paratungstate prices (APT), the product used as a benchmark price for the sale of WO3concentrate, as it is regularly quoted in industry journals, fell to an 11 year low of $160-170/mtu in November last year -after having reached a high of $460-500/mtu in May 2011. Since then prices have been in decline before gradually rebounding to $215-225/mtu in May 2016. However, prices have slipped back, due to low levels of demand, to around $180-195/mtu in October 2016.

Although this price is above our anticipated production costs, financing the project - both debt and equity - would be extremely difficult and risky. The major impact on the market has been from the drop in specialty steel demand.

Finance

Cash Balance

As at 30 September 2016 the Company's cash balance was $1.95 million.

King Island Scheelite (ASX: KIS)

Report for the Quarter Ended 30 September 2016

KIS group activities have related to exploration, there have been no activities relating to production or development.

Tenement reference

Nature of interest

Mining tenements held at the end of the quarter

Exploration Licence EL 19/2001 at Grassy, King Island, TAS (91 sq kms)

100% ownership

Mining Lease Application MLA 1M/2006 at Grassy, King Island, TAS (544 hectares)

100% ownership

Mining tenements acquired during the quarter

Nil

Nil

Mining tenements relinquished during the quarter

Nil

Nil

Beneficial percentage interests held in farm- in or farm-out agreements at the end of the quarter

Nil

Nil

Beneficial percentage interests in farm-in or farm-out agreements acquired or disposed during the quarter

Nil

Nil

Following is a summary of the expenditure incurred on exploration activities during the quarter:

$'000

Dewatering

32

Project management

15

Mine planning & geological work

25

Environmental

17

Other Feasibility Study work 2

TOTAL 91

Johann Jacobs

Chairman

31 October 2016

King Island Scheelite Limited

Level 26, 259 George Street Sydney NSW 2000

Phone (02) 8622 1400

Fax (02) 8622 1401

Email info@kisltd.com.au

For further information go to the company's website www.kingislandscheelite.com.au

Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report

Appendix 5B

+Rule 5.5

Mining exploration entity and oil and gas exploration entity quarterly report

Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10, 01/05/13, 01/09/16

Name of entity

KING ISLAND SCHEELITE LIMITED

ABN Quarter ended ("current quarter")

40 004 681 734

30 September 2016

Consolidated statement of cash flows

Current quarter

$A'000

Year to date (3 months)

$A'000

1.

Cash flows from operating activities

-

-

1.1

Receipts from customers

1.2

Payments for

(a) exploration & evaluation

(91)

(91)

(b) development

-

-

(c) production

-

-

(d) staff costs

-

-

(e) administration and corporate costs

(256)

(256)

1.3

Dividends received (see note 3)

-

-

1.4

Interest received

4

4

1.5

Interest and other costs of finance paid

-

-

1.6

Income taxes paid

-

-

1.7

Research and development refunds

-

-

1.8

Other (provide details if material)

19

19

1.9

Net cash from / (used in) operating

(324)

(324)

activities

  1. Cash flows from investing activities

  2. Payments to acquire:

  3. property, plant and equipment

    (1) (1)

  4. tenements (see item 10) - -

  5. investments - -

  6. other non-current assets - -

  7. + See chapter 19 for defined terms

    1 September 2016 Page 1

King Island Scheelite Limited published this content on 31 October 2016 and is solely responsible for the information contained herein.
Distributed by Public, unedited and unaltered, on 02 November 2016 08:37:05 UTC.

Original documenthttp://www.kingislandscheelite.com.au/client-assets/1612653.pdf

Public permalinkhttp://www.publicnow.com/view/EB9077074AEC2BECAF2FD96051262827F86FE834